Mid-Jordan Light Rail TRAX Construction Update: October 30, 2008*
Please forward this information on to others that would be interested.
*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.
NEW - Progress Highlight: Daybreak
This section highlights project milestones and progress. There are no traffic impacts associated with this section.
The OCS (overhead catenary system) foundations, communications backbone, and drain work have been completed within Daybreak to the existing track at 5600 West. Initial ballast has been placed south of Bingham Creek and is anticipated to be completed to the existing track this week.
Bangerter Bridge
Activity: Crews have removed the median barrier in the area of approximately 8700 South and Bangerter Highway (just south of the Old Bingham Highway overpass). The median has been replaced with water barrels and remains closed through December.
Sugar Factory Area
Activity: Construction of sound wall along right-of-way rail corridor between 2700 West and 3200 West will begin on October 6th and will continue through November.
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Old Bingham Area
Activity: Crews will be removing a median barrier beneath the Old Bingham Highway Bridge. Traffic Impacts: From October 20th through November 2nd, Old Bingham Highway will have one lane open with flagging operations at the Bangerter overcrossing.
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Gardner Village Area
Activity: Crews are working on the new bridge construction at 7800 South near Gardner Village. Traffic Impacts: Westbound traffic will be shifted to the south side of the roadway at the railroad overcrossing with flagging operations at Gardner Village entrances through November 8.
Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.
Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.
Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.
Cottonwood Area
Activity: Construction on Cottonwood Street will begin on September 2nd and will continue through mid-November. Traffic Impacts: Lane restrictions and closures as follows:
· Northbound travel on Cottonwood Street will be closed between Winchester Street and 6500 South for the duration of construction. Southbound travel will remain open and traffic will be shifted to the east side of the roadway while crews reconstruct the west side. Once construction on the west side is complete, traffic will be switched to the west side of the roadway to allow crews to reconstruct the east side.
· Cottonwood Street will accommodate southbound traffic only between Winchester Street and 6500 South. Please use 700 West or State Street as detour routes. Detour signs will be posted.
Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to Winchester Street, and closed to through traffic at 6100 South. Local business access will be available on 300 West between 6100 South and 6300 South.