Greetings,
Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line.
Below is the FrontRunner South quick construction update for the week of December 5.
For a more comprehensive construction update, click here.
Area 16 — Downtown |
Construction Activity: A lot of progress has been made with fiber optic relocations in Area 16 between Traffic Impacts: There are currently no traffic impacts in this area. Station complete. |
Area 15 — 4500 South (Murray) to 7800 South (Midvale) |
Construction Activity: Significant progress has also been made with fiber optic relocations taking place in Area 15. It is anticipated that the fiber optic relocation work is more than 50% complete in this area. Traffic Impacts: None. Murray-5300 South Station: No station construction activities to report. |
Area 14 — 7800 South (Midvale) to |
Construction Activity: Progress continues in Area 14 behind Traffic Impacts: There are no traffic impacts to report at this time. South Jordan/Sandy Station: No station construction activities to report. |
Area 13 — |
Construction Activity: Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi and throughout the Traffic Impacts: Impacts to motorists should be minimal as work proceeds along the railroad right-of-way. Draper/Bluffdale Station: No station construction activities to report. Lehi Station: No station construction activities to report. |
Area 12 — Thanksgiving Point (Lehi) to |
Construction Activity: Construction will once again begin in this area around the first week of February. A lot of progress has already been made at the Traffic Impacts: There are currently no impacts to motorists in this area. American Fork-Main St. Station: Currently construction is not taking place at this station. |
Area 11 — Main Street (American Fork) to 800 South ( |
Construction Activity: Drainage improvements continue to take place along the Union Pacific Railroad tracks from Traffic Impacts: There are currently no impacts to motorists in this area. No station construction activities to report. |
Area 10 — 800 South ( |
Construction Activity: Progress continues in Area 10 along the Union Pacific Railroad corridor between Mainline duct bank installation also continues in Area 10. This duct bank will hold the fiber optics for the FrontRunner System. Traffic Impacts: Impacts to motorists are currently anticipated to be minimal as most work in this area is taking place along the rail corridor. No station construction activities to report. |
No comments:
Post a Comment