West Valley TRAX Construction Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia



Welcome!



Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.





Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 West) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.



Current Construction:

· Overhead electric poles are being installed near West Valley City Hall and Constitution Boulevard.

· Crews continue working on the rail and ballast in the center of Constitution Boulevard.



Upcoming Construction:

· Concrete work will continue next week on grade landings, ramps and steps.

· Crews will continue working on irrigation and landscaping items near Market and Lehman Streets.



Traffic Impacts: There are minor lane restrictions along Constitution Boulevard; however, access is being maintained.



Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained throughout construction and we will coordinate with the E Center so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.



Current Construction:

· Work continues on the TRAX bridge approaches over I-215 on the south side of 3100 South.

· Crews are currently distributing rail and ballast on the south side of 3100 South between Maple Way and Decker Lake Drive.

· Crews are installing rail on the south side of the 3100 South and Decker Lake Drive intersection. Please obey speed limits.

· Work on the overhead electric system is taking place near Decker Lake Drive and 3100 South.



Upcoming Construction:

· Curbs and sidewalks are scheduled to be poured at 3100 South in the next few weeks.



Traffic Impacts:

· Traffic control is in place along 3100 South; however, access is being maintained.



Reach 3

Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees. We will continue to work with businesses to ensure access is maintained.



Current Construction:

· Track and station work continues in the center of Decker Lake Drive.

· Underground utility work continues along Research Way.

· We encourage motorists to please obey the posted speed limits.


Upcoming Construction:

· Temporary closure on Decker Lake Drive begins Monday, March 29 (see map to the right) – The northern portion of Decker Lake Drive between Research Way and approximately 2850 South will close for eight weeks for TRAX construction. This temporary closure will accelerate construction by months in this area. Access will be maintained by the detours listed to the right. We thank the businesses for their support and patience and encourage them to call the construction hotline if issues arise.

· Utility and road construction on Research Way between Decker Lake Drive and Redwood Road – this portion of road work is currently under construction as crews move utilities. The remainder of this work is scheduled to take place during spring 2010 – access will be maintained.

· Redwood Road track crossing – this portion of work is scheduled to take place during spring 2010 – access will be maintained.



Traffic Impacts: Currently, there are lane restrictions along Decker Lake Drive and Research Way, but access is being maintained.



Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties.



Current Construction:

· Significant work has been accomplished in the Chesterfield area. Crews continue to work on the rail and other items.





Reach 5

Reach Description: Reach 5 will include construction along 1070 West in the Chesterfield industrial area. This reach will include bridge structures over the Jordan River and 900 West.



Current Construction:

· Crews will resume work on 1070 West during the first part of April when crews form and pour curb, gutter, sidewalk and driveways. We will meet with businesses as we get closer to construction.

· Trenches are filled and temporarily paved for winter.

· Crews are working on the overhead wiring system.

· Work continues on the Jordan River bridge and the pedestrian and bike tunnel.



Traffic Impacts: There will be lane restrictions, although access will be maintained.



Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction:

· Progress continues on the TRAX bridge structures over 900 West at approximately 2200 South and also at the Union Pacific Railroad Roper Yard area.

· Work is also taking place on the overhead electric system.



Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction:

· Progress continues on the TRAX bridge approaches on either side of 600 West.

· Crews will begin drainage and continue track work throughout April.



Traffic Impacts: Currently there are no traffic impacts on Andy Avenue.




General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.