Mid-Jordan Light Rail TRAX Construction Update: September 25, 2008*
Please forward this information on to others that would be interested.
*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.
Construction on the
Sugar Factory Area
Activity: Utility work at the intersection of 3200 West and the railway. Traffic Impacts: 3200 West will be closed at the trackway between approximately 8600 South and
Activity: Construction of sound wall along right-of-way rail corridor between 2700 West and 3200 West began on September 2nd and will continue through the end of the month.
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Old Bingham Area
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Activity: Access to
Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: The Jordan River Parkway Trail will start a temporary detour near approximately 7500 South beginning September 25th. The trail will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly.
Activity: Construction on retaining walls at 7800 South near
· The eastbound lane on the south side of 7800 South will be closed as necessary starting on August 6th
· The westbound lane on the north side of 7800 South will be closed September 17th through October 1st
Activity: Construction activities on 1300 West at the railway have been postponed. Traffic Impacts: 1300 West will be not be closed at the railway from September 15th through September 22nd. There will be a notification when this work begins.
Activity: Grading and utility work is currently ongoing. Traffic Impacts: Shoulder closures with possible lane restrictions.
Activity: Construction on
· Northbound travel on
·
Activity: Construction on 300 West will begin on September 2nd and continue through November 2008. Traffic Impacts: 300 West will be closed to all traffic from 6300 South to
If you have any question or concerns regarding the project, please let me know.
Sarah Loughlin
Community Involvement Specialist
801-236-4783