Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line.

Below is the FrontRunner South quick construction update for January 17 - 26.

To learn more about the FrontRunner South project, click here.

Area 16 — Downtown Salt Lake City to 4500 South (Murray)

Construction Activity:

There will be no construction occurring in the area this week.

Traffic Impacts:

There are currently no traffic impacts in this area.

Salt Lake Central Station:

Station complete.

Area 15 — 4500 South (Murray) to 7800 South (Midvale)

Construction Activity:

Fiber optic relocations continue in the area with boring taking place at 5300 South, I-215 and 7200 South this week.

Traffic Impacts:

None.

Murray-5300 South Station:

No station construction activities to report.

Area 14 — 7800 South (Midvale) to Bangerter Highway (Draper/Bluffdale)

Construction Activity:

Progress continues in Area 14 behind Salt Lake Community College’s campus at 9800 South as crews construct a bridge that flies over the Union Pacific Railroad tracks. This is the area where FrontRunner will move from the east side to the west side of the tracks. Crews have driven steel pile into the ground to build the base of this structure and are continuing to construct rebar cages for drilled shafts. They will drill and pour one pier this week.

Crews are also constructing a bridge adjacent to the current Union Pacific Railroad bridge at 144th South. Crews will form and pour concrete for the back walls of the structure this week. We thank motorists in this area for their patience and support during construction.

Fiber optic work continues with boring taking place at 100th South and 123rd South.

Traffic Impacts:

A temporary traffic light has been placed at 144th South and the Union Pacific Bridge to help with traffic flow in this area.

South Jordan/Sandy Station:

No station construction activities to report.

Area 14 – Concrete is poured for the north abutment of a bridge adjacent to the current Union Pacific Railroad bridge at 144th South.

Area 13 — Bangerter Highway (Draper/Bluffdale) to Thanksgiving Point (Lehi)

Construction Activity:

Crews continue to establish access in this area and prepare the site along the railroad corridor in Bluffdale and Lehi. Excavation and embankment work throughout the area will continue this week as will fiber optic microduct installation.

Crews will form and pour concrete for the floor slab and aprons of a bridge spanning the East Jordan Canal. They will also begin to form the walls.

Traffic Impacts:

Impacts to motorists should be minimal as work proceeds along the railroad right-of-way.

Draper/Bluffdale Station:

No station construction activities to report.

Area 12 — Thanksgiving Point (Lehi) to Main Street (American Fork)

Construction Activity:

Crews will continue to work on temporary shoring for construction of the pedestrian tunnel that will run underneath the Union Pacific trackway at the Lehi Station.

Fiber optic work continues throughout the area with boring at roads and microduct installation taking place this week.

Traffic Impacts:

There are currently no impacts to motorists in this area.

Lehi Station:

No station construction activities to report.

American Fork-Main St. Station:

Currently construction is not taking place at this station.

Area 11 — Main Street (American Fork) to 800 South (Orem)

Construction Activity:

Drainage and irrigation improvements and embankment work continues along the Union Pacific Railroad tracks from Orem to American Fork.

Construction is underway for a bridge spanning the American Fork River. Crews will continue to form and tie rebar for the north and south abutments this week.

Traffic Impacts:

There are currently no impacts to motorists in this area.

Orem Station:

No station construction activities to report.

Area 10 — 800 South (Orem) to Center Street (Provo)

Construction Activity:

Significant progress has been made in Area 10 along the Union Pacific Railroad corridor between University Parkway in Orem and West Center Street in Provo. Crews have prepared a path for FrontRunner by grading and clearing the right-of-way and relocating water lines.

Crews will begin fiber optic microduct installation throughout the area this week.

Traffic Impacts:

There are currently no impacts to motorists in this area.

Provo Station-University Ave. Station:

No station construction activities to report.

Thanks again for your interest in the FrontRunner South project. If you have construction related questions, please call our 24-hour construction hotline number at 1-888-800-8854. If you have specific questions about the FrontRunner South project, my contact information is listed below. To unsubscribe from this list, please click here, or simply send a reply message indicating you wish to unsubscribe.

Regards,

Marc Bowman
UTA Community Involvement Specialist
www.rideuta.com
801.236.4784