Airport TRAX Line Construction Update



Welcome!

Construction continues on UTA’s Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.

Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Crews are excavating the east side of 3700 West from 510 North to Gate 13. During this time, lane restrictions will be in place; however, access will be maintained.
Crews have begun work on the 24’’ sewer installation. This work will take place within internal airport lots.
Work continues on wet and dry utilities along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained throughout this work.
Work continues on cast in place walls and excavation of the guideway between the X Bar Bridge and 3700 West.


Traffic Impacts:

Bailey Boulevard (an internal airport road) will be closed from 7 p.m. to 5 a.m. on August 13, 16 and 17.
Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.



Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

· Crews are working on duct bank utility runs from X Bar to 2400 West.

Crews are also working on a retaining wall south of the X Bar.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Crews are working at the North Temple intersections located at 2200 West and 2400 West installing new curb, gutter and sidewalks. Various traffic restrictions are in place; however, access to businesses is being maintained.
Traffic signal cabinets are being installed at the 2200 West and 2400 West North Temple intersections.
Crews have removed a portion of the island between North Temple and Old North Temple and restoration is in progress. Lane restrictions are in place; however, access to Old North Temple is being maintained.



Reach 4

Reach Description: Reach 4 extends from I-215 to just east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Traffic signal work, including conduits, pedestals and junction boxes, is taking place at 1950 West and Redwood Road along North Temple.
Crews are installing a new gas line along North Temple, west of Orange Street.
Work is taking place on the joint trench crossing at Orange Street. Various lane restrictions are in place; however, access is being maintained.
Roadway milling will take place on the south side of North Temple on Saturday, August 14.
Wet and dry utility work is taking place on North Temple between I-215 and Redwood Road.
Night work is taking place at Redwood Road and North Temple on joint trench crossings. This work will take place from 7 p.m. to 7 a.m. Noise is expected to be minimal during nighttime work as louder activities will take place during the day.
Crews are removing and replacing curb, gutter, sidewalk and driveways on the south side of North Temple between Redwood Road and I-215.


Upcoming Construction:

Crews are scheduled to begin sewer sag repairs at Orange Street and North Temple on September 13. At this time, various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. In preparation for this work various activities are currently taking place near Orange Street. As we get closer to construction we will meet with businesses in this area.
During the week following Labor Day, weekend crews will begin demolition and reconstruction work at the Redwood Road and North Temple intersection. Significant traffic restrictions and closures will take place during this work. As we get closer to construction we will meet with the businesses.
Crews continue to relocate hydrants and water services in the upcoming weeks. We will continue to meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are right and left lane restrictions between the I-215 overpass and Redwood Road throughout the day. As work progresses, there will be additional lane restrictions for both east and west bound traffic, although access will be maintained.



Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Crews are preparing the Jordan River Bridge to reopen before the Utah State Fair begins September 9.
There is occasional potholing for dry utilities taking place throughout this reach ahead of construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.


Traffic Impacts:

Traffic will be limited to one lane in each direction.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to businesses and the State Fairpark will be maintained.



Current Construction:

Crews are removing and replacing City Creek West between the Jordan River Bridge and 1000 West.


Traffic Impacts: Traffic control near the Jordan River Bridge, which is limited to one lane in each direction, has been extended to support City Creek West work. This traffic control will switch from one side of the bridge to the other as work progresses.



Reach 7

Reach Description: Reach 7 is the area where the Airport TRAX Line will connect with the current north/south line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained throughout the construction project.



Current Construction:

The North Temple Viaduct re-construction project began April 18, 2010 and will continue for approximately 18 months.
Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.
Crews are drilling 16 shafts for the new North Temple Viaduct. Eleven of these shafts have been drilled, set, and poured and the 12th shaft is underway. This work will take place for approximately three weeks and noise is expected to be minimal.
Night work is scheduled for the following dates and times for City Creek East relocation and for pouring the abutment caps:
· Sunday, August 15, from 4 a.m. until 6 p.m.

· Monday, August 16, from 5 a.m. to 9 a.m.

· Sunday, August 22, beginning at 12 a.m. until Monday, August 23, at 3 a.m.

Please see the viaduct construction guide below for information on how to get around during this portion of construction.


General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.

Business Spotlight:

NeighborWorks Salt Lake; Building Homes, Building Lives
“Creating opportunities through housing, resident leadership, and youth and economic development,”
NeighborWorks Salt Lake (NWSL) has found success in “Rebuilding Neighborhoods… One Block at a
Time.”

NWSL works to create affordable housing through partnerships with businesses and
government, and their “outstanding revitalization efforts” were recognized in
1996 by then U.S. President Bill Clinton.
This private non-profit group was launched in 1977 as Salt Lake Neighborhood
Housing Services in the East Liberty Park area of Salt Lake City and has since
grown to include neighborhoods along the North Temple
corridor. Its main offices are now located at 622 West 500
North, under the leadership of Maria Garciaz for the past two
decades.

Today NWSL has a staff of 15 and employs about 45 youth a
year. “We’re not only doing home improvement loans, we’re
doing multi-family development … [building] major subdivisions,
resident leadership … serving thousands of residents,” Garciaz said.
NWSL also invests in creative and leadership opportunities for youth,
supporting murals and artwork featured throughout the region, including
businesses along North Temple.

“When you do house-by-house, block-by-block you get to know people.
And it’s about bringing people together, identifying their needs and really seeing who you can bring to
the table to address those needs,” Garciaz said. “And the people who come to the table to help make a
difference in the community have been tremendous over our 33 years.”
Enhanced by Zemanta

Saturday, August 07, 2010

Airport TRAX Line Construction Update

delta.jpgImage by Laura B. Dahl via Flickr


Welcome!

Construction continues on UTA’s Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utilities along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are excavating the east side of 3700 West from the U.S. Post Office to 510 North. Work will continue in this area toward gate 13. During this time, lane restrictions will be in place; however, access will be maintained.
Crews have begun work on the 24’’ sewer installation. This work will take place within the internal airport lots.
Work continues on cast in place walls and excavation of the guideway between the X Bar Bridge and 3700 West.


Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.

A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.
Bailey Blvd (Airport Internal) will be closed 7 p.m to 5 a.m. Aug. 6, 9, and 10.

Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Crews are working on duct bank runs from X Bar to 2400 West.
Wet and dry utility work continues in this area.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Crews are working at the 2200 West and North Temple intersection. The first phase of this work is now complete and the Park ‘n Jet driveway is now open. Although various traffic restrictions will be in place during this work, access to businesses will be maintained.
Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west in this reach.
Crews are installing signal conduit at 2200 and 2400 West.
Crews have removed a portion of the island between North Temple and Old North Temple and restoration is in progress. Lane restrictions are in place; however, access to Old North Temple is being maintained.
Cast in place wall work continues.



Reach 4

Reach Description: Reach 4 extends from I-215 to just east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is taking place on North Temple approaching Redwood Road.
Crews are working nights on the joint trench crossings. This work will take place from 7 p.m. to 7 a.m. Noise is expected to be minimal as louder activities will take place during the day.
Crews are boring for a gas line under the Redwood Road and North Temple intersection. Various traffic restrictions will be in place, but access will be maintained.
Crews are removing and replacing curbs, gutters, sidewalks and driveways on the south side of North Temple between Redwood Road and 1950 West.
Curb, gutter and sidewalk removal will take place between 1950 West and Redwood Road on the north side of North Temple in support trench utility relocation.
Storm drain work continues and is approaching 1950 West on North Temple.
Crews are relocating utilities on the south side of North Temple between Redwood Road and 1950 West. During this work there will be lane restrictions but access to all businesses will be maintained and signage will be provided.
Traffic signal work, including conduits, pedestals and junction boxes, is taking place.


Upcoming Construction:

Crews are working on a joint trench crossing at Orange Street. At this time, various lane restrictions will be in place; however, access to businesses will be maintained.
Traffic signal work is scheduled to begin this week at the Redwood Road and North Temple intersection.
Crews are scheduled to begin sewer sag repairs at Orange Street and North Temple on Sept. 7. At this time, various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. In preparation for this work various activities are taking place near Orange Street. As we get closer to construction we will be meeting with businesses in this area.
The week following Labor Day weekend, crews will begin demolition and reconstruction work at the Redwood Road and North Temple intersection. Significant traffic restrictions and closures will then take place. As we get closer to construction we will be meeting with businesses in this area.
Crews will continue relocating hydrants and water services in the coming weeks. We will continue to meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are right/left lane restrictions between the I-215 overpass and Redwood Road. As work progresses, there will be additional lane restrictions for both east and west bound traffic, although access will be maintained at all times.



Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews work on the bridge deck. Crews are forming and pouring transition slabs. The Jordan River Bridge is still on schedule to be completed before the Utah State Fair begins in September.
There is occasional potholing for dry utilities taking place throughout this reach ahead of construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.


Traffic Impacts:

Traffic will be limited to one lane in each direction.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to businesses and the State Fairpark will be maintained.



Current Construction:

Crews are removing and replacing City Creek West from the Jordan River Bridge to 1000 West. This work will be completed before the State Fair.


Traffic Impacts: Traffic control near the Jordan River Bridge, which is limited to one lane in each direction, has been extended to support City Creek West work. This traffic control will switch from one side of the bridge to the other as City Creek progresses.



Reach 7

Reach Description: Reach 7 is the area where the Airport TRAX Line will connect with the current north/south line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained.



Current Construction:

The North Temple Viaduct re-construction project began April 18 and will continue for approximately 18 months.
Crews are drilling 16 shafts for the new viaduct. Eight of these shafts have been drilled, set, and poured and the ninth is under way. This work will take place for approximately three weeks and noise is expected to be minimal.
Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.
Night work is scheduled for the following dates and times for City Creek East relocation:
o Monday, Aug. 9 from 4 a.m. until 4 p.m.

o Sunday, Aug. 15 from 4 a.m. until 6 p.m.

o Sunday, Aug. 29 beginning at 12 a.m. until Monday, August 23 at 3 a.m.

Night work is scheduled for the following date and time while pouring the Abutment Caps at the Viaduct
Friday Aug. 13 from 4 a.m. until 9 a.m.
Crews are potholing and boring on 400 West (MCI fiber)
Crews will be relocating MCI Utility at the intersection of 50 North and 400 West
Please see the viaduct construction guide below to find out how to get around during this portion of construction.

General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.





Enhanced by Zemanta

Sunday, August 01, 2010

Airport TRAX Line Construction Update

Salt Lake City InternationalImage by Brisan via Flickr


Welcome!



Construction continues on UTA’s Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utilities along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are excavating the east side of 3700 West from the U.S. Post Office to 510 North. Work will continue in this area toward gate 13. During this time, lane restrictions will be in place; however, access will be maintained.
Crews have begun work on the 24’’ sewer installation. This work will take place within the internal airport lots.
Work continues on cast in place walls and excavation of the guideway between the X Bar Bridge and 3700 West.


Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.
Bailey Blvd (Airport Internal) will be closed 7pm to 5am on Aug. 5, 6, 9, and 10.

Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Work on lock and load walls 1 and 3 will be completed early next week.
In approximately one week crews will begin work on duct bank runs from X Bar to 2400 West.
Wet and dry utility work continues in this area.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Crews are currently working at the 2200 West and North Temple intersection. The first phase of this work is complete and the Park ‘n Jet driveway is open. Various traffic restrictions will be in place during this work; however, access to businesses will be maintained.
Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west in this reach.
Crews are installing signal conduit at 2200 and 2400 West.
Crews have removed a portion of the island between North Temple and Old North Temple and restoration is in progress. Lane restrictions are in place; however, access to Old North Temple is being maintained.
Cast in place wall work continues.



Reach 4

Reach Description: Reach 4 extends from I-215 to east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is taking place on North Temple approaching Redwood Road.
Crews are working nights on the joint trench crossings. This work will take place from 7 p.m. to 7 a.m. Noise is expected to be minimal during nighttime work as louder activities will take place during the day.
Crews will tie in gas line services early next week on the south side of North Temple near Redwood Road. During this work there will be a time where a maintenance truck will be in parking lots to do the tie in. Access will be maintained.
Crews are currently boring for a gas line under the Redwood Road and North Temple intersection. Various traffic restrictions will be in place; however, access will be maintained.
Crews are removing and replacing curb, gutter, sidewalk and driveways on the south side of North Temple between Redwood Road and 1950 West.
Curb, gutter and sidewalk removal will take place between 1950 West and Redwood Road on the north side of North Temple in support of trench utility relocation.
Storm drain work continues and is approaching 1950 West on North Temple.
Crews are relocating utilities on the south side of North Temple between Redwood Road and 1950 West. During this work there will be lane restrictions but access to all businesses will be maintained and signage will be provided.
Traffic signal work, including conduits, pedestals and junction boxes, is taking place.


Upcoming Construction:

Crews to begin Joint Trench Crossing at Orange Street next week. At this time, various lane restrictions will be in place; however, access will be maintained.
Traffic signal work is scheduled to begin this week at the Redwood Road and North Temple intersection.
Crews are scheduled to begin sewer sag repairs at Orange Street and North Temple on September 7. At this time, various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. In preparation for this work various activities are taking place near Orange Street. As we get closer to construction we will be meeting with businesses in this area.
The week following Labor Day weekend crews will begin demolition and reconstruction work at the Redwood Road and North Temple intersection. During this time significant traffic restrictions and closures will take place. As we get closer to construction we will be meeting with businesses in this area.
Crews will continue relocating hydrants and water services in the upcoming weeks. We will continue to meet with the businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are right/left lane restrictions between the I-215 overpass and Redwood Road throughout the day. As work progresses, there will be additional lane restrictions for both east and west bound traffic. Access will be maintained at all times.



Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews work on the bridge deck. Crews are forming and pouring transition slabs. The Jordan River Bridge is on schedule to be completed before the Utah State Fair in September.
There is occasional potholing for dry utilities taking place ahead of construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.


Traffic Impacts:

Traffic will be limited to one lane in each direction.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to businesses and the State Fairpark will be maintained.



Current Construction:

Crews are removing and replacing City Creek West from the Jordan River Bridge to 1000 West. This work will be completed before the State Fair.


Traffic Impacts: Traffic control near the Jordan River Bridge, which is limited to one lane in each direction, has been extended to support City Creek West work. This traffic control will switch from one side of the bridge to the other as City Creek progresses



Reach 7

Reach Description: Reach 7 is the area where the Airport TRAX Line will connect with the current north/south line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained.



Current Construction:

The North Temple Viaduct re-construction project began April 18 and will continue for approximately 18 months.
Crews are drilling 16 shafts for the new North Temple Viaduct. Eight of these shafts have been drilled, set, and poured and the ninth is under way. This work will take place for approximately three weeks and noise is expected to be minimal.
Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.
Off-hours work is scheduled for the following dates and times for City Creek East relocation:
o Monday, August 9 from 4 a.m. until 4 p.m.

o Sunday, August 15 from 4 a.m. until 6 p.m.

o Sunday, August 22 beginning at 12 a.m. until Monday, August 23 at 3 a.m.

Night work is scheduled for the following date and time while pouring the Abutment Caps at the Viaduct
Friday August 13 from 4am until 9am
Crews are potholing and boring on 400 West
Crews will be relocating MCI Utility at the intersection of 50 North and 400 West
Please see the viaduct construction guide below to find out how to get around during this portion of construction.

General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.

Business Spotlight

Home of “Killer Mexican Food”
Brings North Temple to Life
It goes without saying, if
you’re looking for great Mexican
food in Salt Lake City, you go to
the Red Iguana. After 40 years
of successful business, being
recognized as Utah’s most
awarded Mexican Restaurant with more than 38 national and local
awards, even City Weekly asks, “Can anyone remember a year
when Red Iguana didn’t win the Best of Utah award for Best
Mexican?”

What may not have been mentioned is that despite the
ongoing lunch-time lines of customers that circle the building at
736 West and continuing rave reviews, Red Iguana is feeling the
pinch of TRAX construction along North Temple. Owners of the famous eatery,
however, are taking the bull by the horn, voicing their optimism for a better
community and taking an active role in ensuring that none of the businesses
along North Temple are forgotten.

“We are a part of this community,” said owner Bill Coker, proudly
displaying the community-developed button that reads, “Shop North Temple, I
Do.” And he’s a man of his word. Coker and his wife Lucy Cardenas, daughter of the original owners,
have been instrumental in the distribution of these buttons. Coker also participates in a local
community advisory committee, which works to bring North Temple businesses together to discuss
construction and strategies to mitigate its impact on the local economy. “I have a business to run,” he
says, although he still invests his valuable time in helping plan a marketing campaign for businesses
affected by the reconstruction of the North Temple viaduct.

If you would like to join Bill Coker’s efforts to reshape the North Temple community, call him at
801-322-1489 or Bill Knowles at 801-580-2626.


Enhanced by Zemanta

Saturday, July 24, 2010

Airport TRAX Line Construction Update





Welcome!



Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utilities along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are currently excavating the east side of 3700 West from the U.S. Post Office to 400 North. Crews are scheduled to be at 510 North near Terminal One next week. During this time, lane restrictions will be in place, but access will be maintained.
Work continues on cast in place walls and excavation of the guideway between the X Bar Bridge and 3700 West.


Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.



Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Crews are excavating for upcoming wall work.
Wet and dry utility work continues in this area.
A power cutover is scheduled for lighting along the airport corridor this coming week.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Crews are currently working at the 2200 West and North Temple intersection. Various traffic restrictions will be in place, but access to Park ‘n Jet will be maintained.
Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west.
Crews are installing signal conduit at 2200 and 2400 West.
Crews have removed a portion of the island between North Temple and Old North Temple and restoration is in process. Lane restrictions are in place; however, access to Old North Temple is being maintained.
Cast in place wall work continues.



Reach 4

Reach Description: Reach 4 extends from I-215 to just east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is taking place on North Temple approaching Redwood Road.
Crews are working nights on the joint trench crossings. This work will take place from 7 p.m. to 7 a.m. Noise is expected to be minimal during nighttime work as louder activities will take place during the day.
Crews are removing and replacing curbs, gutters, sidewalks and driveways on the south side of North Temple between Redwood Road and 1950 West.
Curb, gutter and sidewalk removal will take place between 1950 West and Redwood Road on the north side of North Temple in support of the trench utility relocation.
Storm drain work continues and is approaching 1950 West on North Temple.
Crews are also relocating utilities on the south side of North Temple between Redwood Road and 1950 West. During this work there will be lane restrictions, but access will be maintained and signage will be provided.
Traffic signal work, including conduits, pedestals and junction boxes, is currently taking place.


Upcoming Construction:

Crews will begin boring for a gas line under the Redwood Road and North Temple intersection beginning Wednesday, July 28. Various traffic restrictions will be in place, but access will be maintained.
Traffic signal work is scheduled to begin this week at the Redwood Road and North Temple intersection.
Crews are scheduled to begin sewer sag repairs at Orange Street and North Temple on August 2. At this time, various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. In preparation for this work various activities are taking place near Orange Street. As we get closer to construction we will meet with businesses in this area.
Crews will continue relocating hydrants and water services in the upcoming weeks. We will continue to meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are right/left lane restrictions between the I-215 overpass and Redwood Road. As work progresses, there will be additional lane restrictions for both east and west bound traffic. Access will be maintained at all times.

Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews work on the bridge deck. Crews are forming and pouring transition slabs. The Jordan River Bridge is on schedule to be completed before the Utah State Fair in September.
There is occasional potholing for dry utilities taking place ahead of construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.


Traffic Impacts:

Traffic will be limited to one lane in each direction.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to the many businesses and the State Fairpark will be maintained.



Current Construction:

On Monday, July 26, crews are scheduled to begin relocating City Creek West from the Jordan River Bridge to 1000 West.


Traffic Impacts: Traffic control near the Jordan River Bridge, which is limited to one lane in each direction, will be extended to support City Creek West work.



Reach 7

Reach Description: Reach 7 is the area where the Airport TRAX Line will connect with the current north/south line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained.



Current Construction:

The North Temple Viaduct re-construction project began April 18 and continues for approximately 18 months.
Crews are drilling 16 drill shafts for the new viaduct. Seven of these shafts have been drilled, set, and poured. This work will take place for approximately three weeks and noise is expected to be minimal.
Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.
Night work is scheduled for the following dates and times for City Creek East relocation:
o Monday, August 9 from 4 a.m. until 4 p.m.

o Sunday, August 15 from 4 a.m. until 6 p.m.

o Sunday, August 22 beginning at 12 a.m. until Monday, August 23 at 3 a.m.

Crews are potholing and boring on 400 West.
Crews will be relocating MCI Utility at the intersection of 50 North and 400 West
Please see the viaduct construction guide below to find out how to get around during construction.

General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.

Business Spotlight:

Front End Grille Serves up Genuine Service and Great Food
Even in the roughest of circumstances, you just might find
the best food and nicest people in town. Adjacent to and hosting
various mechanics’ garages and the Next Step Home Foundation, the

Front End Grille offers up a 50’s style eating experience, along with
an old-fashioned full-service attitude.
Opening in February 2008, this oldstyle
diner, located at 510 West and 200
North, has served a wide variety of people
in the community—including those who are
dealing with a car or a life that has hit a
bump in the road.

―I just love it here,‖ said the
Grille’s manager, Louann. ―We have people from the neighborhood
[and as far as Draper] who come in everyday. And it’s not just for
the food, but for the company.‖ Serving up specialty foods—
including breakfast all day-- the Grille’s interior features murals painted by local artists and the outside
dining patio is shaded under full-sized trees.

More than just a stop along the way, the Front End Grille also manages a community of
businesses on its property under the name of Trackside. The well-maintained offices upstairs are home to
various businesses, including the Next Step Home Foundation – which also manages The Rail Event
Center-- Nourse Productions, TM Keaty & Associates, and SLC Mediation, Trackside provides several
garages for tenets such as DeBreeze Automotive, D&C Welding and Repair, JT Auto Body, Gaytan Car
Detailing.
The Front End Grille is a place where ―you just belong,‖ Louann said.

Sunday, July 18, 2010

Airport TRAX Line Construction Update

Salt LakeImage by SheldonPhotography via Flickr


Welcome!

Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utility work along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are currently excavating the east side of 3700 West from the U.S. Post Office to 400 North. After sidewalks and driveways are restored, crews will continue north towards 510 North with similar activities. Lane restrictions will be in place, but access will be maintained.
Crews are working on cast-in-place walls and excavating the guideway between the X Bar Bridge and 3700 West.


Upcoming Construction:

· The Rocky Mountain Power crossing may not need to cross Terminal drive, crews are waiting on more information. We will keep you posted.



Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.



Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Crews are excavating for upcoming wall work.
Wet and dry utility work continues in this area.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Crews are working at the 2200 West and North Temple intersection. Various traffic restrictions will be in place, but access to Park ‘n Jet will be maintained at all times.
Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west in this reach.
Crews are installing signal conduit at 2200 West and 2400 West.
Crews have removed a portion of the island between North Temple and Old North Temple and restoration is in progress. Lane restrictions are in place, but access to Old North Temple is being maintained.
Cast in place wall work continues



Reach 4

Reach Description: Reach 4 extends from I-215 to just east or Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is taking place on North Temple approaching Redwood Road.
Crews are working nights on the joint trench crossings. This work will take place from 7 p.m. to 7 a.m. Noise is expected to be minimal as louder activities will take place during the day.
Crews are removing and replacing curbs, gutters, sidewalks and driveways on the south side of North Temple between Redwood Road and 1950 West.
Crews are also relocating utilities on the south side of North Temple between Redwood Road and 1950 West. There will be lane restrictions, but access to businesses will be maintained and signage will be provided.


Upcoming Construction:

In the coming weeks, crews will begin sewer sag repairs at Orange Street and North Temple. At this time, various lane restrictions will be in place, but access to businesses will be maintained and signage will be provided. In preparation, various activities will take place near Orange Street. As we get closer to construction we will meet with businesses in this area.
Crews will continue relocating hydrants and water services in the upcoming weeks. We will continue to meet with the businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are right/left lane restrictions between the I-215 overpass and Redwood Road. As work progresses, there will be additional lane restrictions for both east and west bound traffic, although access will be maintained.

Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews work on the bridge deck. Crews are forming and pouring transition slabs. The Jordan River Bridge is on schedule to be completed before the Utah State Fair in September.
There is occasional potholing for dry utilities taking place ahead of construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.


Traffic Impacts:

Traffic will be limited to one lane in each direction.

Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to the many businesses and the State Fairpark will be maintained.



Current Construction:

No work is currently taking place in this reach.


Upcoming Construction:

Crews will begin relocating City Creek West from the Jordan River Bridge to 1000 West in late July.


Traffic Impacts: Traffic management is in place near the Jordan River Bridge and is limited to one lane in each direction.



Reach 7

Reach Description: Reach 7 is the area where the Airport Line will connect with the current north/south TRAX Line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained.



Current Construction:

The North Temple Viaduct re-construction project began April 18 and will continue for approximately 18 months. Crews are now nearing completion of the demoltion portion of the work.
Crews are drilling 16 drill shafts for the new viaduct. Four of these shafts have been drilled, set, and poured. This work will take place for approximately three weeks and noise is expected to be minimal.
Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.

No night work is scheduled for the viaduct; however, if Union Pacific Railroad grants approval for night work we will notify all residents and businesses in the area as soon as possible.

Crews are potholing and boring on 400 West (MCI fiber)
Crews will be relocating MCI Utility at the intersection of 50 North and 400 West
Please see the viaduct construction guide below to find out how to get around during construction.

Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.

Front End Grille Serves up Genuine Service and Great Food
Even in the roughest of circumstances, you just might find
the best food and nicest people in town. Adjacent to and hosting
various mechanics’ garages and the Next Step Home Foundation, the
Front End Grille offers up a 50’s style eating experience, along with
an old-fashioned full-service attitude.
Opening in February 2008, this oldstyle
diner, located at 510 West and 200
North, has served a wide variety of people
in the community—including those who are
dealing with a car or a life that has hit a
bump in the road.

―I just love it here,‖ said the
Grille’s manager, Louann. ―We have people from the neighborhood
[and as far as Draper] who come in everyday. And it’s not just for
the food, but for the company.‖ Serving up specialty foods—
including breakfast all day-- the Grille’s interior features murals painted by local artists and the outside
dining patio is shaded under full-sized trees.

More than just a stop along the way, the Front End Grille also manages a community of
businesses on its property under the name of Trackside. The well-maintained offices upstairs are home to
various businesses, including the Next Step Home Foundation – which also manages The Rail Event
Center-- Nourse Productions, TM Keaty & Associates, and SLC Mediation, Trackside provides several
garages for tenets such as DeBreeze Automotive, D&C Welding and Repair, JT Auto
Body, Gaytan Car
Detailing.

The Front End Grille is a place where ―you just belong,‖ Louann said.

Enhanced by Zemanta

Saturday, July 10, 2010

Airport TRAX Line Construction Update

SALT LAKE CITY, UT - APRIL 15: Delta Airlines ...Image by Getty Images via @daylife



Welcome!



Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utility work along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are currently excavating the east side of 3700 West from the United States Post Office to 400 North. After sidewalks and driveways are restored, crews will continue north towards 510 North with similar activities. Lane restrictions will be in place, but access will be maintained.
Crews are working on walls and excavating the guideway between the X Bar Bridge and 3700 West.


Upcoming Construction:

· Crews are waiting on more information, but the Rocky Mountain Power crossing may not need to cross Terminal drive. We will keep you posted.



Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.



Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Deck work is nearing completion at Surplus South.
Crews are working on wet and dry utility work.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west.
Crews are currently installing signal conduit at 2200 and 2400 West.
Crews have removed a portion of the island between North Temple and Old North Temple and restoration is in progress. Lane restrictions are in place, but access to Old North Temple will be maintained.
Cast-in-place wall work continues.


Upcoming Construction:

Beginning next week, crews will work at the 2200 West and North Temple intersection. Traffic restrictions will be in place, but access will be maintained.



Reach 4

Reach Description: Reach 4 extends from I-215 to just east Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is taking place on North Temple approaching Redwood Road.
Crews are working nights on the joint trench crossings. This work will take place from 7 p.m. to 7 a.m. Noise is expected to be minimal as louder activities will take place during the day.
Crews are removing and replacing curb, gutter, sidewalks and driveways on the south side of North Temple between Redwood Road and 1950 West.
Crews are also relocating utilities on the south side of North Temple between Redwood Road and 1950 West. There will be lane restrictions, but access will be maintained and signage will be provided.


Upcoming Construction:

In the coming weeks, crews will begin sewer sag repairs at Orange Street and North Temple. At this time, various lane restrictions will be in place, but access to businesses will be maintained and signage will be provided. In preparation to this work various activities will take place near Orange Street. As we get closer to construction we will meet with businesses.
Crews will begin relocating a gas line early next week on the south side of North Temple between Redwood Road and Duder Street, which will require various temporary driveway closures. Before this work begins we will meet with businesses.

Crews will continue relocating hydrants and water services in the upcoming weeks. We will continue to meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are right/left lane restrictions between the I-215 overpass and Redwood Road. As work progresses, there will be additional lane restrictions for both east and west bound traffic, although access will be maintained.

Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews work on the deck and form and pour columns. The Jordan River Bridge is on schedule to be completed before the Utah State Fair in September.
There is occasional potholing for dry utilities taking place ahead of construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.


Traffic Impacts:

Traffic will be limited to one lane in each direction.

Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to the many businesses and the State Fairpark will be maintained.



Current Construction:

No work is currently taking place.


Upcoming Construction:

Crews will begin relocating City Creek West from the Jordan River Bridge to 1000 West in late July.
On July 10, North Temple will be closed from 600 West to 700 West for the Mestizo’s West Side Art’s Festival.


Traffic Impacts: Traffic management is in place near the Jordan River Bridge and is limited to one lane in each direction.



Reach 7

Reach Description: Reach 7 is the area where the Airport TRAX Line will connect with the current north/south Line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained.



Current Construction:

The North Temple Viaduct re-construction project began April 18 and will continue for approximately 18 months. Crews are now nearing completion of demolition.
Crews are drilling 16 drill shafts for the new viaduct. Two of these shafts have been drilled, set, and poured. This work will take place for approximately three weeks and noise is expected to be minimal.
Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.

No night work is scheduled for the viaduct; however, if Union Pacific Railroad grants approval for night work we will notify all residents and businesses in the area as soon as possible.
Crews are potholing and boring on 400 West to relocate MCI Utility at the intersection of 50 North and 400 West
Please see the viaduct construction guide below to find out how to get around during construction.

General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.

Business Focus:

Little Pet Stop Around the Corner


The dogs and cats of North Temple have found a friend in the
Pet Stop Veterinary Clinic, where they find not only attention for
their “owies” and illnesses, but preventative care for a long, healthy -
- and slobbery -- life. “Pet care begins with a healthy start,” said Tess,
office manager for the clinic. “At Pet Stop Vet Clinic, we provide for
your pet a full range of dental, medical and surgical services.”

Pet Stop Veterinary Clinic, located at 44 North 800 West –
just south of North Temple-- is a full service clinic providing
affordable, quality care to cats, dogs, birds, reptiles and pocket pets
for more than 25 years. And not only are these services provided under the quality care of Dr. Matthew
Belman, Cornell University graduate, the clinic offers some unique pricing options to help local patients
and their masters pay for the care they need. The basic, primary and optimum health plans provide for
a complete assortment of services for one yearly payment, which can
also be paid through a three month, no interest, payment plan.

“We are conveniently located in downtown Salt Lake City
minutes from the freeway,” said Tess, whose own dog, Bailey, has
received and continues to receive quality care at the clinic. “We
recommend that puppies and kittens begin their immunizations at six
to eight weeks of age against a variety of diseases prevalent in our
area. A series of timed boosters is imperative so your pet develops a
strong immune system.” Call 801-531-0662 for more information on
their health plans or visit www.petstopvet.com.






Enhanced by Zemanta

Friday, June 25, 2010

Airport TRAX Line Construction Update

Siemens-built tram of the UTA's TRAX network a...Image via Wikipedia



Welcome!



Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

Welcome!



Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utility work along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are currently excavating the east side of 3700 West from the US Post Office to 400 North. After sidewalk and driveway is restored, crews will continue north towards 510 North with similar activities. Lane restrictions will be in place; however, access will be maintained.
Crews are working on walls and excavating the guideway between the X Bar Bridge and 3700 West.


Upcoming Construction:

· Crews will be crossing Terminal Drive with utility work in the upcoming weeks. More details will follow as we get closer to this work.



Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.



Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Work at the North Surplus Canal is now complete.
Now that girders are in place, crews have begun deck work at South Surplus Canal. This work will continue for the next two weeks.
Crews are working on wet and dry utilities.
Lock and load walls are being installed throughout this reach.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west.
Crews are nstalling a signal conduit at 2200 West.
Crews have begun removing a portion of the island between North Temple and Old North Temple. Lane restrictions are in place; however, access to Old North Temple will be maintained.
Beginning the first week of July crews will begin work at 2200 West and North Temple. As we get closer to construction we will meet with businesses in this area.



Reach 4

Reach Description: Reach 4 extends from I-215 to just east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is taking place on North Temple approaching Redwood Road.
Beginning Sunday, June 27, crews will be working nights to relocate a joint trench. This work will take place from 7 p.m. to 7 a.m. for approximately two weeks. Noise is expected to be minimal as louder activities will take place during the day.
Beginning early next week crews will be removing and replacing curbs, gutters, sidewalks and driveways on the south side of North Temple between Redwood Road and 1950 West.
Crews are relocating utilities on the south side of North Temple between Redwood Road and 1950 West. There will be lane restrictions, but access to all businesses will be maintained and signage will be provided.


Upcoming Construction:

In approximately two weeks, crews will begin sewer sag repairs at Orange Street and North Temple. Various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. As we get closer to construction we will be meeting with businesses in this area.
Crews will begin relocating hydrants and water services in the upcoming weeks. As we get closer to this work we will meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are currently right/left lane restrictions between the I-215 overpass and Redwood Road throughout the day. As work progresses, there will be additional lane restrictions for both east and west bound traffic. Access will be maintained at all times.



Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews work on the bridge deck. The Jordan River Bridge is still on schedule to be completed before the Utah State Fair begins in September.
Crews are installing a storm drain on the south side of the Jordan River Bridge.
There is occasional potholing for dry utilities taking place ahead of heavier construction.
Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.
Heavier construction is anticipated to begin in summer 2010.


Traffic Impacts:

Traffic will be limited to one lane in each direction.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to the many businesses and the State Fairpark will be maintained.



Current Construction:

No work is taking place in this reach.


Upcoming Construction:

Crews will begin relocating City Creek West from the Jordan River Bridge to 1000 West late July.
On July 10 North Temple will be closed from 600 West to 700 West for the Mestizo’s West Side Art’s Festival.


Traffic Impacts: Traffic management is in place near the Jordan River Bridge and is limited to one lane in each direction.



Reach 7

Reach Description: Reach 7 is the area where the Airport Line will connect with the current north/south TRAX Line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained throughout the construction project.



Current Construction:

The North Temple Viaduct re-construction project has begun and will last approximately 18 months. Crews are now nearing completion of the demoltion portion of the work.

In approximately one week, crews will start drilling 16 drill shafts for the new viaduct. This work will take place for approximately three weeks and noise is expected to be minimal.

Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.
No night work is scheduled for the viaduct; however, if Union Pacific Railroad grants approval for night work we will notify all residents and businesses as soon as possible.
Crews are potholing on 400 West to prepare for utility relocations.


Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.



Enhanced by Zemanta

Saturday, June 19, 2010

Airport TRAX Line Construction Update

A Delta Air Lines MD-90 (N910DN) at Salt Lake ...Image via Wikipedia


Welcome!



Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utility work along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Crews are currently excavating the east side of 3700 West from the United States Post Office to 400 North. After sidewalks and driveways are restored, crews will continue north toward 510 North with similar activities. During this time, lane restrictions will be in place; however, access will be maintained.
Crews are currently working on walls and excavating the guideway between the X Bar Bridge and 3700 West.


Upcoming Construction:

· Crews will be crossing Terminal Drive with utility work in the upcoming weeks. More details will follow as we get closer to this work.


Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.

A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.

Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Work at the North Surplus Canal is now complete.
Now that girders are in place, crews have begun deck work at South Surplus Canal. This work will continue for the next two weeks.
Crews are currently working on wet and dry utility work.
Lock and load walls are being installed.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.



Current Construction:

Curb, gutter, sidewalk, and wet and dry utility work continues to make its way west.
Crews have begun removing a portion of the island between North Temple and Old North Temple. Lane restrictions will take place; however, access will be maintained.
Beginning the first week of July crews will begin work at 2200 West and North Temple. As we get closer to construction we will meet with businesses in this area.



Reach 4

Reach Description: Reach 4 extends from I-215 to just east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is currently taking place on North Temple approaching Redwood Road.
Crews are currently relocating utilities and reconstructing driveways on the south side of North Temple between Redwood Road and 1950 West. During this work there will be lane restrictions but access to all businesses will be maintained and signage will be provided.


Upcoming Construction:

In approximately two weeks, crews will begin sewer sag repairs at Orange Street and North Temple. At this time, various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. As we get closer to construction we will meet with businesses in this area.
Beginning the first week of July crews will be removing and replacing curb, gutter, sidewalk and driveways on the south side of North Temple between Redwood Road and 1950 West.
Crews will begin relocating hydrants and water services in the coming weeks. As we get closer to this work we will meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are currently right/left lane restrictions between the I-215 overpass and Redwood Road throughout the day. As work progresses, there will be additional lane restrictions for both east and west bound traffic. Access will be maintained at all times.


Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews begin working on the bridge deck. The Jordan River Bridge is still on schedule to be completed before the Utah State Fair begins in September.
Crews are currently installing a storm drain on the south side of the Jordan River Bridge.
There is occasional potholing for dry utilities taking place ahead of actual construction.


Upcoming Construction:

In the coming weeks crews will begin wet and dry utility work.
Heavier construction is anticipated to begin in summer 2010.


Traffic Impacts:

Traffic will be limited to one lane in each direction.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to the many businesses and the State Fairpark will be maintained.



Current Construction:

No work is currently taking place in this reach.


Upcoming Construction:

Crews will begin relocating City Creek West from the Jordan River Bridge to 1000 West from early July to late August.
On July 10 North Temple will be closed from 600 West to 700 West for the Mestizo’s West Side Art’s Festival.


Traffic Impacts: Traffic management is currently in place near the Jordan River Bridge and is limited to one lane in each direction.



Reach 7

Reach Description: Reach 7 is the area where the Airport Line will connect with the current north/south TRAX Line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained throughout construction.



Current Construction:

The North Temple Viaduct re-construction project began in April and will last for approximately 18 months. Crews are now nearing completion of the demoltion portion of the work.

Crews are currently working on a gas line at 300 West. This work is being done underground with a boring machine and will not require any driveway closures.

In approximately two weeks, crews will start drilling 16 drill shafts for the new North Temple Viaduct. This work will take place for approximately three weeks and noise is expected to be minimal.

Wet and dry utility relocations are taking place to prepare for the City Creek East relocation.

No night work is scheduled for the viaduct; however, if Union Pacific Railroad grants approval for night work we will notify all residents and businesses in the area as soon as possible.

Please see the viaduct construction guide attached below to find out how to get around during construction.

Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.


If you own a business along North Temple and would like to be featured as a “Business Spotlight” please email your information to tcamp@rideuta.com, or call the hotline at 888-800-8854





Enhanced by Zemanta

Saturday, May 29, 2010

Airport TRAX Line Construction Update

A train in Salt Lake City similar to what Omah...Image via Wikipedia



Welcome!

Construction progress continues on the Airport TRAX Line. To keep business and traffic impacts to a minimum, this six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.



Reach 1

Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport on the side of the Airport Access Road to the surplus canal bridge just north of the Wingpointe Golf Course.



Current Construction:

Work continues on wet and dry utility work along 3700 West. Various traffic restrictions are in place for internal airport traffic; however, access is being maintained.
Beginning the first week of June, crews will excavate the east side of 3700 West from the United States Post Office to 400 North. During this time lane restrictions will be in place; however, access will be maintained. We will meet with businesses as we get closer to construction.
Crews are currently working on walls and excavating the guideway between the X Bar Bridge and 3700 West.


Traffic Impacts:

Right lane restrictions along Bangerter Highway just north of the I-80 off-ramp entering the airport are in place Monday through Friday, and occasionally on Saturday.
A traffic plan has been distributed to the 3700 West businesses. This plan does not affect those traveling to the airport.



Reach 2

Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the Airport Access Road fence line to 2400 West.



Current Construction:

Work continues on the second phase of construction at the North Surplus Canal. This phase of construction will include diverting the water, de-watering the culvert, excavating and forming the culvert walls and floors. This work will be complete by mid-June.
Now that girders are in place, crews are beginning items associated with the “Deck Work” at South Surplus Canal.



Reach 3

Reach Description: Reach 3 extends from 2400 West along North Temple to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.





Current Construction:

Curb, gutter, sidewalk and wet and dry utility work continues to make its way west.
Old North Temple is now reopened; however, on June 2 crews will close it again to relocate a power line conduit. This work is anticipated to take five to seven days and traffic will be detoured to 2200 West. As we get closer to construction we will be meeting with businesses in this area.




Reach 4

Reach Description: Reach 4 extends from I-215 to just east of Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West. Access to the many businesses and governmental organizations will be maintained.



Current Construction:

Wet and dry utility work is currently taking place on North Temple approaching Redwood Road.


Upcoming Construction:

Crews are currently relocating utilities and reconstruction driveways on the south side of North Temple between Redwood Road and 1950 West. During this work there will be lane restrictions, but access to all businesses will be maintained and signage will be provided.
Early next week crews will begin work on a water line at the 1950 West and North Temple intersection. This work is expected to last three days and access will be maintained.
In approximately two weeks crews will begin sewer sag repairs at Orange Street and North Temple. At this time various lane restrictions will be in place; however, access to businesses will be maintained and signage will be provided. As we get closer to construction we will be meeting with businesses in this area.
Crews will begin relocating hydrants and water services in the upcoming weeks. As we get closer we will meet with businesses and coordinate any planned interruptions to services.


Traffic Impacts: There are currently right/left lane restrictions between the I-215 overpass and Redwood Road. As work progresses, there will be additional lane restrictions for both east and west bound traffic. Access will be maintained at all times.



Reach 5

Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West. Access to the many businesses and office complexes will be maintained.



Current Construction:

Work continues on the south side of the Jordan River Bridge as crews have begun the second phase of construction, which includes diverting the water and pile driving activities. The bridge is scheduled to be completed before the State Fair begins in September.
Crews are currently installing a storm drain on the south side of the Jordan River Bridge.
There is occasional potholing for dry utilities taking place ahead of actual construction.
Heavier construction is anticipated to begin in summer 2010.


Traffic Impacts:

Traffic will be limited to one lane in each direction.
Traffic is now switched to the newly constructed north side of the Jordan River Bridge on North Temple near the State Fairpark.



Reach 6

Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1100 West and 800 West. Access to the many businesses and the State Fairpark will be maintained.



Upcoming Construction:

Early next week crews will be replacing a small stretch of sidewalk on the north side of North Temple between the I-15 overpass and 600 West. This work will take place for approximately three days and a pedestrian walkway will be in place.
City Creek West relocation will take place from the Jordan River Bridge to 1000 West in mid June to late August.


Traffic Impacts: Traffic management is currently in place near the Jordan River Bridge and is limited to one lane in each direction.



Reach 7

Reach Description: Reach 7 is the area where the Airport Line will connect with the current north/south TRAX Line at the Arena Station. This reach extends from I-15 to 400 West along North Temple and turns south on 400 West to South Temple. Access to offices and the Gateway will be maintained throughout the construction project.



Current Construction:

The North Temple Viaduct re-construction project has begun and will last for approximately 18 months. Crews are nearing completion of the demo portion of the work.
No night work is scheduled for the viaduct; however, if Union Pacific Railroad grants approval for night work we will notify all residents and businesses as soon as possible.
Please see the viaduct construction guide which is attached below to find out how to get around during construction.

***North Temple Business Spotlight***

Serving Up Sweet Treats with Old Time Flare

Amid an economic tightening of belts, Leatherbys wants to ensure its patrons have to loosen theirs with a collective sigh. Leatherbys is an ice-cream lover's paradise, playing an integral role in not only delivering gourmet ice-cream, but opportunity for an expanding community as well.

The family-owned and operated ice cream eatery first opened its doors on North Temple and 735 West near the heart of downtown in March of 2004, offering up the nostalgia of yesterday with a no fuss approach. Leatherbys offers a family-friendly dining experience that is great for any occasion. Celebrate anyone’s birthday, whether they are marking one or 100 birthdays, come discover the real taste of ice cream at Leatherbys.

Just as it is close to everything downtown, but far enough away to provide free parking, Leatherbys offers wholesome and affordable food for those who enjoy all that Salt Lake City has to offer. Leatherbys has a variety of desserts that will satisfy any sweet tooth and compliment each event -- whether it’s a play at Capital Theatre, celebrating the Ute’s win, or watching a Jazz play-off game or concert. Dive in to the bliss of a Black and Tan Sundae topped with homemade caramel and chocolate. Share a banana split with a co-worker, or enjoy the Raspberry Chocolate Rhapsody.

Leatherbys also offers a simple yet satisfying menu that would be worthy of “grandma's” cooking. Try a local favorite, the Pastrami Burger, or experience the thrill of a Bar-B-Que Roundup....all served on homemade buns. Bacon Cheeseburgers, Philly Cheesteaks, fish and chips, and freshly made soups and salads are always available, made when you order and guaranteed to not only leave you full, but more importantly, satisfied.





General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending on conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.