Mid Jordan TRAX Construction Update

Gallivan Plaza TRAXImage by Steven Vance via Flickr
UTA Mid-Jordan TRAX Line Weekly Construction Update: September 24, 2010

* Traffic on 7800 South in West Jordan will be subject to lane shifts continuing through early October.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.


The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line.

It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing is ongoing in Daybreak. Crews continue installing canopy components including bench brackets and side slats. Crews will also be cleaning up at the 5600 West park & ride.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Miscellaneous track work continues in this segment. Crews will be striping the 4800 West park & ride.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Work moves forward for the entrance to the West Jordan City Center park & ride. Light pole foundations are being poured. Track and overhead catenary system (OCS) work continues in this segment.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

Canopies are scheduled to be erected at the Bingham Junction station, and ADA ramps are scheduled to be poured as well. Landscaping continues at the Historic Gardner park & ride.



ACTIVITY: Bridge repairs at 7800 South

TRAFFIC IMPACT: 7800 South will have lane shifts in place through early October.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Grading crews continue working at the Fashion Place park & ride, and curb, gutter and sidewalks are being constructed. The canopies are scheduled to be painted, and the dirt parking lot south of the Y tracks is scheduled for grading prior to being paved in early October. OCS and electrical work continues.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.
Enhanced by Zemanta

Saturday, September 11, 2010

Mid Jordan TRAX Construction Update

Gallivan Plaza TRAXImage by Steven Vance via Flickr
UTA Mid-Jordan TRAX Line Weekly Construction Update: September 10, 2010

* Winchester Street will remain closed at the TRAX crossing through Friday, September 17.

* Traffic on 7800 South in West Jordan will be subject to lane shifts continuing through mid-September.

* Night work near Winchester Street will continue through Saturday, September 11.

* 3200 West will remain closed at 8600 South in West Jordan through September 17.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.

The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad.

At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing is ongoing in Daybreak. Crews are installing canopy components (such as slats and roof panels).

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Canopy work continues at 4800 West. Crews continue preparing the berms for hydroseeding, and signal and communications equipment is being installed.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Work at the 3200 West crossing will be completed next week. Crews will be installing and regulating overhead catenary system (OCS) wire from Redwood Road to Gardner Village.



* ACTIVITY: Installation of storm drain, new asphalt, curb, gutter and concrete medians at 3200 West

TRAFFIC IMPACT: 3200 West will be closed at the intersection with 8600 West through September 17.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

Landscaping work is going on at Gardner Village. The station canopies at Gardner Village will be painted, and fiber optic cable is being installed.



ACTIVITY: Bridge repairs at 7800 South

TRAFFIC IMPACT: 7800 South will have lane shifts in place through mid-September.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Cottonwood Street and Winchester Street will be paved next week. Grading crews will be working at the Fashion Place park & ride, and concrete will be poured for the platform ramps and landings. Work continues with track and OCS in Lovendahl Yard.



* ACTIVITY: Construction of new curb and gutter, sidewalk, concrete medians and repaving of Winchester Street.

TRAFFIC IMPACT: Winchester Street will be closed between Cottonwood Street and the TRAX crossing through September 17.



ACTIVITY: Installation of OCS poles, wires, and power and signal equipment south of Winchester Street

IMPACT: Work will take place during overnight hours Saturday night, July 24 through Saturday night, September 11.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.
Enhanced by Zemanta

Saturday, August 14, 2010

Mid Jordan TRAX Construction Update




UTA Mid-Jordan TRAX Line Weekly Construction Update: August 13, 2010



* Cottonwood Street will be closed between Winchester Street and 6500 South from Monday, August 16 through Thursday, September 2.

* Traffic on 7800 South in West Jordan will be subject to lane shifts continuing through mid-September.

* Night work near Winchester Street will continue through Saturday, September 11.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad.

At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing is ongoing in Daybreak. Crews will be painting station canopy frames and finishing landscaping at the park & rides.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews continue installing drainage and finishing the concrete channel along Old Bingham Highway. Crews will begin removing weeds from the sound berm, and the signals at 5200 West and 4000 West are scheduled for activation this week.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Grading work continues at the Redwood park & ride, and curbs and gutters are scheduled for pouring this week. Crews are also scheduled to paint the canopy at the Redwood station platform. Landscaping continues at the 2700 West park & ride. Crews continue to string overhead catenary system (OCS) wire from Redwood road to Gardner Village.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

Work on the 7800 South bridge moves forward as construction crews paint the new bridge and conduct repairs on the old one. The Gardner Village park & ride is scheduled to be paved this week, and the concrete for the station platform will be poured.



ACTIVITY: Bridge repairs at 7800 South

TRAFFIC IMPACT: 7800 South will have lane shifts in place through mid-September.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

The new Mid-Jordan track is being installed west of the new station platform at Fashion Place station. This week, grading operations will begin for the new park & ride lot west of Fashion Place station, and OCS wire is being installed and tested.



* ACTIVITY: Reconstruction of Cottonwood Street in cooperation with Murray City.

TRAFFIC IMPACT: Cottonwood Street will be closed between Winchester Street and 6500 South from Monday, August 16 through Thursday, September 2.



ACTIVITY: Installation of OCS poles, wires, and power and signal equipment south of Winchester Street

IMPACT: Work will take place during overnight hours Saturday night, July 24 through Saturday night, September 11.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.

Saturday, August 07, 2010

Mid Jordan TRAX Construction Update

Gallivan Plaza TRAXImage by Steven Vance via Flickr


UTA Mid-Jordan TRAX Line Weekly Construction Update: August 4, 2010



* Cottonwood Street will be closed between Winchester Street and 6500 South from Monday, August 16 through Thursday, September 2.

* Traffic on 7800 South in West Jordan will be subject to lane shifts continuing through mid-September.

* Night work near Winchester Street will continue through Saturday, September 11.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development.

For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing is ongoing in Daybreak. Crews will be installing roof panels at the station canopies.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews continue installing drainage and modifying the concrete channel along Old Bingham Highway. Landscape work at the 4800 West park & ride is nearly complete. The traffic signal at 5200 West will be activated soon.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Grading work continues at the Redwood park & ride, prior to construction of curbing, gutters and asphalt paving. Concrete work continues at the Redwood station platform, and landscaping begins at the 2700 West park & ride. Crews continue to string overhead catenary system (OCS) wire.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

Work on the 7800 South bridge moves forward as construction crews paint the new bridge and conduct repairs on the old one. The Gardner Village park & ride is scheduled to be paved next week. OCS poles are being erected in this segment, and track work moves continues.



ACTIVITY: Bridge repairs at 7800 South

TRAFFIC IMPACT: 7800 South will have lane shifts in place through mid-September.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.



* NEW ACTIVITY: Reconstruction of Cottonwood Street in cooperation with Murray City.

TRAFFIC IMPACT: Cottonwood Street will be closed between Winchester Street and 6500 South from Monday, August 16 through Thursday, September 2.



ACTIVITY: Installation of OCS poles, wires, and power and signal equipment south of Winchester Street

IMPACT: Work will take place during overnight hours Saturday night, July 24 through Saturday night, September 11.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.

Enhanced by Zemanta

Sunday, August 01, 2010

Mid Jordan TRAX Construction Update

A Siemens LRV in service with UTA TRAX. The ba...Image via Wikipedia



UTA Mid-Jordan TRAX Line Weekly Construction Update: July 30, 2010



* 1300 West will be closed at the railroad crossing (approximately 7950 South) from Monday, July 26 through Friday, July 30. It will reopen Saturday, July 31.

* Night work near Winchester Street will take place from Saturday night, July 24 through Saturday, August 21.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad.

At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing is ongoing in Daybreak. Painting the station canopies continues this week, as well as prep work prior to installation of roof panels. Crews will also be installing signs and striping at the Daybreak park & ride lots.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews continue installing drainage and modifying the concrete channel along Old Bingham Highway. Weed removal is in progress. Landscape work at the 4800 West park & ride continues with planting of trees and bushes. Minor track improvements are also taking place.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Electrical work and light pole foundation installation continues at the Redwood park & ride. The station canopy at Redwood is scheduled for installation this week. Crews continue to string overhead catenary system (OCS) wire and install balance weight assemblies.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

Crews are scheduled to begin forming and pouring concrete for the Gardner Village platform. Track work in this section is ongoing as crews lay new track across the Jordan River and 7800 South bridges. Work continues to prepare the Gardner Village Park & Ride lot for paving in early August. The 1300 West grade crossing work should be completed today, and the road will reopen Saturday morning, July 31.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.



* ACTIVITY: Installation of OCS poles, wires, and power and signal equipment south of Winchester Street

* IMPACT: Work will take place during overnight hours Saturday night, July 24 through Saturday night, August 21.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.

Enhanced by Zemanta

Saturday, July 24, 2010

Mid Jordan TRAX Construction Update




UTA Mid-Jordan TRAX Line Weekly Construction Update: July 22, 2010



* 1300 West will be closed at the railroad crossing (approximately 7950 South) from Monday, July 26 through Friday, July 30. It will reopen Saturday, July 31.

* Night work near Winchester Street will take place intermittently from Saturday night, July 24 through Saturday, August 21.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line.

It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing continues in Daybreak. Crews are scheduled to begin painting the station canopies this week. Crews will also be installing signs and striping at the Daybreak park & ride lots.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews continue installing drainage and modifying the concrete channel along Old Bingham Highway. Weed removal is in progress. Landscape work at the 4800 West park & ride is moving forward, as well as installation of electrical and fiber optic equipment.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Canopy frames at Bangerter and 2700 West stations are scheduled for painting. Concrete work is moving forward at the 2700 West and Redwood platforms. Electrical work and light pole foundation installation will take place at the Redwood park & ride.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail will reopen this weekend. Concrete work is scheduled to begin at the Bingham Junction station in Midvale and the Gardner Village station. The 1300 West grade crossing is scheduled for reconstruction and installation of curb, gutter and concrete medians this week.



* NEW ACTIVITY: Construction of the 1300 West grade crossing.

TRAFFIC IMPACT: 1300 West will be closed at the rail crossing (approx. 7950 South) from Monday, July 26 through Friday, July 30.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.



* ACTIVITY: Installation of OCS poles, wires, and power and signal equipment south of Winchester Street

* IMPACT: Work will take place during overnight hours Saturday night, July 24 through Saturday night, August 21.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.

Sunday, July 18, 2010

Mid Jordan TRAX Construction Update

A train in Salt Lake City similar to what Omah...Image via Wikipedia



UTA Mid-Jordan TRAX Line Weekly Construction Update: July 16, 2010



* Cottonwood Street is closed to through traffic between Winchester Street and the I-215 bridge through Sunday, July 18. Business access will be maintained during the closure.

* Night work near Winchester Street will take place intermittently from Friday night, July 16 through next Friday, July 23.

* The Jordan River Parkway Trail is closed between 7800 South and the Jordan River through Tuesday, July 20 for additional embankment work and fence installation.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad.

At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



New vehicle testing continues in Daybreak. Trackwork is essentially complete, and crews are preparing to paint the canopies at the station platforms.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews continue installing drainage and modifying the concrete channel along Old Bingham Highway. Weed removal is in progress, and work to extend the sound berm at Wasatch Meadows continues this week.



* NEW ACTIVITY: Repaving at the 9000 South crossing

TRAFFIC IMPACT: 9000 South will be subject to lane closures from Monday, July 19 to Friday, July 23. Also, Old Bingham Highway will be closed from 9000 South to Wasatch Meadows Drive from Monday, July 19 through Wednesday, July 21.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Crews are installing overhead catenary system (OCS) poles and balance weight assemblies. Concrete work is moving forward at the 2700 West and Redwood platforms.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail between 7800 South and 7400 South is closed through Tuesday, July 20 while crews finish embankment work and install fencing along the UTA right-of-way. Concrete work is scheduled to begin at the Bingham Junction station in Midvale. Crews continue installing OCS (overhead catenary system) pole foundations between the Jordan River and Bingham Junction station. Grading at the Gardner Village park & ride lot is nearing completion, with paving scheduled near the end of the month.



* ACTIVITY: Fence installation along the Jordan River Parkway Trail.

TRAFFIC IMPACT: The Jordan River Parkway Trail will remain closed between 7800 South and the TRAX bridges near 7400 South through Tuesday, July 20.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.



* NEW ACTIVITY: Installation of track, OCS poles, wires, and power and signal equipment south of Winchester Street

* IMPACT: Work will take place during overnight hours Friday night, July 16 through Friday night, July 23



* ACTIVITY: Fabrication and installation of a new turnout switch at Fashion Place Station

*TRAFFIC IMPACT: Cottonwood Street will be closed to through traffic between Winchester Street and the I-215 bridge from Thursday, July 15 through Sunday, July 18. Business access will be maintained during the closure.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.
Enhanced by Zemanta

Saturday, July 10, 2010

Mid Jordan TRAX Construction Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia



UTA Mid-Jordan TRAX Line Weekly Construction Update: July 9, 2010



* Cottonwood Street will be closed to through traffic between Winchester Street and the I-215 bridge from Thursday, July 15 through Sunday, July 18. Business access will be maintained during the closure.

* Night work near Winchester Street will take place Friday night, July 9, and Saturday night, July 10 between 12 am and 8 am.

* The Jordan River Parkway Trail will be closed between 7800 South and the Jordan River through Tuesday, July 20 for additional embankment work and fence installation.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad.

At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Concrete and canopy work continues at station platforms in Daybreak. Crews continue working on landscaping at 5600 West, and testing of the new vehicles is ongoing.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews are completing installation of sound wall panels, and working to modify the drainage channel between 5200 West and 4800 West. Landscaping continues at the 4800 West Park & Ride, and electrical and signal work is ongoing.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Concrete work at Bangerter, 2700 West and Redwood Road continues. Crews have nearly completed paving of the 2700 West Park & Ride, and continue installation of traffic signals at 3200 West.


Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail between 7800 South and 7400 South is closed through Tuesday, July 20 while crews finish embankment work and install fencing along the UTA right-of-way. Crews continue installing OCS (overhead catenary system) pole foundations between the Jordan River and Bingham Junction station. Grading at the Gardner Village park & ride lot is nearing completion, with paving scheduled near the end of the month.



* ACTIVITY: Fence installation along the Jordan River Parkway Trail.

TRAFFIC IMPACT: The Jordan River Parkway Trail will remain closed between 7800 South and the TRAX bridges near 7400 South through Tuesday, July 20.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.



* NEW ACTIVITY: Installation of OCS foundations south of Winchester Street

* IMPACT: Work will take place during overnight hours Friday night, July 9, and Saturday night, July 10



* NEW ACTIVITY: Fabrication and installation of a new turnout switch at Fashion Place Station

*TRAFFIC IMPACT: Cottonwood Street will be closed to through traffic between Winchester Street and the I-215 bridge from Thursday, July 15 through Sunday, July 18. Business access will be maintained during the closure.


General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.

Enhanced by Zemanta

Friday, June 25, 2010

Mid Jordan TRAX Construction Update

A Siemens LRV in service with UTA TRAX. The ba...Image via Wikipedia



UTA Mid-Jordan TRAX Line Weekly Construction Update: June 25, 2010



* 2700 West will be closed between Sugar Factory Road and Spaulding Lane from Wednesday, June 30th through Friday, July 2. It will reopen on Saturday, July 3.

* Sugar Factory Road will be closed at 2700 West from Wednesday, June 30th through Friday, July 2. It will reopen on Saturday, July 3.

* The Jordan River Parkway Trail is now open in its permanent configuration. The temporary detour over the railroad tracks south of the Jordan River bridge has been

removed.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Concrete work continues at station platforms in Daybreak. Crews are also testing the new light rail vehicles in this segment.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews continue finishing concrete work on the 4800 West station platform. The sound berm extension on the west side of Wasatch Meadows has been rescheduled for this week. Crews will also be working to repair the drainage channel west of 4800 West.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Concrete work continues at the Bangerter and 2700 West station platforms – the canopies have been erected at Bangerter, and will soon be installed at 2700 West as well. OCS work progresses as well, as nearly all poles have been installed and wire is being hung.



* NEW ACTIVITY: Asphalt paving at the 2700 West railroad crossing.

TRAFFIC IMPACT: 2700 West will be closed at the railroad crossing from Wednesday, June 30

through Friday, July 2. Sugar Factory Road will be closed at 2700 West during this time.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail is now open. Work has now begun to shape the embankment just south of 7800 South. Workers continue installing OCS foundations between the Jordan River and Bingham Junction station. Grading at the Gardner Village park & ride lot and concrete work at the station platform are both scheduled for this week.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.


















Enhanced by Zemanta

Saturday, June 19, 2010

Mid Jordan TRAX Construction Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia


UTA Mid-Jordan TRAX Line Weekly Construction Update: June 18, 2010



UTA thanks everyone who attended the unveiling of its new light rail vehicles this morning. Construction of the Mid-Jordan TRAX extension is moving forward, and the line should be operational by late 2011.



* 5200 West will be closed at the railroad crossing on Saturday, June 19th from 7 am to 5 pm.

* The Jordan River Parkway Trail will reopen June 22.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Concrete work continues at station platforms in Daybreak. Crews are also testing the new light rail vehicles in this segment.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Crews are also repaving the railroad crossing at 5200 West, and finishing concrete work on the 4800 West station platform. Overhead catenary system (OCS) poles are being erected and arms are being installed near 4000 West.



* NEW ACTIVITY: Installation of new asphalt pavement at the railroad crossing on 5200 West.

TRAFFIC IMPACT: 5200 West will be closed Saturday, June 19 between 7 am and 5 pm.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Construction of the Redwood Road rail crossing is complete, and crews have nearly finished installing concrete medians and sidewalks. Concrete work is moving forward at the Bangerter and 2700 West station platforms. Crews are also working to complete track work in this segment.



* NEW ACTIVITY: Asphalt paving at the 2700 West railroad crossing.

TRAFFIC IMPACT: 2700 West will be closed at the railroad crossing from Wednesday, June 30

through Friday, July 2.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail will reopen Tuesday, June 22 as crews have nearly completed widening the embankment of the rail right-of-way between 7800 South and the Jordan River. Work has now begun to shape the embankment just south of 7800 South. Workers continue installing OCS foundations between the Jordan River and Bingham Junction station.



* ACTIVITY: Embankment work between the Jordan River and 7800 South.

TRAFFIC IMPACT: The Jordan River Parkway Trail will be closed from 7800 South to the Jordan River through Tuesday, June 22.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.




















Enhanced by Zemanta

Wednesday, June 16, 2010

New TRAX cars debut


While I have not had the opportunity to ride these cars yet (San Diego and Portland use them), I have heard good things about these from people in the Portland area. The down falls of low floor buses don't seem to apply to low floor rail vehicles. Sadly I will not be able to make this debut on Friday.

UTA to Debut New Light Rail Vehicles

What: UTA will introduce its new S70 light rail vehicles with an inaugural public ride on a new section of the Mid-Jordan TRAX line.

When: Friday, June 18, 10 a.m.

Where: 5600 West park and ride lot, Mid-Jordan TRAX line

5651 West Old Bingham Highway, West Jordan

Directions: Go west on 9000 South to 4800 West, then south to Old Bingham Highway and west to 5600 West

More Info:

· UTA has ordered 77 new light rail vehicles for its four new light rail lines: Airport, Draper, Mid-Jordan and West Valley

· New vehicles began arriving in March and are being tested on the newly completed Daybreak section of the Mid-Jordan TRAX line

· S70 light rail vehicles have low floors for platform-level boarding

· Doorways have deployable boarding ramps for greater accessibility

· The new vehicles are expected to first enter service in 2011

Saturday, June 12, 2010

Mid Jordan TRAX Construction Update

MA Siemens LRV in service with UTA TRAX. The ba...Image via Wikipedia



UTA Mid-Jordan TRAX Line Weekly Construction Update: June 11, 2010



UTA invites you to the unveiling of its new light rail vehicles on Friday, June 18 from 10 am to noon. The event, which is open to the public, will be held at the new 5600 West Park & Ride at 5651 West Old Bingham Highway in West Jordan. The inaugural ride on the new vehicles is scheduled for 10:30.



* Old Bingham Highway will be closed just west of 9000 South from Monday, June 14 through Thursday, June 17. Please use 4800 West as an alternate.

* 5200 West will be closed at the railroad crossing on Saturday, June 19th from 7 am to 5 pm.

* The Jordan River Parkway Trail will be closed from 7800 South north to the UTA Jordan River bridge for approximately two weeks, from June 8 through June 22.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Concrete work continues at station platforms in Daybreak. Crews are also testing the new light rail vehicles in this segment.


Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

This week, crews will resume installation of sound wall panels along Old Bingham Highway between 4000 West and Bangerter Highway. Crews are also installing a new storm drain under Old Bingham Highway just west of 9000 South, which will require Old Bingham Highway to be closed for four days at 9000 South. Residents and businesses can use 4800 West as an alternate. Crews are also repaving the railroad crossing at 5200 West.



* NEW ACTIVITY: Storm drain tie-in at Old Bingham Highway

TRAFFIC IMPACT: Old Bingham Highway will be closed just west of 9000 South from June 14 to June 17.



* NEW ACTIVITY: Installation of new asphalt pavement at the railroad crossing on 5200 West.

TRAFFIC IMPACT: 5200 West will be closed Saturday, June 19 between 7 am and 5 pm.



* NEW ACTIVITY: Installation of sound wall panels along Old Bingham Highway between 4000 South and Bangerter Highway

TRAFFIC IMPACT: Old Bingham Highway will be subject to intermittent lane closures beginning Monday, June 14.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Construction of the Redwood Road rail crossing is complete, and crews are installing concrete medians and sidewalks. Overhead catenary system (OCS) poles, arms and wire are being installed between 3200 West and 1300 West. Crews are also installing ballast and laying rail throughout this segment.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail will be closed between Tuesday, June 8 and Tuesday, June 22 as crews begin widening the embankment of the rail right-of-way between 7800 South and the Jordan River. Grading work is moving forward at the Gardner Village Park & Ride, and crews will begin work to install OCS foundations between the Jordan River and Bingham Junction station.



* ACTIVITY: Embankment work between the Jordan River and 7800 South.

TRAFFIC IMPACT: The Jordan River Parkway Trail will be closed from 7800 South to the Jordan River from Tuesday, June 8 through Tuesday, June 22.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Work is also progressing at the site of the future west platform at the Fashion Place station. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.


General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.


















Enhanced by Zemanta

Friday, June 04, 2010

Mid Jordan TRAX Construction Update

Jordan River Parkway in the Cottonwood Grove parkImage via Wikipedia





FOR IMMEDIATE RELEASE
Contact: Gerry Carpenter, 801-859-6095

Date: June 4, 2010 Press Release





Jordan River Parkway Closure
In Midvale for TRAX Construction





A section of the Jordan River Parkway trail near Gardner Village will close for two weeks beginning Tuesday, June 8, to accommodate TRAX construction in the area. The trail will reopen on June 23.



The closure will extend from 7800 South to approximately 7400 South in Midvale. There will be no trail detour for the duration of the work. The closure will allow construction crews to bring in fill material and widen the railroad embankment for the future Mid-Jordan TRAX line. This is the final trail closure related to this project.



Questions from the public regarding this closure should be directed to the Mid-Jordan TRAX construction hotline at (888) 550-2211.



UTA Mid-Jordan TRAX Line Weekly Construction Update: June 4, 2010



* Redwood Road will be closed at the railroad crossing at approximately 8050 South in West Jordan from 10 pm Saturday, June 5 through 2 pm Sunday, June 6. Please use an alternate route.

* The Jordan River Parkway Trail will be closed from 7800 South north to the UTA Jordan River bridge for approximately two weeks, from June 8 through June 22.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.





The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.


Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Work continues on the landscaping at the 5600 West station and Park & Ride. Crews are installing concrete bench foundations and ADA-accessible ramps at the station platforms.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Track and grading/drainage work is moving forward in Old Bingham. Crews are inspecting and testing overhead catenary system (OCS) poles and wires, and concrete curbing, sidewalks and gutters are being installed at the park & rides. This week, crews will resume installation of sound wall panels along Old Bingham Highway between 4000 West and Bangerter Highway.



* NEW ACTIVITY: Storm drain tie-in at Old Bingham Highway

TRAFFIC IMPACT: Old Bingham Highway will be closed just south of 9000 South from June 14 to June 18.



* NEW ACTIVITY: Installation of sound wall panels along Old Bingham Highway between 4000 South and Bangerter Highway

TRAFFIC IMPACT: Old Bingham Highway will be subject to intermittent lane closures beginning Monday, June 14.

Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Construction of the Redwood Road rail crossing is in progress. Concrete work is moving forward at the Bangerter and 2700 West station platforms, and foundations for OCS poles are being installed. Crews are also installing ballast and laying rail throughout this segment.



* NEW ACTIVITY: Rail installation at the Redwood Road rail crossing.

TRAFFIC IMPACT: Redwood Road will be closed from approximately 8020 South to 8150 South beginning Saturday night, June 5, at 10 pm. Redwood Road will reopen at 2 pm on Sunday, June 6.





* NEW ACTIVITY: Construction of the east half of the Redwood Road rail crossing.

TRAFFIC IMPACT: From 7 pm Friday, June 4 through 5 am Monday, June 7, all traffic on Redwood Road will be shifted to the west side of the street (the three northbound lanes) between 7600 South and 8600 South.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail will be closed between Tuesday, June 8 and Tuesday, June 22 as crews begin widening the embankment of the rail right-of-way between 7800 South and the Jordan River. Embankment work is in progress between 1300 South and 7800 South. Work continues at the Jordan River bridge and the 700 West bridge, and at the Gardner Village Park & Ride.



* NEW ACTIVITY: Embankment work between the Jordan River and 7800 South.

TRAFFIC IMPACT: The Jordan River Parkway Trail will be closed from 7800 South to the Jordan River from Tuesday, June 8 through Tuesday, June 22.


Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

Track work, including switches, derails and signals, is moving forward on both sides of Cottonwood Street as crews work towards connecting the Mid-Jordan line with the Sandy-Salt Lake line. Lovendahl Yard track work continues as switches, pre-curved rail and other special track is installed.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.

Reblog this post [with Zemanta]

Saturday, May 29, 2010

Mid Jordan TRAX Construction Update

Gallivan Plaza TRAXImage by Steven Vance via Flickr



UTA Mid-Jordan TRAX Line Weekly Construction Update: May 28, 2010



* Redwood Road will be closed at the railroad crossing at approximately 8050 South in West Jordan from 10 pm Saturday, June 5 through 2 pm Sunday, June 6. Please use an alternate route.

*Winchester Street will be closed between the TRAX crossing and 300 West (Cottonwood Street) from May 24 through June 1. It will reopen Wednesday morning, June 2 at 5 am.

* The Jordan River Parkway Trail will be closed from 7800 South north to the UTA Jordan River bridge for approximately two weeks, from June 3 through June 18.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



Winchester Street Businesses Open During Construction

Although Winchester Street will be closed from May 24 through June 1, business access will still be maintained, and UTA encourages residents to continue to shop at businesses located on Winchester. West of the construction area, customers can access businesses via Winchester Street or 300 West (Cottonwood Street). East of the construction area, customers can access businesses using Winchester Street – the street is only closed at the TRAX crossing. The following Winchester Street businesses are still open during construction:

West Side Nursery

Winchester Gardens

Taylor D’Shaw Salon

Wood Connection Furniture

The Whistle Stop



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.

Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Work continues on the landscaping at the 5600 West station and Park & Ride. Crews are installing concrete bench foundations and sidewalks at the station platforms.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Track and grading/drainage work is moving forward in Old Bingham. OCS installation is essentially complete, and the station platform concrete work continues. The bus loop at the 4800 West station on Old Bingham Highway is nearly complete.


Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Construction of the Redwood Road rail crossing is in progress. The 2700 West Park & Ride lot will be paved this week. Concrete work is moving forward at the Bangerter and 2700 West station platforms, and foundations for OCS poles are being installed.





* NEW ACTIVITY: Rail installation at the Redwood Road rail crossing.

TRAFFIC IMPACT: Redwood Road will be closed from approximately 8020 South to 8150 South beginning Saturday night, June 5, at 10 pm. Redwood Road will reopen at 2 pm on Sunday, June 6.





* NEW ACTIVITY: Construction of the east half of the Redwood Road rail crossing.

TRAFFIC IMPACT: From 7 pm Friday, June 4 through 5 am Monday, June 7, all traffic on Redwood Road will be shifted to the west side of the street (the three northbound lanes) between 7600 South and 8600 South.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail will be closed between Thursday, June 3 and Friday, June 18 as crews begin widening the embankment of the rail right-of-way between 7800 South and the Jordan River. Embankment work is in progress between 1300 South and 7800 South. Work continues at the Jordan River bridge and the 700 West bridge.



* NEW ACTIVITY: Embankment work between the Jordan River and 7800 South.

TRAFFIC IMPACT: The Jordan River Parkway Trail will be closed from 7800 South to the Jordan River from Thursday, June 3 through Friday, June 18.



* NEW ACTIVITY: Concrete work at the 700 West bridge.

TRAFFIC IMPACT: Lane closures on 700 West at the railroad bridge (approximately 7400 South) on Tuesday, June 1.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

The new rail crossing at Winchester Street is scheduled for construction beginning May 24. Crews will reconstruct the existing northbound TRAX crossing as well as construct a new crossing for the Mid-Jordan line. The excavation for the new Fashion Place station platform should be complete next week. Track work, including switches, derails and signals, is progressing. Work is also moving forward in the Lovendahl Yard.



* NEW ACTIVITY: Construction of a new rail crossing at Winchester Street and renovation of the existing crossing.

TRAFFIC IMPACT: Winchester Street will be closed between the TRAX crossing and 300 West (Cottonwood Street) from May 24 through June 1.



* NEW ACTIVITY: Concrete work at the 7200 South TRAX bridge.

TRAFFIC IMPACT: 7200 South will have lane closures in place on Wednesday, June 2 and Thursday, June 3.


General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.




















Reblog this post [with Zemanta]

Saturday, May 22, 2010

Mid Jordan TRAX Construction Update

A Siemens LRV in service with UTA TRAX. The ba...Image via Wikipedia



UTA Mid-Jordan TRAX Line Weekly Construction Update: May 21, 2010



* Redwood Road between 7800 South and 9000 South will be subject to ongoing lane closures through late May. The full closure of Redwood Road has been postponed to later in June due to inclement weather this weekend.

*Winchester Street will be closed between the TRAX crossing and 300 West (Cottonwood Street) from May 24 through June 1.

* The Jordan River Parkway Trail will be closed from 7800 South north to the UTA Jordan River bridge for approximately two weeks, from June 3 through June 18.

* Please use caution when approaching railroad crossings throughout the project area. Crews and equipment travel on the rails frequently.



Winchester Street Businesses Open During Construction

Although Winchester Street will be closed from May 24 through June 1, business access will still be maintained, and UTA encourages residents to continue to shop at businesses located on Winchester. West of the construction area, customers can access businesses via Winchester Street or 300 West (Cottonwood Street). East of the construction area, customers can access businesses using Winchester Street – the street is only closed at the TRAX crossing. The following Winchester Street businesses are still open during construction:

West Side Nursery

Winchester Gardens

Taylor D’Shaw Salon

Wood Connection Furniture

The Whistle Stop



The Mid-Jordan TRAX line is a 10.6 mile light rail line that will connect the communities of Murray, Midvale, West Jordan and South Jordan with the existing Sandy/Salt Lake TRAX line. It runs from the existing TRAX line at 6400 South to approximately 7400 South, then turns west along the Bingham Branch of the Union Pacific Railroad. At 5600 West, the line turns south again and ends at the southern end of the Daybreak development. For construction purposes, the line has been segmented into five sections. The map below shows each section in a different color, beginning with Daybreak on the southwest end and ending with Cottonwood at the northeast end.



Daybreak Area

(This segment runs north through the Daybreak development to Old Bingham Highway at approximately 5600 West)



Work continues on the landscaping at the 5600 West station and Park & Ride. Finish work at the Daybreak South and Daybreak North station platforms is ongoing.

Old Bingham Area

(This segment runs parallel to the existing Union Pacific Railroad Bingham Branch line,

along the Old Bingham Highway from approximately 5600 West to the Bangerter Station, east of Bangerter Highway)

Track and grading/drainage work is moving forward in Old Bingham. OCS installation is essentially complete, and the station platform concrete work continues.


Sugar Factory Area

(This segment continues northeast along the UPRR Bingham Branch from approximately Bangerter
Highway to Gardner Village)

Construction of the Redwood Road rail crossing is in progress. The 2700 West Park & Ride lot will be paved this week. Concrete work is moving forward at the Bangerter and 2700 West station platforms, and foundations for OCS poles are being installed.



* NEW ACTIVITY: Construction of the east half of the Redwood Road rail crossing.

TRAFFIC IMPACT: The lane closure originally scheduled for this weekend (May 21-24) has been postponed.

Gardner Village Area

(This segment continues along the UPRR Bingham Branch northeast from Gardner Village to 700 West)

The Jordan River Parkway Trail will be closed between Thursday, June 3 and Friday, June 18 as crews begin widening the embankment of the rail right-of-way between 7800 South and the Jordan River. Embankment work is in progress between 1300 South and 7800 South. The concrete has been poured at the 7800 South bridge, and removal of the forms will be complete this week.



NEW ACTIVITY: Embankment work between the Jordan River and 7800 South.

TRAFFIC IMPACT: The Jordan River Parkway Trail will be closed from 7800 South to the Jordan River from Thursday, June 3 through Friday, June 18.



ACTIVITY: 7800 South bridge deck work.

TRAFFIC IMPACT: Lane shifts on 7800 South from Monday, May 17 through Tuesday, May 25.

Cottonwood Area

(This segment extends north from 700 West along the existing light rail alignment to its terminus at the 6400 South-

Fashion Place Station)

The new rail crossing at Winchester Street is scheduled for construction beginning May 24. Crews will reconstruct the existing northbound TRAX crossing as well as construct a new crossing for the Mid-Jordan line. The excavation for the new Fashion Place station platform should be complete next week. Track work, including switches, derails and signals, is progressing. Work is also moving forward in the Lovendahl Yard.



* NEW ACTIVITY: Construction of a new rail crossing at Winchester Street and renovation of the existing crossing

TRAFFIC IMPACT: Winchester Street will be closed between the TRAX crossing and 300 West (Cottonwood Street) from May 24 through June 1.

General Information

This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction is permitted to take place between 7 am to 7 pm Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 550-2211.



For More Information

Information is available to assist business and residential communities as well as commuters and stakeholders.

If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 550-2211 or e-mail midjordan@rideuta.com. You can also visit the UTA Web site at www.rideuta.com/projects/midjordanlightrail.