Friday, December 05, 2008

West Valley TRAX Update

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.

Currently, construction is taking place in all reaches.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.


Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.

Current Construction: In conjunction with construction on the bus rapid transit project on Market Street, the intersection at Market Street and Lehmann Avenue is closed for construction. Other work taking place in this area includes third party utility relocations along Constitution Boulevard and excavation and utility work near West Valley City Center.

Upcoming Construction: Construction is scheduled to begin on 2700 West from 3500 South to 3100 South in December. This work will mainly include utility relocations and will proceed along the side of the roadway. Impacts to motorists should be minimal. As we get closer to construction, we will meet with all residents in this area to discuss how to minimize impacts.

We want to thank the residents bordering Constitution Boulevard for working with us during the pre-construction phase of this project. As work progresses, we will keep in contact with them to help mitigate any issues that may arise.

Traffic Impacts: Current impacts to motorists should be minimal; however, there will be minor lane restrictions as utility companies work along Constitution Boulevard.

Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained throughout construction and we will work with The E Center to coordinate our efforts so you can continue to enjoy the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.

Current Construction: Construction has begun on the TRAX bridge over I-215 on the south side of 3100 South. The foundation work for this structure includes driving steel pile into the ground using a machine that may generate significant noise and vibration. To help alleviate impacts, pile driving activities will take place over the next few weeks and will be limited to the hours of 7:00 a.m. to 5:00 p.m. Monday through Friday.

Upcoming Construction: Construction will continue on the TRAX bridge over I-215 for the next several months. Utility work will also begin on 3100 South near The E Center and Decker Lake Drive during the first couple of weeks in January 2009.

Traffic Impacts: There will be some lane restrictions on I-215 as crews progress with bridge construction. We will work with the partnering agencies to notify travelling motorists about possible lane restrictions.

Reach 3

Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis. We will continually work with these businesses to ensure access is provided at all times.

Current Construction: Crews are currently working on a storm drain on the east side of Decker Lake Drive. A lot of progress has been made and traffic is expected to switch to the other side of the street sometime in January 2009. Access is being maintained in this area and we thank the businesses and motorists for their support during construction.

Upcoming Construction: Construction is anticipated to take place along Decker Lake Drive throughout the next several months.

Traffic Impacts: Access to businesses is being maintained. Traffic is anticipated to switch again from the west side of Decker Lake Drive to the east side sometime in January 2009.

Please be mindful of workers in this area and obey posted speed limits.

Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties throughout construction.

Current Construction: The majority of construction on the West Valley Line has taken place in this reach on the east side of Redwood Road. Crews are now installing a permanent wall along both sides of the Crosstowne Trail. Significant drainage and irrigation work has been accomplished in this reach as well as foundation work for TRAX’s overhead wiring system. A permanent fence has been installed just east of the Brighton Canal to the Khadeeja Islamic Center on Parkway Avenue.

Upcoming Construction: Sound wall installation in the Chesterfield neighborhood is anticipated to take place over the next couple of months.

Traffic Impacts:

· The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will once again be operational.

Reach 5

Reach Description: Reach 5 will include construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.

Current Construction: The majority of construction is taking place on 1070 West just north of Parkway Avenue, involving mainly third party utility work. There will be some lane restrictions implemented at this time. A joint trench for utilities and sewer line work is also taking place along 1070 West, in addition to pile driving for a retaining wall.

Traffic Impacts: As construction proceeds, there will be some lane restrictions, although we will maintain access in this area at all times.

Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents in this reach, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel will be maintained. Reach 6 will include an extensive bridging system that will enable TRAX to operate above ground, over other train traffic.

Current Construction: Crews have installed steel piles 120’ into the ground to form the main foundations for the aerial bridge that will carry TRAX over the Union Pacific Railroad tracks. These steel piles are welded together and then pounded into the earth until they reach bedrock and form the bases of the bridge structure. Crews have started to prepare a base course for TRAX.

Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.

Traffic Impacts: Not applicable. This is a Union Pacific Railroad work area.

Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current North/South TRAX Line. Construction in this reach will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses in this reach to ensure access is maintained at all times. A construction survey has been conducted with the businesses along 400 West between Andy Avenue and 2100 South to determine the best time to construct in the Andy Avenue/600 West intersection. We will get back to businesses to deliver the survey results and ensure adequate access.

Current Construction: Storm drain installation along Andy Avenue has been completed. We thank the businesses for their support during construction.

Upcoming Construction: The next phase of construction will begin near Andy Avenue in the Spring. We will continue to work with businesses to maintain access and mitigate any issues that may arise.

Traffic Impacts: Access will be maintained at all times during construction in this area

General Information

Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where temporary access might be required.

Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. In addition, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.

Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.

For More Information

Timely and helpful information is available to assist businesses and residential communities as well as commuters and stakeholders.

If you have further questions not answered by this report or any comments regarding the project, please contact toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.

Please note that construction information provided is subject to change.



Reblog this post [with Zemanta]

No comments: