Wednesday, November 05, 2008

Front Runner South Construction Update

Sounder Commuter Rail at King Street Station, ...Image via Wikipedia

Greetings,

Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line. Below is the FrontRunner South quick construction

update for the week of November 2. For a more comprehensive construction update, click here.

Area 16 — Downtown Salt Lake City to 4500 South (Murray)

Construction Activity:

A lot of progress has been made with fiber optic relation in Area 16 between Murray and Salt Lake City along the eventual FrontRunner trackway.

Traffic Impacts:

There are currently no traffic impacts in this area.

Salt Lake Central Station:

Station complete.

Area 15 — 4500 South (Murray) to 7800 South (Midvale)

Construction Activity:

Fiber optic relocation also continues throughout Area 15.

Traffic Impacts:

None.

Murray-5300 South Station:

No station construction activities to report.

Area 14 — 7800 South (Midvale) to Bangerter Highway (Draper/Bluffdale)

Construction Activity:

Construction is gearing up in Area 14. On Sunday, October 19th, a crane was set up at the track crossover near 144th South and the Union Pacific Railroad. A construction fence has also been installed behind Salt Lake Community College’s campus at 9800 South in anticipation for work on a flyover bridge to be built in this area.

Crews will begin driving steel pile into the ground for the flyover that will be constructed near Salt Lake Community College. This work is scheduled to take place beginning next week.

Traffic Impacts:

There are no traffic impacts to report at this timel.

South Jordan/Sandy Station:

No station construction activities to report.

Area 13 — Bangerter Highway (Draper/Bluffdale) to Thanksgiving Point (Lehi)

Construction Activity:

Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi and throughout the Jordan Narrows. Work on the South Jordan Canal will begin next week in this area as well as embankment improvements.

Traffic Impacts:

Impacts to motorists should be minimal as work proceeds along the railroad right-of-way.

Draper/Bluffdale Station:

No station construction activities to report.

Lehi Station:

No station construction activities to report.

Area 12 — Thanksgiving Point (Lehi) to Main Street (American Fork)

Construction Activity:

Extensive excavation work has taken place at the Lehi Park and Ride Lot near Thanksgiving Point as crews continue to clear and grub the area and begin drainage improvements. Construction is also taking place along the rail corridor in this area just south of 11000 North in Lehi.

Crews are also beginning to construct a pedestrian tunnel underneath the Union Pacific trackway that leads to the eventual park and ride lot at Thanksgiving Point.

Traffic Impacts:

There are currently no impacts to motorists in this area.

American Fork-Main St. Station:

A temporary entrance has been established at this station so work can proceed.

Area 11 — Main Street (American Fork) to 800 South (Orem)

Construction Activity:

Drainage improvements are currently taking place along the Union Pacific Railroad tracks from Orem to American Fork.

Traffic Impacts:

There are currently no impacts to motorists in this area.

Orem Station:

No station construction activities to report.

Area 10 — 800 South (Orem) to Center Street (Provo)

Construction Activity:

A lot of progress is being made in Area 10 along the Union Pacific Railroad corridor between University Parkway in Orem and West Center Street in Provo. Crews continue to prepare a path for FrontRunner by grading and clearing the right-of-way and relocating water lines. Since an additional track is being constructed for FrontRunner to operate on, any existing box culvert or waterway must be extended under the newly built trackway. Existing signal poles located in the right-of-way have also been removed in this area.

Crews have removed old railroad ties and rail all the way from 500 West in Provo to University Parkway in Orem. Old materials removed from this area are either reused or recycled.

Traffic Impacts:

Impacts to motorists are currently anticipated to be minimal as most work in this area is taking place along the rail corridor.

Provo Station-University Ave. Station:

No station construction activities to report.

Hobble Creek Wetlands Project — Springville, Utah

Description:

Although FrontRunner’s terminus is located in Provo, crews have nearly finished construction on a floodplain south of Provo in Springville, Utah, to offset wetlands impacts related to building commuter rail in Utah County. In cooperation with the June Sucker Recovery Implementation Program and other agencies, this project will be constructed adjacent to a new Hobble Creek channel which is a tributary to Utah Lake and will replace major wetlands functions and vegetation and provide a protected nursery habitat for newly hatched June sucker fish. For more information on this wetlands project, please visit UTA’s Web site at www.riduta.com. Click on the Programs tab and then Projects. Additional information can also be found at www.junesuckerrecovery.org.

Construction Activity:

Construction on this 21-acre site located between I -15 and Utah Lake in Springville, Utah, is nearly completed. Crews have accomplished extensive excavation of the site to prepare a stream for the eventual release of the endangered June Sucker fish. The stream located to the north of this site is anticipated to be cutover the last week of October 2008.

.

Traffic Impacts:

None.

Ribbon Cutting Event:

On November 12, 2008, the June Sucker Recovery Implementation Program will host a ribbon cutting event to celebrate the completion of the Hobble Creek Wetlands Project.

Hobble Creek Wetlands Project – Landscaping is taking place throughout the Hobble Creek Project

General Construction Information

Access during Construction

UTA is committed to maintaining access to all of the businesses and residences along the construction corridor.

Construction Hours

Construction on the project is permitted to take place between 7 a.m. and 7 p.m. Monday through Saturday each week.

Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials

Thanks again for your interest in the FrontRunner South project. If you have construction related questions, please

call our 24-hour construction hotline number at 1-888-800-8854. If you have specific questions about the

FrontRunner South project, my contact information is listed below. To unsubscribe to this list, please click here.

Regards,

--
Marc Bowman
UTA Community Involvement Specialist
www.rideuta.com
801.236.4784
801.867.4573 (mobile)

Reblog this post [with Zemanta]

No comments: