Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this 5-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.
Currently, construction is taking place in all reaches.
A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.
Reach 1 |
Reach Description: Reach 1 is the area along Construction Activity: Preliminary construction continues as third party utility relocations are taking place on Traffic Impacts: Current impacts to motorists should be minimal at this time; however, there will be minor lane restrictions as other utility companies work along |
Reach 2 |
Reach Description: Reach 2 is the area along 3100 South from Construction Activity: Off-road construction continues to take place along the south side of 3100 South just east of TRAFFIC IMPACTS: Current impacts to motorists should be minimal in this reach because the majority of work takes place along the south side of 3100 South |
Reach 3 |
Reach Description: Reach 3 is the area along Construction Activity: TRAX construction continues to take place on Crews in this area continue to install sewer lines and other utilities on the west side of Crews have also started to expose utilities along Traffic Impacts: One lane of traffic is operational in each direction on the west side of |
Reach 4 |
Reach Description: Reach 4 runs through the Construction Activity: The majority of construction taking place on the West Valley Line is currently taking place in this area. Construction in this reach is on the east side of Construction also continues east of Traffic Impacts: Motorists should be aware that The Crosstowne Trail along 2770 South just east of |
Reach 5 |
Reach Description: Reach 5 will include construction along 1070 West in the Construction Activity: Crews have started preliminary construction in this reach along 1070 West. They are currently “potholing” or exposing utilities in this area to determine their exact locations under the street. Crews have created a corridor for TRAX that extends from Reach 4 to connect with 1070 West in this reach. Traffic Impacts: Currently, any impacts to motorists should be minimal in this construction reach. |
Reach 6 |
Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents in this reach, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel will be maintained. Reach 6 will include an extensive bridging system that will enable TRAX to operate above ground, over other train traffic in this area. Construction Activity: Construction crews continue to pothole and install utilities in this reach. Traffic Impacts: Not applicable. This is a Union Pacific Railroad work area. |
Reach 7 |
Reach Description: Reach 7 is the area where the West Valley Line will connect with the current North/South TRAX Line. Construction in this reach will take place along Construction Activity: Crews have removed the old track along Traffic Impacts: Impacts to motorists should be minimal at this time. |
Reach 1 – Third party utility relocations are taking place on
Reach 3 - Crews continue to install sewer and utility lines along the west side of
Drive. Access is being maintained in this area.
Reach 4- Crews have started concrete reinforcements beginning at
Reach 6- Crews Continue to pothole and install utilities in this area extending through
General Information
Access during Construction
UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where temporary access might be required.
Construction Hours
Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.
Construction
If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.
For More Information
Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.
If you have further questions not answered by this report or any comments regarding the project, please contact toll-free 24-hour hotline at (888) 800-8854 or e-mail csaley@rideuta.com or thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.
Please note that construction information provided is subject to change.