Mid-Jordan Light Rail TRAX Construction Update: October 22, 2008*
Please forward this information on to others that would be interested.
*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.
Activity: Crews will be drilling in preparation for the main center pier in the median area at approximately 8700 South (just south of the
Sugar Factory Area
Activity: Construction of sound wall along right-of-way rail corridor between 2700 West and 3200 West will begin on October 6th and will continue through November.
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Old Bingham Area
Activity: Crews will be removing a median barrier beneath the
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Activity: Access to
Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: A temporary detour began the week of October 13th on the Jordan River Parkway Trail near approximately 7500 South. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.
Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.
Activity: Construction on
· Northbound travel on
·
Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to
If you have any question or concerns regarding the project, please let me know.
Sarah Loughlin
Community Involvement Specialist
801-236-4783
No comments: