Friday, February 20, 2009

West Valley TRAX Update

I created this map with ESRI software and Utah...Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.

Currently, construction is taking place in all reaches.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.


Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.

Current Construction: TRAX construction is taking place in conjunction with UTA’s bus rapid transit project on Market Street. Crews are currently working on the station platform between West Valley City Hall and the Public Safety Building. Pedestrian access is being maintained, watch for way-finding signs and project fact sheets for more information.

Upcoming Construction: Work has extended into Market Street as crews begin work on the station platform.

Traffic Impacts: Market Street is closed for north/south traffic between 3650 South and Lehmann Avenue.

Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained throughout construction and we will work with the E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.

Current Construction: Progress has been made on the TRAX bridge over I-215 on the south side of 3100 South. Crews have now moved the crane from the west side to the east side of I-215. The foundation work for this structure includes driving steel pile into the ground using a machine that may generate significant noise and vibration for local residents. To help alleviate impacts, pile driving activities will be limited to the hours of 7:00 a.m. to 5:00 p.m. Monday through Friday.

Work on the south side of 3100 South near the E Center continues as crews prepare the way for TRAX.

Upcoming Construction: The intersection at Mapleway and 3100 South will be closed to traffic for the next two to three weeks from 7:00 a.m. to 5:30 p.m. Motorist are encouraged to use 3360 South during the daytime hours. Pedestrian access will be maintained at all times through this closure.

Traffic Impacts: There will be some lane restrictions on I-215 as crews progress with bridge construction.

Reach 3

Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis. We will continually work to ensure access is provided.

Current Construction: Construction continues on Decker Lake Drive as crews work on the storm drain on the east side of the road. Access is being maintained and we thank the businesses and motorists for their support during construction.

Upcoming Construction: Construction is anticipated to take place along Decker Lake Drive throughout the next several months.

Traffic Impacts: Access to businesses is being maintained.

Please be mindful of workers and obey posted speed limits.

Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties.

Current Construction: Crews have installed a permanent wall along both sides of the Crosstowne Trail in Chesterfield. Significant drainage and irrigation work has also been accomplished, as well as foundation work for TRAX’s overhead wiring system. We would like to thank the residents for their patience during construction.

Upcoming Construction: This coming spring, crews will backfill the area along the new fence on each resident’s property.

Traffic Impacts:

· The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will once again be operational.



Reach 5

Reach Description: Reach 5 includes construction along 1070 West in the Chesterfield industrial area. This reach will include a bridge structure over the Jordan River and another over 900 West.

Current Construction: The majority of construction in this area is taking place on 1070 West just north of Parkway Avenue. Third party utility work is currently taking place. There will be some lane restrictions implemented. Work on a joint trench for utilities and a sewer line is taking place along 1070 West, as well as pile driving for a retaining wall.

Upcoming Construction: Construction is anticipated to take place for the next several months. After the third party utilities are completed, crews will begin construction.

Traffic Impacts: As construction proceeds, there will be lane restrictions. However, access will be maintained at all times.

Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents in this reach, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel will be maintained. Reach 6 will include an extensive bridging system that will enable TRAX to operate above ground, over other train traffic.

Current Construction: Progress has been made on the overhead structure in roper yard. Crews have installed steel piles 120’ into the ground to form the main foundations for the aerial bridge.

Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.

Traffic Impacts: Not applicable. This is a Union Pacific Railroad work area.

Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current North/South TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained. A construction survey has been conducted with the businesses along 400 West between Andy Avenue and 2100 South to determine the best time to construct in the Andy Avenue/600 West intersection. We will get back to businesses to deliver the survey results and ensure adequate access.

Current Construction: Storm drain installation along Andy Avenue has been completed. We thank the businesses for their support.

Upcoming Construction: The next phase of construction will begin near Andy Avenue next spring. We will continue to work with businesses to maintain access and mitigate any issues that may arise.

Traffic Impacts: Access will be maintained during construction.

General Information

Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access might be temporarily limited.

Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.

Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.

For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.

If you have further questions or any comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.

Please note that construction information provided is subject to change.