Mid-Jordan Light Rail TRAX Construction Update: January 10, 2009*
Please forward this information on to others that would be interested.
*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.
Activity: Crews have removed the median barrier in the area of approximately 8700 South and
Sugar Factory Area
NEW Activity: Crews will be performing work in the area of 2200 West and
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Old Bingham Area
Activity: Crews continue to work on
Activity: Access to
Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th, 2008 on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.
Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Activity: Crews are continuing access and utility work near 300 West and the intersection of
If you have any questions or concerns regarding the project, please let me know.