Greetings,
Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line. Below is the FrontRunner South quick construction
update for the week of November 2. For a more comprehensive construction update, click here.
Area 16 — Downtown |
Construction Activity: A lot of progress has been made with fiber optic relation in Area 16 between Traffic Impacts: There are currently no traffic impacts in this area. Station complete. |
Area 15 — 4500 South (Murray) to 7800 South (Midvale) |
Construction Activity: Fiber optic relocation also continues throughout Area 15. Traffic Impacts: None. Murray-5300 South Station: No station construction activities to report. |
Area 14 — 7800 South (Midvale) to |
Construction Activity: Construction is gearing up in Area 14. On Sunday, October 19th, a crane was set up at the track crossover near 144th South and the Union Pacific Railroad. A construction fence has also been installed behind Crews will begin driving steel pile into the ground for the flyover that will be constructed near Traffic Impacts: There are no traffic impacts to report at this timel. South Jordan/Sandy Station: No station construction activities to report. |
Area 13 — |
Construction Activity: Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi and throughout the Traffic Impacts: Impacts to motorists should be minimal as work proceeds along the railroad right-of-way. Draper/Bluffdale Station: No station construction activities to report. Lehi Station: No station construction activities to report. |
Area 12 — Thanksgiving Point (Lehi) to |
Construction Activity: Extensive excavation work has taken place at the Crews are also beginning to construct a pedestrian tunnel underneath the Union Pacific trackway that leads to the eventual park and ride lot at Thanksgiving Point. Traffic Impacts: There are currently no impacts to motorists in this area. American Fork-Main St. Station: A temporary entrance has been established at this station so work can proceed. |
Area 11 — Main Street (American Fork) to 800 South ( |
Construction Activity: Drainage improvements are currently taking place along the Union Pacific Railroad tracks from Traffic Impacts: There are currently no impacts to motorists in this area. No station construction activities to report. |
Area 10 — 800 South ( |
Construction Activity: A lot of progress is being made in Area 10 along the Union Pacific Railroad corridor between Crews have removed old railroad ties and rail all the way from 500 West in Traffic Impacts: Impacts to motorists are currently anticipated to be minimal as most work in this area is taking place along the rail corridor. No station construction activities to report. |
Hobble Creek Wetlands Project — |
Description: Although FrontRunner’s terminus is located in Construction Activity: Construction on this 21-acre site located between I -15 and . Traffic Impacts: None. Ribbon Cutting Event: On November 12, 2008, the June Sucker Recovery Implementation Program will host a ribbon cutting event to celebrate the completion of the Hobble Creek Wetlands Project. |
Hobble Creek Wetlands Project – Landscaping is taking place throughout the Hobble Creek Project
General Construction Information
Access during Construction
UTA is committed to maintaining access to all of the businesses and residences along the construction corridor.
Construction Hours
Construction on the project is permitted to take place between 7 a.m. and 7 p.m. Monday through Saturday each week.
Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials
Thanks again for your interest in the FrontRunner South project. If you have construction related questions, please
call our 24-hour construction hotline number at 1-888-800-8854. If you have specific questions about the
FrontRunner South project, my contact information is listed below. To unsubscribe to this list, please click here.
Regards,
--
Marc Bowman
UTA Community Involvement Specialist
www.rideuta.com
801.236.4784
801.867.4573 (mobile)
No comments:
Post a Comment