Friday, December 05, 2008

Front Runner South Construction Update

Salt Lake City Intermodal HubImage via Wikipedia

Greetings,

Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line.

Below is the FrontRunner South quick construction update for the week of December 5.

For a more comprehensive construction update, click here.

Area 16 — Downtown Salt Lake City to 4500 South (Murray)

Construction Activity:

A lot of progress has been made with fiber optic relocations in Area 16 between Murray and Salt Lake City along the eventual FrontRunner trackway.

Traffic Impacts:

There are currently no traffic impacts in this area.

Salt Lake Central Station:

Station complete.

Area 15 — 4500 South (Murray) to 7800 South (Midvale)

Construction Activity:

Significant progress has also been made with fiber optic relocations taking place in Area 15. It is anticipated that the fiber optic relocation work is more than 50% complete in this area.

Traffic Impacts:

None.

Murray-5300 South Station:

No station construction activities to report.

Area 14 — 7800 South (Midvale) to Bangerter Highway (Draper/Bluffdale)

Construction Activity:

Progress continues in Area 14 behind Salt Lake Community College’s campus at 9800 South in anticipation for work on a flyover bridge to be built in this area. Crews have driven steel pile into the ground to build the base of this structure.

Traffic Impacts:

There are no traffic impacts to report at this time.

South Jordan/Sandy Station:

No station construction activities to report.

Area 13 — Bangerter Highway (Draper/Bluffdale) to Thanksgiving Point (Lehi)

Construction Activity:

Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi and throughout the Jordan Narrows. Excavation is currently taking place along the east side of the Jordan Narrows. Crews have started work on the South Jordan Canal in this area as well as embankment improvements.

Traffic Impacts:

Impacts to motorists should be minimal as work proceeds along the railroad right-of-way.

Draper/Bluffdale Station:

No station construction activities to report.

Lehi Station:

No station construction activities to report.

Area 12 — Thanksgiving Point (Lehi) to Main Street (American Fork)

Construction Activity:

Construction will once again begin in this area around the first week of February. A lot of progress has already been made at the Lehi Park and Ride Lot near Thanksgiving Point. When construction resumes, crews will continue work at the park and ride lot and the pedestrian tunnel that will run underneath the Union Pacific trackway.

Traffic Impacts:

There are currently no impacts to motorists in this area.

American Fork-Main St. Station:

Currently construction is not taking place at this station.

Area 11 — Main Street (American Fork) to 800 South (Orem)

Construction Activity:

Drainage improvements continue to take place along the Union Pacific Railroad tracks from Orem to American Fork. Third party utility work is also progressing north through this area.

Traffic Impacts:

There are currently no impacts to motorists in this area.

Orem Station:

No station construction activities to report.

Area 10 — 800 South (Orem) to Center Street (Provo)

Construction Activity:

Progress continues in Area 10 along the Union Pacific Railroad corridor between University Parkway in Orem and West Center Street in Provo. Crews continue to prepare a path for FrontRunner by grading and clearing the right-of-way and relocating water lines. Since an additional track is being constructed for FrontRunner operations, any existing box culvert or waterway must be extended under the newly built trackway.

Mainline duct bank installation also continues in Area 10. This duct bank will hold the fiber optics for the FrontRunner System.

Traffic Impacts:

Impacts to motorists are currently anticipated to be minimal as most work in this area is taking place along the rail corridor.

Provo Station-University Ave. Station:

No station construction activities to report.

Reblog this post [with Zemanta]

No comments: