Tuesday, March 31, 2009

Front Runner South Construction Update

Greetings,



Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line.

Below is the FrontRunner South construction update for March 30 – April 5.

To learn more about the FrontRunner South project, click here .



Area 16 — Downtown Salt Lake City to 4500 South (Murray)



Construction Activity:

Crews will continue construction on a cut wall at 3900 South in South Salt Lake. Also, utility crews will be splicing fiber optics throughout the area.



Traffic Impacts:

There are currently no traffic impacts in this area.



Salt Lake Central Station:

Station complete.





Area 15 — 4500 South (Murray) to 7800 South (Midvale)



Construction Activity:

Crews will be splicing fiber optics throughout the area this week.



Traffic Impacts:

There are currently no impacts to motorists in this area.



Murray-5300 South Station:

No station construction activities to report.





Area 14 — 7800 South (Midvale) to Bangerter Highway (Draper/Bluffdale)



Construction Activity:

Progress continues in Area 14 behind Salt Lake Community College’s campus at 9800 South as crews construct a bridge that flies over the Union Pacific Railroad tracks. This is the area where FrontRunner will move from the east side to the west side of the tracks. Crews will be erecting shoring for the flyover bridge and begin excavation work and wick drain installation for a wall that will be constructed near the bridge.



Crews will also be installing micro-fiber and splicing fiber optics throughout the area this week.



Traffic Impacts:

There are currently no impacts to motorists in this area.



South Jordan/Sandy Station:

No station construction activities to report.





Area 13 — Bangerter Highway (Draper/Bluffdale) to Thanksgiving Point
(Lehi)



Construction Activity:

Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi. Excavation and embankment work throughout the area will continue this week and crews will also be installing micro-fiber and splicing fiber optics.



Crews will continue work on the South Jordan Canal channel, install sheet pile for the East Jordan Canal bridge and drive pile for an abutment of the future Jordan River bridge.



Traffic Impacts:

There are currently no impacts to motorists in this area.



Draper/Bluffdale Station:

No station construction activities to report.







Area 12 — Thanksgiving Point (Lehi) to Main Street (American Fork)



Construction Activity:

Cleanup work will take place at the pedestrian tunnel that will run underneath the Union Pacific trackway at the Lehi Station. Crews will continue excavation and embankment work for the new Union Pacific Railroad Siding on the west side of the corridor near the Lehi station.



Utility work will take place throughout the area as crews install micro-fiber, splice fiber optics, relocate power and extend water line casings.



Traffic Impacts:

There will be several sets of flaggers stationed along Garden Drive this week to support utility and excavation work and help direct truck traffic near the corridor.



Lehi Station:

No station construction activities to report.







Area 11 — Main Street (American Fork) to 800 South (Orem)



Construction Activity:

Trackway embankment work has begun in American Fork and near the Orem Park and Ride Lot. Crews will also be splicing fiber optics throughout the area this week.



Traffic Impacts:

Flaggers will be directing traffic at Main Street and Millpond Road in American Fork on Wednesday while crews conduct asphalt work.



In addition, flaggers will be stationed all week at 6400 North in American Fork to direct truck traffic leaving the corridor and near Vineyard Road and 250 West in Orem to direct truck traffic entering the corridor.



American Fork-Main St. Station:

No station construction activities to report.



Orem Station:

No station construction activities to report.





Area 10 — 800 South (Orem) to Center Street (Provo) Construction Activity:

Significant progress has been made in Area 10 along the Union Pacific Railroad corridor between University Parkway in Orem and West Center Street in Provo. Crews have prepared a path for FrontRunner by grading and clearing the right-of-way and relocating water lines.



Crews will be installing micro-fiber and splicing fiber optics throughout the area this week.



Traffic Impacts:

There are currently no impacts to motorists in this area.



Provo Station-University Ave. Station:

No station construction activities to report.

Friday, March 27, 2009

West Valley TRAX Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. This five-mile project has been separated into seven construction “reaches,”
or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.







Currently, construction is taking place in all reaches.



A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.






Reach 1



Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.



Current Construction: TRAX construction is taking place in conjunction with UTA’s bus rapid transit project on Market Street. Crews are currently working on the station platform in between West Valley City Hall and the Public Safety Building. Pedestrian access has been changed to accommodate paving for the Public Safety Building parking lot. To access the Public Safety Building and West Valley City Justice Courts, please go through the West Valley City Hall main lobby.



Signals are also being placed along Constitution Boulevard and work is taking place on the east side of the street. We appreciate the travelling public’s patience during this phase of construction.



Crews continue to replace the storm drain from 3500 South to 3100 South on Constitution Boulevard for the next couple of weeks. Access will be maintained during this construction.



Upcoming Construction: Work is scheduled to take place in the intersection at 3500 South and Constitution Boulevard in April. More details will be provided as they become available.



Traffic Impacts: 3360 South at Constitution Boulevard will close for one day on Saturday, March 28th to accommodate utility work. The intersection will close early Saturday morning and will open again around 5 p.m. the same day. Motorists are encouraged to detour at Maple Way and 3100 South during this temporary closure. Thank you for your patience.



Reach 2



Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained throughout construction and we will work with the E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.



Current Construction: Progress has been made on the TRAX bridge over
I-215 on the south side of 3100 South. Crews have now moved the crane from the west side to the east side of I-215.



Crews are in the process of dewatering and storm water installation on the south side of 3100 South near the E Center.



Upcoming Construction: The sidewalk on the south side of 3100 South over the I-215 bridge will close next week to accommodate bridge construction. Pedestrians will have to use the north sidewalk over I-215, which can be accessed at 2700 West and also at Decker Lake Drive.



Traffic Impacts: There will be some lane restrictions on I-215 as crews progress with bridge construction.



Reach 3



Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis.



Current Construction: The west side of Decker Lake Drive is open and access is being maintained. Crews have started work on the storm drain on the east side of the road.



Upcoming Construction: Construction is anticipated to take place along Decker Lake Drive throughout the next several months.



Traffic Impacts: Access to businesses is being maintained. Please be mindful of workers and obey posted speed limits.



Reach 4



Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties throughout construction.



Current Construction: Crews have installed a permanent wall along both sides of the Crosstowne Trail in Chesterfield. Significant drainage and irrigation work has also been accomplished, along with foundation work for TRAX’s overhead wiring system. We would like to thank the residents for their patience during construction.



Upcoming Construction: As weather improves, crews will backfill the area along the new fence on each resident’s property.



Traffic Impacts:

The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will open again.











Reach 5



Reach Description: Reach 5 will include construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.



Current Construction: The majority of construction is taking place on
1070 West just north of Parkway Avenue with third party utility work.
Currently there are lane restrictions as crews work on utilities and a retaining wall. Access is being maintained and we appreciate the businesses’ patience as work take place along 1070 West.



Pile driving for the new bridge structure at 900 West is currently underway.



Upcoming Construction: Construction is anticipated to take place for the next several months.



Traffic Impacts: As construction proceeds, there will be lane restrictions, although access will be maintained.







Reach 6



Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel is maintained.
Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction: Progress has been made on the overhead structure in roper yard. Crews have installed steel piles 120’ into the ground to form the main foundations for the aerial bridge that will carry TRAX over the Union Pacific Railroad tracks. Crews are now installing geofoam to form the basis of the bridge structure over the Roper Yard area.



Construction is also proceeding just east of 900 West along the south side of SR 201.



Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.



Traffic Impacts: Not applicable. This is a Union Pacific Railroad work area.










Reach 7



Reach Description: Reach 7 is the area where the West Valley Line will connect with the current North/South TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction: Storm drain installation along Andy Avenue has been completed. We thank businesses for their support during this phase of construction.



Upcoming Construction: The next phase of construction will begin near Andy Avenue next spring. We will continue to work with businesses to maintain access and mitigate any issues that may arise.



Traffic Impacts: Access will be maintained during construction.


General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to
7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.



If you have further questions not answered by this report or any comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com .



Please note that construction information provided is subject to change.



Reblog this post [with Zemanta]

Airport TRAX line construction update

UTA TRAX Sandy train at the Gallivan Plaza sto...Image via Wikipedia

March 27, 2009



Welcome!



Construction has begun on the UTA Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

airportNODATES

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (800) 888-8854.





Reach 1



Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of North Temple Drive to the surplus canal bridge just north of the Wingpointe Golf Course.



Upcoming Construction: Heavier construction is anticipated during Summer 2009.



Traffic Impacts: Access will be maintained throughout the construction project.





Reach 2



Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course near the Salt Lake City International Airport along the fence line on North Temple Drive to 2400 West.



Upcoming Construction: Heavier construction is anticipated Fall 2009.



Traffic Impacts: Currently there are no traffic impacts.





Reach 3



Reach Description: Reach 3 extends from 2400 West along North Temple Drive to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction: Currently utility work is taking place in the center of North Temple on either side of the I-215 overpass. West bound traffic west of 1-215 has been diverted to Old North Temple down to 2200 West for the next two weeks. Access to all businesses will be maintained and flaggers will be on site to direct traffic. Utility work is scheduled at the 2200 West and North Temple intersection for approximately two weeks beginning mid-April.



Upcoming Construction: Heavy construction will begin during Spring 2009.



Traffic Impacts: There are lane restrictions near the I-215 overpass on North Temple, but access is being maintained.





Reach 4



Reach Description: Reach 4 extends from I-215 to just past Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West North Temple. Access to the many businesses and governmental organizations will be maintained.



Current Construction: Utility work extends just east of the I-215 overpass on North Temple. Heavier construction is not anticipated until later this fall.



Upcoming Construction:

· Preliminary utility work is scheduled for the Redwood Road and
North Temple intersection for approximately two weeks beginning the second week of April. More details will be provided. There will be lane restrictions, but traffic will be maintained at all times. Heavier construction is anticipated to begin Fall 2009.



Traffic Impacts: Currently there are no traffic impacts.





Reach 5



Reach Description: Reach 5 extends from Redwood Road to the Jordan River. TRAX will be center running and includes a station at 1500 West.
Access to the many businesses and office complexes will be maintained.



Upcoming Construction: Construction is anticipated to begin Autumn 2009.



Traffic Impacts: Currently there are not traffic impacts.





Reach 6



Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1500 West and 1100 West. Access to the many businesses and the State Fairpark will be maintained.



Current Construction: Preliminary utility work is currently taking place at approximately 641 West North Temple. This work is scheduled for approximately two weeks.



Upcoming Construction:

After the utility work is completed at 641 West, preliminary work is expected to begin for approximately two weeks at 900 West. Heavy construction is anticipated during Spring 2010.



Traffic Impacts: There are lane restrictions on North Temple that extend from 800 West to just east of 600 West. Access is being maintained throughout this area. We appreciate the businesses and public’s patience during this work.





Reach 7



Reach Description: Reach 7 is the area where the Airport Line will connect with the current North/South TRAX Line at the Arena Station.
This reach extends from I-15 to 400 West along North Temple. Access to offices and the Gateway will be maintained throughout the construction project.



Current Construction: Crews in will be potholing for utilities throughout the next week.



Upcoming Construction: Heavy construction is anticipated to begin during Summer 2010.



Traffic Impacts: There are currently no traffic impacts.

Reach 6 – Access is being maintained to businesses near 800 West where preliminary utility work is taking place.

Reach 3 – Work continues on North Temple near I-215 as crews relocated a water line from the center to the side of the street.

Reach 7 – Crews continue

“potholing” or excavating utilities along North Temple to determine exact locations.

General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com . You can also visit UTA’s Web site at www.rideuta.com .



Please note that construction information provided is subject to change.





Reblog this post [with Zemanta]

Thursday, March 26, 2009

Mid Jordan TRAX line construction update

San Diego Trolley Green Line, westbound, appro...Image via Wikipedia

Mid-Jordan Light Rail TRAX Construction Update: March 26, 2009*

Please forward this information on to others that would be interested.

*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.

Bangerter Bridge

Activity: Crews have removed the median barrier in the area of approximately 8700 South and Bangerter Highway (just south of the Old Bingham Highway overpass). The median has been replaced with water barrels and will remain closed through April.

Sugar Factory Area

NEW Activity: Crews will be performing utility investigation work along Redwood Road. Traffic Impacts: Two right-hand northbound lanes will be closed beginning April 6th through 10th. The following week, the two right-hand southbound lanes will be closed from April 13th through 17th.

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Old Bingham Area

NEW Activity: Crews will be working on the rail crossing on 9000 South between 4000 West and approximately 4400 West. Traffic Impacts: Traffic is restricted to one lane in each direction on the north side of 9000 South until April 1st. Crews will then move work to the opposite side of the road, and traffic will be shifted to one lane in each direction on the south side of the road beginning April 2nd; 9000 South is anticipated to fully re-open on Wednesday, April 8th. To accommodate construction, access to and from Old Bingham Highway at 9000 South will be closed beginning on March 25th. Old Bingham Highway will remain accessible from 4800 West.

Activity: Eastbound shoulder closure on Old Bingham Highway west of Bangerter Highway through April.

Gardner Village Area

UPDATED Activity: Crews will be resuming work on the bridge at 7800 South near Gardner Village. Traffic Impacts: Eastbound traffic has been shifted to the north side of 7800 South until April 19th.

Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.

Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th, 2008 on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.

Cottonwood Area

Activity: Crews are working on the bridge abutments on the bridge at Winchester Street. Traffic Impacts: Traffic is subject to intermittent periods one lane configurations with flagging operations on the following days: March 26th, 30th and 31st. Please plan accordingly.

Activity: Crews are continuing access and utility work near 300 West and the intersection of Winchester Street and Cottonwood Street. Traffic Impacts: Shoulder work with lane restrictions.

If you have any questions or concerns regarding the project, please let me know.

Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783

sloughlin@rideuta.com

Reblog this post [with Zemanta]

Friday, March 20, 2009

Mid Jordan TRAX line construction update

{{de|Gleis mit Holzschwellen im Schotterbett}}...Image via Wikipedia

Mid-Jordan Light Rail TRAX Construction Update: March 18, 2009*

Please forward this information on to others that would be interested.

*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.

*** 9000 South Grade Crossing Work ***

Crews will be starting work on the 9000 South grade crossing beginning on March 25th. This work will require a partial closure of 9000th south at the railway tracks (approximately 4100 West to 4300 West), with some periods of full closure necessary for rail placement. More details will be e-mailed in a separate e-mail as they become available; please watch your mailbox for more information and contact the project team if you have questions or concerns.

Bangerter Bridge

NEW Activity: Crews will be working on the bridge structure on Bangerter Highway at approximately 8700 South. Traffic Impacts: The centermost north and south lane will be closed on Friday, March 20th.

Activity: Crews have removed the median barrier in the area of approximately 8700 South and Bangerter Highway (just south of the Old Bingham Highway overpass). The median has been replaced with water barrels and will remain closed through April.

Sugar Factory Area

NEW Activity: Survey crews will be working in the area. Impacts: Spot impacts in the area of Redwood Road and approximately 8100 South to accommodate survey crews on Thursday, March 19th. Please expect minor impacts.

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Old Bingham Area

No traffic impacts are expected.

Gardner Village Area

UPDATED Activity: Crews will be working above and around the trackway (approximately 7400 South) and 700 West. Traffic Impacts: One southbound lane will be closed on March 18th and 19th. The shoulder of 700 West is also subject to closure. Please plan accordingly.

UPDATED Activity: Crews will be resuming work on the bridge at 7800 South near Gardner Village. Traffic Impacts: Westbound traffic has been shifted to the south side of 7800 South until March 21st.

Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.

Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th, 2008 on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.

Cottonwood Area

Activity: Crews are working on the bridge abutments on the bridge at Winchester Street. Traffic Impacts: Traffic is subject to intermittent periods one lane configurations with flagging operations on the following days: March 18th, 25th-26th and 30th-31st. Please plan accordingly.

Activity: Crews are continuing access and utility work near 300 West and the intersection of Winchester Street and Cottonwood Street. Traffic Impacts: Shoulder work with lane restrictions.

If you have any questions or concerns regarding the project, please let me know.

Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783

sloughlin@rideuta.com

Reblog this post [with Zemanta]

Thursday, March 19, 2009

Blog Postings that May Interest You.T

The Karen-Blixen-Parc in the new suburb Øresta...Image via Wikipedia

From the Carless Parenting Blog:

The Trolley Option?

Always Room for Improvement.

Interesting note that the focus group about UTA required that you had a car.

From the Transport Polictic Blog:

Paris Announces Biggest Rapid Transit Investment Since RER

Paris is looking at a circular transit line to improve suburb to suburb commuting.

From Streetsblog San Francisco:

DOT and HUD Team Up for TOD

DOT and HUD: Transportation and Land-Use Planning Should Prioritize TOD

Streetfilms: Tap Foot, Lights Blink, Cross Street

Stim-Funded Highways to Nowhere

AC Transit Board Votes to Raise Fares

The True Cost of Moving to Cheaper Suburban Housing

From the Daybreak Today Blog:

Daybreak Place: Apartments in Daybreak, Utah

From the Mobilizing the Region Blog:

Back to the Future: U.S. Transit Use Hit 50-Year High in 2008

From the Transit Miami Blog:

Action Alert

Taken For A Ride

From Streetsblog LA:

L.A.’s “Congestion Pricing” Gaining National Attention

Fatal Newport Beach Sports Car Crash Highlights Lawlessness of Car Culture

Wiki Wednesday: Zürich, Where Transit Gets Priority on the Street

LaHood to Bike Advocates: U.S. DOT Will Be Your “Full Partner”

From the Sprawled Out Blog:

UPDATED - Franklin's default setting: Bikes and pedestrians be damned - Go big, go wide, go fast

The Last Shopping Mall? New Jersey Awaits Xanadu - TIME







Reblog this post [with Zemanta]

Articles

Trams in Frankfurt, GermanyImage via Wikipedia

Here is a bunch of articles from the last week.

Salt Lake City plans for bicycle transit station

Bikestation to assist Davis commuters

Plan for reversible lanes getting mixed reviews

Public comment sought on routes

Bountiful seeks ‘streetcar named desire’

Bills address roads, rails, ruins


Streetcar plan gets reviewed

Proposal Still Needs Final Approval



Reblog this post [with Zemanta]

Wednesday, March 18, 2009

Front Runner South Construction Update

The new commuter train arrives at last.Image by jotor via Flickr

Greetings,



Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line.

Below is the FrontRunner South construction update for March 17 – 22.

To learn more about the FrontRunner South project, click here .



Area 16 — Downtown Salt Lake City to 4500 South (Murray)



Construction Activity:

Crews will continue excavation and construction on a cut wall at 3900 South in South Salt Lake. Also, utility crews will be splicing fiber optics throughout the area.



Traffic Impacts:

There are currently no traffic impacts in this area.



Salt Lake Central Station:

Station complete.





Area 15 — 4500 South (Murray) to 7800 South (Midvale)



Construction Activity:

Crews will be splicing fiber optics throughout the area this week.



Traffic Impacts:

There are currently no impacts to motorists in this area.



Murray-5300 South Station:

No station construction activities to report.





Area 14 — 7800 South (Midvale) to Bangerter Highway (Draper/Bluffdale)



Construction Activity:

Progress continues in Area 14 behind Salt Lake Community College’s campus at 9800 South as crews construct a bridge that flies over the Union Pacific Railroad tracks. This is the area where FrontRunner will move from the east side to the west side of the tracks. Crews will continue work on three of the bridge piers this week.



The substructure construction is now complete on the bridge adjacent to the current Union Pacific Railroad bridge over 144th South. The temporary traffic light has been removed and replaced with stop signs near their original locations at the bridge.





Crews will install micro-fiber and micro-duct as well as begin splicing fiber optics throughout the area.



Traffic Impacts:



There will be flaggers in the area of 104th South and Jordan Gateway helping to direct truck traffic entering the corridor near the South Jordan/Sandy Station park and ride lot.



South Jordan/Sandy Station:

No station construction activities to report.





Area 13 — Bangerter Highway (Draper/Bluffdale) to Thanksgiving Point
(Lehi)



Construction Activity:

Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi. Excavation and embankment work throughout the area will continue this week and crews will also be installing micro-fiber and splicing fiber optics.



Crews will install a trash rack on the South Jordan Canal channel, install shoring, clay liner and rip rap near the East Jordan Canal bridge and install a temporary bridge over the Jordan River to support construction in the area.



Traffic Impacts:

There may be a partial lane closure along Garden Drive this week as crews work on extending water pipe casings and relocating water lines near the corridor. If there is a lane closure, flaggers will be in the area to direct traffic.



Draper/Bluffdale Station:

No station construction activities to report.







Area 12 — Thanksgiving Point (Lehi) to Main Street (American Fork)



Construction Activity:

Crews will backfill the pedestrian tunnel that will run underneath the Union Pacific trackway at the Lehi Station and construct a retaining wall. They will also continue excavation and embankment work for the new Union Pacific Railroad Siding on the west side of the corridor near the Lehi station.



Utility work will take place throughout the area as crews install micro-duct and micro-fiber and splice fiber optics.



Traffic Impacts:

There may be a partial lane closure along Garden Drive this week as crews work on extending water pipe casings and relocating water lines near the corridor. If there is a lane closure, flaggers will be in the area to direct traffic.



Lehi Station:

No station construction activities to report.







Area 11 — Main Street (American Fork) to 800 South (Orem)



Construction Activity:

Trackway embankment work has begun in American Fork. Crews will also be installing micro-duct and splicing fiber optics throughout the area this week.



Traffic Impacts:

There are currently no impacts to motorists in this area.



American Fork-Main St. Station:

No station construction activities to report.



Orem Station:

No station construction activities to report.





Area 10 — 800 South (Orem) to Center Street (Provo) Construction Activity:

Significant progress has been made in Area 10 along the Union Pacific Railroad corridor between University Parkway in Orem and West Center Street in Provo. Crews have prepared a path for FrontRunner by grading and clearing the right-of-way and relocating water lines.



Crews will be splicing fiber optics throughout the area this week.



Traffic Impacts:

There will be a partial lane closure in the middle of the week at Freedom Boulevard in Provo while crews pothole to confirm location of a gas line. Flaggers will be directing traffic.



Provo Station-University Ave. Station:

No station construction activities to report.

Reblog this post [with Zemanta]

Wednesday, March 11, 2009

Mid Jordan TRAX line construction update

{{de|Gleis mit Holzschwellen im Schotterbett}}...Image via Wikipedia

Mid-Jordan Light Rail TRAX Construction Update: March 11, 2009*

Please forward this information on to others that would be interested.

*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.

Bangerter Bridge

UPDATED Activity: Crews have removed the median barrier in the area of approximately 8700 South and Bangerter Highway (just south of the Old Bingham Highway overpass). The median has been replaced with water barrels and will remain closed through April.

Sugar Factory Area

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

Old Bingham Area

No traffic impacts are expected.

Gardner Village Area

NEW Activity: Crews will be resuming work on the bridge at 7800 South near Gardner Village. Traffic Impacts: Westbound traffic will be shifted to the south side of 7800 South on March 9th until March 13th. Eastbound traffic will be shifted to the north March 13th and 14th.

Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.

Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th, 2008 on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.

Cottonwood Area

NEW Activity: Crews will be working near the bridge structure on Winchester Street. Traffic Impacts: Traffic may be subject to intermittent periods one lane configurations with flagging operations from March 9th through March 13th. Please plan accordingly.

NEW Activity: Crews will be working above and around the trackway (approximately 7400 South) and 700 West. Traffic Impacts: Traffic will be restricted to one lane with flagging operations on March 16th and March 17th. Please plan accordingly.

Activity: Crews are continuing access and utility work near 300 West and the intersection of Winchester Street and Cottonwood Street. Traffic Impacts: Shoulder work with lane restrictions.

If you have any questions or concerns regarding the project, please let me know.

Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783

sloughlin@rideuta.com

Reblog this post [with Zemanta]

Inside the Silver Meteor trainImage via Wikipedia

This Week at Amtrak; March 11, 2009

A weekly digest of events, opinions, and forecasts from

United Rail Passenger Alliance, Inc.

America’s foremost passenger rail policy institute

1526 University Boulevard, West, PMB 203 • Jacksonville, Florida 32217-2006 USA

Telephone 904-636-7739, Electronic Mail info@unitedrail.orghttp://www.unitedrail.org

Volume 6, Number 8

Founded over three decades ago in 1976, URPA is a nationally known policy institute that focuses on solutions and plans for passenger rail systems in North America. Headquartered in Jacksonville, Florida, URPA has professional associates in Minnesota, California, Arizona, New Mexico, the District of Columbia, Texas, and New York. For more detailed information, along with a variety of position papers and other documents, visit the URPA web site at http://www.unitedrail.org.

URPA is not a membership organization, and does not accept funding from any outside sources.

1) The combined arrogance and hubris of these people is incredible; maybe some enterprising staffer on Capitol Hill will start looking into this and have someone in the House or Senate start demanding some answers. It’s a good thing former Amtrak President and CEO Alex Kummant is gone, but that doesn’t take the Amtrak Board of Directors off the hook for not doing their lawful duty and asking more questions and demanding better of Amtrak.

Brandweek.com has reported Amtrak spent $15.3 million on U.S. media in 2008, not including online expenditures, up from $14.8 million in 2007, according to Nielsen Monitor-Plus.

If you think that’s a lot of money in today’s world of paid media, you’re very wrong. It’s more like a half a drop in the bucket.

Last year, Amtrak spent $98.1 million on what it categorizes as advertising and sales according to its year end figures. That $98.1 million generated ticket revenue of $1,699,300,000. Most successful companies the size of Amtrak spend about 10% of revenues on advertising and marketing costs; Amtrak spent just slightly less than six percent. Even worse, on actual media the public sees, Amtrak spent only .009 – less than a single percent – on advertising.

No wonder Amtrak perpetually remains America’s Best Kept Secret.

To no one’s surprise, the biggest slice of the advertising and sales money was spent on the Northeast Corridor, instead of the long distance national network where the most good for total transportation output could be achieved.

At this point you may be wondering, what’s all the fuss about?

All the fuss is about how Amtrak positions itself with its customers, which, obviously is not its passengers in the minds of Amtrak executives. Amtrak’s true customers, where all of its efforts are spent, are the various public treasuries of the federal and state governments which constantly have to feed the voracious Amtrak bottomless financial pit.

Amtrak’s decision to spend so very little money on national or local media clearly demonstrates how little it cares about being a successful company.

Is Amtrak afraid of success?

Good heavens, what would Amtrak actually do if a lot of people showed up and wanted to ride its trains?

As always, this isn’t an argument about how much free federal monies Amtrak receives as a result of its annual begfest on Capitol Hill, it’s an argument over unsound management decisions and mis-allocation of resources and poor priorities.

During the same year Amtrak spent less than one percent of its ticket revenues on paid advertising, it received about $1.2 billion in free federal monies, of which less than $500 million was for nationwide/systemwide operating assistance.

Let’s be radical and say Amtrak suddenly saw the light and reoriented its priorities and (Gasp!) tripled its annual expenditures on advertising to less than three percent (Still woefully below any national averages for companies in the real world.) What would happen? Amtrak’s load factors would soar, wiping out at least half, if not more, of the annual operating subsidy requirement.

This also directly goes to the debunked lie no passenger railroad system in the world makes money, when we know factually systems in Japan, Germany, The Netherlands and elsewhere do, in fact, make money.

If, like Amtrak, you run a passenger railroad and don’t bother to tell anyone you’re running trains, well, yes, it’s not going to make money, or even come close to breaking even because no one knows there are trains to ride.

2) Let’s revisit some familiar territory, Amtrak’s load factors. We know a load factor of 65% technically makes a long distance train sold out, because allowances have to be made for entraining/detraining passengers at intermediate station stops. When a passenger on the Silver Meteor boards in Miami at the train’s originating terminal, and detrains in Palatka, leaving a vacant seat, that seat may not be filled again until Savannah, 206 route miles to the north. However, that Savannah passenger stays in that seat all the way to Philadelphia, just 101 miles short of the Meteor’s final terminal in New York City. So, that coach seat on the Meteor (which probably needed new upholstery) was occupied for 1,082 miles out of the total route length of 1,389 miles. The magic of trains is when one passenger detrains, most of the time another passenger entrains.

Those with endpoint mentalities or airline mentalities where there are no intermediate stops on a route, often have difficulty grasping this concept. It’s true, once an airplane pushes out from the gate at its originating terminal, any vacant seat on the plane has no other opportunity to be sold/filled. However, once the Silver Meteor departs Miami on its northward journey, that are still 25 more opportunities for passengers to board the train before it reaches the silly "discharge only" territory of the Northeast Corridor, where long distance trains are banned from picking up passengers between Alexandria, Virginia and New York City so Amtrak can falsely prop up NEC numbers without interference from those pesky, money-making long distance trains.

Look at Amtrak’s load factors for last year:

Long Distance Routes

Silver Star – 58.9%

Cardinal – 55.5%

Silver Meteor – 62.5%

Empire Builder – 63.4%

Capitol Limited – 66.9%

California Zephyr – 52.3%

Southwest Chief – 63.8%

City of New Orleans – 63.8%

Texas Eagle – 53.4%

Sunset Limited – 56.7%

Coast Starlight – 62.4%

Lake Shore Limited – 64.1%

Palmetto – 51.3%

Crescent – 51.6%

Auto Train – 63.6%

Average Long Distance Routes Load Factor – 59.7%

State Corridors and Short Distance Routes

Ethan Allen – 40.8%

Vermonter – 45.8%

Maple Leaf – 54.0%

Downeaster – 31.8%

New Haven-Springfield – 47.1%

Keystone – 35.5%

Empire Service – 35.0%

Chicago-St. Louis – 46.6%

Hiawathas – 40.4%

Wolverines – 54.9%

Illini – 50.0%

Illinois Zephyr – 43.1%

Heartland Flyer – 43.0%

Surfliners – 36.5%

Cascades – 56.6%

Capitols – 29.1%

San Joaquins – 39.1%

Adirondack – 69.4%

Blue Water – 78.7%

Washington, D.C.-Newport News – 60.2%

Hoosier State – 35.4%

Kansas City-St. Louis – 37.4%

Pennsylvanian – 74.3%

Pere Marquette – 67.3%

Carolinian – 77.9%

Piedmont – 44.6%

Average State Corridors and Short Distance Routes Load Factor – 43.5%

Northeast Corridor Routes

Acela – 62.6%

Northeast Regional – 48.1%

Average Northeast Corridor Routes Load Factor – 52.9%

These figures show Amtrak has plenty of room for more passengers without adding a single piece of equipment to its far-too-short existing consists.

Look at the numbers above, realizing the sad state of Amtrak’s skeletal national system, lack of operable locomotives and passenger cars, and lack of rational business plan, and think what a combination of advertising, getting bad-ordered and wrecked cars back on trains, and lengthening consists could accomplish. Close your eyes and start thinking about second and third frequencies, and, suddenly you have the beginnings of a robust, healthy system. Go one step further and start implementing Gil Carmichael’s Interstate II vision, and, astonishingly, you have a real railroad, not a shadow of a ghost of railroads past.

2) We’re talking chump change here in the overall Amtrak universe to begin to get Amtrak up to acceptable levels of advertising expenditures. One cannot help but question Emmet Fremaux, Amtrak’s Vice President who handles marketing, as to why he has allowed these advertising numbers to be so low. Has this been intentional, or a result of more senior managers only allocating so little for his total budget?

Where was the board of directors on this? Oh, wait, they were here, but, consider that of the five board members who constituted the Amtrak board last year, not a single one has corporate background experience; each and every one is either a creature of government service, or a Washington lobbyist or Washington attorney. After David Laney, Enrique Sosa, and Floyd Hall all left the board, not a single member replacing them or remaining has any real world, corporate experience, and would automatically know Amtrak’s abysmally low advertising expenditures amount to corporate malfeasance, and, at best, poor stewardship of public funds when the company willingly asks for billions in government subsidies, and then does nothing to promote the company and try and actually attract paying passengers who would replace the need for government subsidies.

3) Well-respected Washington Post Writers Group syndicated columnist Neal Peirce has been writing about Washington for decades, and often strays to the subject of Amtrak. Mr. Peirce again recently wrote about Amtrak and our new President Obama’s spending on passenger rail. One quote from Mr. Peirce’s column bears repeating, for it demonstrates how Amtrak has gotten away for so long with being America’s Best Kept Secret and nobody seems to care.

[Begin quote]

Asserts James RePass, founder-leader of the 20-year-old National Corridors Initiative; "Suddenly, by the grace of God, we have a president who absolutely, positively gets it." This signifies, he adds, an end of the reign of "the ideological libertarians out to destroy the transportation system by saying ‘the market’ will take care of it, that Amtrak should make a profit – which is nuts!"

[End quote]

It’s this type of clearly wrong thinking that has been pervasive throughout America, bolstered by Amtrak’s bad behavior and not spending near enough on advertising to the public that makes Amtrak such a mess today.

Only when this type of wrong opinion is no longer considered gospel will Amtrak stop being enabled and start working towards being more self-sufficient. There’s nothing in our national government constitution that says every government entity has to lose money. There is nothing unpatriotic about Amtrak being self-sufficient. This is something grossly unpatriotic about Amtrak being such a poor steward of the public’s money and doing such disagreeable and arrogant things like taking public money and then not spending it wisely or in such a way which creates more business, more revenue, and more self-sufficiency.

Joe Boardman, as Amtrak’s Interim President and CEO, what steps are you taking to solve this problem and stop keeping Amtrak as America’s Best Kept Secret?

If you are reading someone else’s copy of This Week at Amtrak, you can receive your own free copy each week by sending your e-mail address to

freetwa@unitedrail.org

You MUST include your name, preferred e-mail address, and city and state where you live. If you have filters or firewalls placed on your Internet connection, set your e-mail to receive incoming mail from twa@unitedrail.org; we are unable to go through any individual approvals processes for individuals. This mailing list is kept strictly confidential and is not shared or used for any purposes other than the distribution of This Week at Amtrak or related URPA materials.

All other correspondence, including requests to unsubscribe, should be addressed to

brucerichardson@unitedrail.org

Copies of This Week at Amtrak are archived on URPA’s web site, www.unitedrail.org and also on www.todaywithjb.blogspot.com where other rail-related writings of Bruce Richardson may also be found.

URPA leadership members are available for speaking engagements.

J. Bruce Richardson

President

United Rail Passenger Alliance, Inc.

1526 University Boulevard, West, PMB 203

Jacksonville, Florida 32217-2006 USA

Telephone 904-636-7739

brucerichardson@unitedrail.org

http://www.unitedrail.org


Reblog this post [with Zemanta]