West Valley TRAX Update

A TRAX train passing the Frank E.Image via Wikipedia

Currently, construction is taking place in all reaches.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.


Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.

Current Construction: TRAX construction is taking place in conjunction with UTA’s bus rapid transit project on Market Street. Crews are working in between West Valley City Hall and the Public Safety Building. Watch for project signs in the work areas that display West Valley TRAX Line fact sheets for more information.

Other work taking place in this area includes third party utility relocations along Constitution Boulevard, and excavation and utility work near West Valley City Center.

Upcoming Construction: Construction is scheduled to begin on 2700 West from 3500 South to 3100 South during December. This work will mainly include utility relocations and will proceed along the side of the roadway. Impacts to motorists should be minimal when this work begins. As we get closer to construction, we will meet with all residents to discuss how to minimize impacts.

We want to thank the residents bordering Constitution Boulevard for working with us during the pre-construction phase of this project. As work progresses, we will keep in contact to help mitigate any issues that may arise.

Traffic Impacts: Current impacts to motorists should be minimal; however, there will be minor lane restrictions as utility companies work along Constitution Boulevard.

Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained in this reach and we will work with The E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.

Current Construction: Construction has begun on the TRAX bridge over I-215 on the south side of 3100 South. The foundation work for this structure includes driving steel pile into the ground using a machine that may generate significant noise and vibration for local residents. To help alleviate impacts, pile driving activities will take place over the next few weeks and will be limited to the hours of 7:00 a.m. to 5:00 p.m. Monday through Friday. Construction will also include minor lane restrictions periodically on I-215 throughout the next couple of months.

Upcoming Construction: Construction will continue on the TRAX bridge over I-215 for the next several months. Utility work will also begin on 3100 South near The E Center and Decker Lake Drive during the first couple of weeks of January 2009.

Traffic Impacts: There will be some lane restrictions on I-215 as crews progress with bridge construction. We will work with the partnering agencies to notify travelling motorists about possible lane restrictions in this area.





Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties throughout construction.

Current Construction: The majority of construction on the West Valley Line has taken place in this reach on the east side of Redwood Road. Crews are now installing a permanent wall along both sides of the Crosstowne Trail. Significant drainage and irrigation work has been accomplished as well as foundation work for TRAX’s overhead wiring system. A permanent fence has been installed just east of the Brighton Canal to the Khadeeja Islamic Center on Parkway Avenue.

Upcoming Construction: Sound wall installation in the Chesterfield neighborhood is anticipated to take place over the next couple of months.

Traffic Impacts:

· The Crosstowne Trail along 2770 south just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will once again be operational.

Reach 5

Reach Description: Reach 5 will include construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.

Current Construction: The majority of construction is third party utility work taking place on 1070 West just north of Parkway Avenue. There will be some lane restrictions as a joint trench for utilities and sewer line is dug along 1070 West, along with pile driving for a retaining wall.

Traffic Impacts: As construction proceeds, there will be some lane restrictions. However, we will maintain access at all times.

Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel is maintained. Reach 6 will include an extensive bridging system that will enable TRAX to operate above ground, over other train traffic.

Current Construction: Crews have installed steel piles 120’ into the ground to form the main foundations for the aerial bridge that will carry TRAX over the Union Pacific Railroad tracks. Crews are currently pouring concrete to form the columns for the bridge. Utility work is also taking place.

Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.

Traffic Impacts: Not applicable.

Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current North/South TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained at all times.

Current Construction: Storm drain installation along Andy Avenue has been completed. We thank the businesses in this area for their support during this phase of construction.

Upcoming Construction: The next phase of construction will begin near Andy Avenue next Spring. We will continue to work with businesses to maintain access and mitigate any issues that may arise.

Traffic Impacts: Access will be maintained at all times during construction.

General Information

Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where temporary access might be required.

Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.

Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.

For More Information

Timely and helpful information is available to assist businesses and residential communities, as well as commuters and stakeholders.

If you have further questions not answered by this report or any comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.

Please note that construction information provided is subject to change.