Mid-Jordan Light Rail TRAX Construction Update: November 26, 2008*
Please forward this information on to others that would be interested.
*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.
NEW Crews will not be working November 27th-November 30th for the Thanksgiving holiday. Traffic control will remain in place as needed for your safety.
Activity: Crews have removed the median barrier in the area of approximately 8700 South and
UPDATED Activity: Crews are performing work on the center pier of the new TRAX bridge in the area of the approximately 8700 South and
Sugar Factory Area
Activity: Construction of sound walls along rail corridor right-of-way between 2700 West and 3200 West began on October 6th and will continue through November with possible flagging operations near 8600 South and 3200 West.
Activity: Construction of sound walls along rail corridor right-of-way between approximately 2500 West and 2200 West began on November 17th.
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Old Bingham Area
UPDATED Activity: Crews are performing work beneath the
NEW Activity: Crews will be working on the at-grade crossing on Wasatch Meadows Drive at the railroad tracks. Traffic Impacts: Wasatch
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
UPDATED Activity: Crews are working on the new bridge construction at 7800 South near
Activity: Access to
Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.
Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.
NEW Activity: New railroad bridge construction over
UPDATED Activity: Construction on
Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to
If you have any questions or concerns regarding the project, please let me know.
Sarah Loughlin
Community Involvement Specialist
801-236-4783
You have been included on the Mid-Jordan Light Rail TRAX Construction Update project update email list. Each time the construction schedule is updated, you will receive an email notifying you of the update. If you would like to be removed from this list, simply send an email stating so.
3 comments:
Your blog is the best source of information on transit projects in the Salt Lake area. I have followed it for some time and I am impressed. I have a question for you. How will the mid Jordan line impact the Daybreak community once it is up and running? I would like to hear your opinion on it as I would like to write a post on it soon at my blog: Daybreak Today - http://daybreaktoday.blogspot.com
goyard
hermes birkin
jordan shoes
michael jordan shoes
nike air force 1
off white
kyrie 5 spongebob
nike max
balenciaga shoes
calvin klein outlet
n8p39i1k20 g5x19j0k35 r0s41d9j23 b3h76s3x71 u1t41o3b17 a9q38y5p82
Post a Comment