Wednesday, November 05, 2008

Mid Jordan TRAX line construction update

:en:TriMet :en:MAX Yellow Line tram on opening...Image via Wikipedia

Mid-Jordan Light Rail TRAX Construction Update: November 5, 2008*

Please forward this information on to others that would be interested.

*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.

Progress Highlight: Daybreak

Construction continues on the Mid-Jordan LRT line, and crews have been hard at work in the Daybreak area. All underground work at the two Daybreak Park and Rides has been completed, and paving is anticipated to be completed this week.

Bangerter Bridge

Activity: Crews have removed the median barrier in the area of approximately 8700 South and Bangerter Highway (just south of the Old Bingham Highway overpass). The median has been replaced with water barrels and remains closed through December.

Sugar Factory Area

Activity: Construction of sound wall along right-of-way rail corridor between 2700 West and 3200 West will begin on October 6th and will continue through November.

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Old Bingham Area

Activity: Crews will be installing new railway track and performing roadway reconstruction at 4800 West between Old Bingham Highway and Sunny Meadow Drive. Traffic Impacts: Beginning at 7:00 a.m. on Monday, November 10, 4800 West will be closed at the trackway until 5:00 p.m. on Monday, November 17th. Please use Wasatch Meadows Drive as a detour. Signs will be posted.

Activity: Crews will be removing a median barrier beneath the Old Bingham Highway Bridge. Traffic Impacts: From October 20th through November 8nd, Old Bingham Highway will have one lane open with flagging operations at the Bangerter overcrossing.

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Gardner Village Area

Activity: Crews are working on the new bridge construction at 7800 South near Gardner Village. Traffic Impacts: Westbound traffic will be shifted to the south side of the roadway at the railroad overcrossing with flagging operations at Gardner Village entrances through November 8. Westbound traffic will be shifted to the north side of the roadway beginning November 10th through November 14th.

Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.

Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.

Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.

Cottonwood Area

Activity: Construction on Cottonwood Street will begin on September 2nd and will continue through mid-November. Traffic Impacts: Lane restrictions and closures as follows:

· Northbound travel on Cottonwood Street will be closed between Winchester Street and 6500 South for the duration of construction. Southbound travel will remain open and traffic will be shifted to the east side of the roadway while crews reconstruct the west side. Once construction on the west side is complete, traffic will be switched to the west side of the roadway to allow crews to reconstruct the east side.

· Cottonwood Street will accommodate southbound traffic only between Winchester Street and 6500 South. Please use 700 West or State Street as detour routes. Detour signs will be posted.

Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to Winchester Street, and closed to through traffic at 6100 South. Local business access will be available on 300 West between 6100 South and 6300 South.

If you have any questions or concerns regarding the project, please let me know.

Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783

sloughlin@rideuta.com