Wednesday, August 27, 2008

Mid Jordan TRAX line construction update

Light railImage via Wikipedia

Mid-Jordan Light Rail TRAX Construction Update: August 27, 2008*

Please forward this information on to others that would be interested.

*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.

Sugar Factory Area

Activity: Construction of sound wall along right-of-way rail corridor between 2700 West and 3200 West will begin on September 2 and will continue through the end of the month.

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Old Bingham Area

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Gardner Village Area

Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.

Activity: The Jordan River Parkway Trail will be detoured near approximately 7500 South beginning in early September. More details regarding specific impacts will follow in a separate email update.

Activity: Construction on retaining walls at 7800 South near Gardner Village began on June 30th and will continue for approximately 2 months. Traffic Impacts: There will be a designated truck turning lane on the north side of 7800 South accessing the Gardner Village property. Flagging operations will be in place as trucks enter and exit the roadway. To accommodate this construction, the following closures will be in place:

· The eastbound lane on the south side of 7800 South will be closed as necessary starting on August 6th

· The westbound lane on the north side of 7800 South will be closed with flagging operations through September 5th

Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.

Cottonwood Area

Activity: Utility work will continue in the Cottonwood Street area through the month of August. Traffic Impacts: Possible lane restrictions.

Activity: Construction on Cottonwood Street will begin on September 2nd and will continue through mid-November. Traffic Impacts: Lane restrictions and closures as follows:

· Northbound travel on Cottonwood Street will be closed between Winchester Street and 6500 South for the duration of construction. Southbound travel will remain open and traffic will be shifted to the east side of the roadway while crews reconstruct the west side. Once construction on the west side is complete, traffic will be switched to the west side of the roadway to allow crews to reconstruct the east side.

· Cottonwood Street will accommodate southbound traffic only between Winchester Street and 6500 South. Please use 700 West or State Street as detour routes. Detour signs will be posted.

Activity: Utility work will take place at the intersection of 300 West and Winchester Street from 6 a.m. September 9th through 5 a.m.

September 11th. Traffic Impacts: The intersection will be closed during this time. Please follow detour routes as posted.

Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to Winchester Street, and closed to through traffic at 6100 South. Local business access will be available on 300 West between 6100 South and 6300 South.

If you have any question or concerns regarding the project, please let me know.

Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783