Mid-Jordan Light Rail TRAX Construction Update: February 26, 2009*

Please forward this information on to others that would be interested.

*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.

Bangerter Bridge

Activity: Crews have removed the median barrier in the area of approximately 8700 South and Bangerter Highway (just south of the Old Bingham Highway overpass). The median has been replaced with water barrels and will remain closed through mid-February.

UPDATED Activity: Crews will be performing work on the bridge structure at approximately 8700 South and Bangerter Highway. Traffic Impacts: The centermost lane in each direction will be closed on Bangerter Highway from January 26th through March 13th.

Sugar Factory Area

Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.

UPDATED Activity: Crews continue to work on the sound wall on the north side of Sugar Factory Road between 2200 West and approximately 2450 West. Traffic Impacts: Traffic has been shifted to the east side of 2200 West until February 27th.

Old Bingham Area

UPDATED Activity: Crews continue to work on Old Bingham Highway near the Bangerter Bridge overpass. Traffic Impacts: Traffic will be restricted to one lane with flagging operations at the overpass on February 25th and March 5th through the 10th, except on the weekend.

NEW Activity: Survey work will be taking place at the 9000 South grade crossing. Traffic Impacts: Traffic will be subject to traveling closures for surveyors working in the area on Thursday, February 26th. Please be aware.

Gardner Village Area

NEW Activity: Crews will be resuming work on the bridge at 7800 South near Gardner Village. Traffic Impacts: Westbound traffic will be shifted to the south side of 7800 South on March 9th until March 13th.

Activity: Crews are performing utility work on 1300 West at the trackway (approximately 7900 South). Traffic Impacts: 1300 West is completely closed at the trackway until March 2nd. Please plan accordingly.

Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.

Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th, 2008 on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.

Cottonwood Area

Activity: Crews are continuing access and utility work near 300 West and the intersection of Winchester Street and Cottonwood Street. Traffic Impacts: Shoulder work with lane restrictions.

If you have any questions or concerns regarding the project, please let me know.

Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783

sloughlin@rideuta.com