Jordan Line Update

Rail tracks.Image via WikipediaMid-Jordan Light Rail TRAX Construction Update: October 1, 2008*

Please forward this information on to others that would be interested.



*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Bangerter Bridge



Activity: Crews will be removing the median barrier in the area of approximately 8700 South (near the Old Bingham Highway overpass). Traffic Impacts: Northbound and southbound centermost lanes will be closed from 9:00 a.m. to 4:00 p.m. on October 13th through October 17th. The median will be replaced with water barrels and remain closed through early December.



Activity: Crews will be drilling in the median area at approximately 8700 South (near the Old Bingham Highway overpass). Traffic Impacts: The Old Bingham Highway overpass at Bangerter Highway and the northbound centermost lane and southbound centermost and center lanes of Bangerter Highway will be closed from 9:00 p.m. on October 24th through 5:00 a.m. on October 27th.



Sugar Factory Area



Activity: Construction of sound wall along right-of-way rail corridor between 2700 West and 3200 West will begin on October 6th and will continue through early November.



Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.



Old Bingham Area



Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.



Gardner Village Area



Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.



Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: The Jordan River Parkway Trail will start a temporary detour near approximately 7500 South in early October. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.



Activity: Construction on retaining walls at 7800 South near Gardner Village began on June 30th and is currently ongoing. Traffic Impacts: There will be a designated truck turning lane on the north side of 7800 South accessing the Gardner Village property. Flagging operations will be in place as trucks enter and exit the roadway. To accommodate this construction, the eastbound lane on the south side of 7800 South will be closed as necessary starting on August 6th.



Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.



Cottonwood Area



Activity: Construction on Cottonwood Street will begin on September 2nd and will continue through mid-November. Traffic Impacts: Lane restrictions and closures as follows:

· Northbound travel on Cottonwood Street will be closed between Winchester Street and 6500 South for the duration of construction. Southbound travel will remain open and traffic will be shifted to the east side of the roadway while crews reconstruct the west side. Once construction on the west side is complete, traffic will be switched to the west side of the roadway to allow crews to reconstruct the east side.

· Cottonwood Street will accommodate southbound traffic only between Winchester Street and 6500 South. Please use 700 West or State Street as detour routes. Detour signs will be posted.



Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to Winchester Street, and closed to through traffic at 6100 South. Local business access will be available on 300 West between 6100 South and 6300 South.



If you have any question or concerns regarding the project, please let me know.



Sarah Loughlin

Community Involvement Specialist

Utah Transit Authority

801-236-4783

sloughlin@rideuta.com



You have been included on the Mid-Jordan Light Rail TRAX Construction Update project update email list. Each time the construction schedule is updated, you will receive an email notifying you of the update. If you would like to be removed from this list, simply send an email stating so.