Sunday, July 26, 2009

West Valley TRAX Construction Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.


Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.



Current Construction:

· Significant progress continues on 2700 West as crews have prepared the roadway so traffic can be switched on July 23rd, to the east side of Constitution Boulevard.

· Progress continues on the station platform between West Valley City Hall and the Public Safety Building. Work is taking place on the embedded track and the parking lot.

· Third party utility work continues along both sides of Constitution Boulevard, and curb and gutter work is taking place in front of Valley Fair Mall.



Upcoming Construction:

· Work will take place on the tail tracks near the end of the line the last week of July.

· Crews will begin replacing current fencing along the west side of Constitution Boulevard with temporary fencing on July 27th. We will meet with each resident bordering the west side of Constitution Boulevard early next week to talk about this process.



Traffic Impacts: Traffic on 2700 West between 3100 South and 3500 South is operational on the west side of the road. There are also lane restrictions south of 3500 South; however, access is maintained at all times. Please be mindful of construction crews and obey posted speed limits.



Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.



Current Construction: Crews continue to build the TRAX bridge approach between Maple Way and I-215. Work also continues on the actual bridge crossing I-215. Utility work continues at the E Center.



Upcoming Construction:

· Nighttime construction is taking place on the TRAX bridge over I-215 on the south side of 3100 South. Work will begin at 7 p.m and last until 5 a.m. Noise impacts are anticipated to be minimal during nighttime work activities. Residents are encouraged to call the 24-hour hotline number at (888) 800-8854 if there are questions or concerns.



Traffic Impacts: Currently there are lane restrictions on 3100 South; however, access is being maintained.



Reach 3

Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis.



Current Construction: Crews have started work on the storm drain on the east side of the road. Preliminary utility work has also begun on Research Way near Redwood Road.



Upcoming Construction: On July 27th, Decker Lake Drive between 3100 South and Research Way will close for approximately four months for TRAX construction. Access to all businesses will be maintained via posted detours. After consulting with numerous businesses in this area, it was decided to temporarily close this road to lessen the amount of impact and allow this area to be completed in four months instead of ten months. Please feel free to contact any of the following people to find out more: Annie at (801) 808-6018; Kris at (801) 831-5991: or the project hotline at 888-800-8854. Thank you for your patience. Please see detour route below:


A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.







Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail.



Current Construction: Significant work has been accomplished in the Chesterfield area. Crews are currently preparing the trackway and have placed ties and rail in various areas throughout the reach. Rail has been installed at the Lester Street crossing between Claybourne Avenue and Southgate Avenue.



Upcoming Construction: Light poles are scheduled to be reinstalled at Lester Street in mid-July. Construction on the eastbound track will begin toward the end of July.



Traffic Impacts:

The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal has been paved but will remain closed until TRAX is completed in this area.





Reach 5

Reach Description: Reach 5 includes construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.



Current Construction: Storm drain work is scheduled to be completed toward the end of July. Work will begin on the east side water line on July 21st. Work is also being completed on the Jordan River TRAX bridge. Access is being maintained and we appreciate the businesses’ patience.



Upcoming Construction: After utility work is complete, crews will begin work on the curb, gutter and roadway on the west side of 1070 West, which should last until the end of the summer season. Once the west side of the roadway is completed, crews will then work on the east side of the roadway.



Traffic Impacts: As construction proceeds, there will be lane restrictions, although access will be maintained.





Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction: Significant progress continues on the TRAX bridge structures over the Roper Yard area near 2200 South and 600 West. Crews are also excavating the TRAX guideway just south of SR 201 between the Jordan River and 900 West.



Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.



Traffic Impacts: Not applicable.



Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction: Roadway construction is currently underway along Andy Avenue and is scheduled to be repaved by July 27th. We thank businesses for their support during this phase of construction.



Upcoming Construction: Roadway work will continue on Andy Avenue for the next week. Crews will then move to work on the waterway and slope protection under I-215.



Traffic Impacts: Bearcat at Andy Avenue is now permanently closed. Flaggers are on sight to direct traffic and access will be maintained during construction.




General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access is temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.





Reblog this post [with Zemanta]

Friday, July 03, 2009

West Valley TRAX Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.





Reach 1



Reach Description: Reach 1 is the area along Constitution Boulevard (2700 W.) from West Valley City Hall at 3600 S. extending north to 3100 S. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.



Current Construction:

· Progress continues on the station platform between West Valley City Hall and the Public Safety Building. Embedded track is scheduled to be installed beginning the first week of July.

· Third party utility work continues along both sides of Constitution Boulevard, and curb and gutter work is taking place in front of Valley Fair Mall.

· Crews continue to do roadwork on Constitution Boulevard between 3100 S. and 3500 S., and have completed the 16” waterline work.



Upcoming Construction:

· Traffic is scheduled to switch to the east side of Constitution Boulevard on July 22nd.

· Crews will begin replacing current fencing along the west side of Constitution Boulevard with temporary fencing on July 22nd. We will meet with each resident bordering the west side of Constitution Boulevard early next week to talk about this process.



Traffic Impacts: Traffic on 2700 W. between 3100 S. and 3500 S. is operational on the west side of the road. There are also lane restrictions south of 3500 S.; however, access is maintained at all times. Please be mindful of construction crews and obey posted speed limits.



Reach 2



Reach Description: Reach 2 is the area along 3100 S. from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 S. Access will be maintained throughout construction and we will work with the E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 S., it will operate on the south side of the roadway.



Current Construction: Crews continue to build the TRAX bridge approach between Maple Way and I-215. Work also continues on the bridge crossing I-215 south of 3100 S. Utility work also continues at the E Center.



Upcoming Construction:

· Nighttime construction is scheduled to take place on the TRAX bridge over I-215 on the south side of 3100 S. on July 6th. Work will begin at 7 p.m. and last until 5 a.m. Noise impacts are anticipated to be minimal during nighttime work activities. Residents are encouraged to call the 24-hour hotline number at (888) 800-8854 if there are questions or concerns.



Traffic Impacts: Currently, there are lane restrictions on 3100 S.; however, access is being maintained.



Reach 3



Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 S. to Research Way (2770 S.) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis. We will continue working with businesses to ensure access is maintained.



Current Construction: The west side of Decker Lake Drive is open and access is being maintained. Crews have started work on the storm drain on the east side of the road. Preliminary utility work has also begun on Research Way near Redwood Road.



Upcoming Construction: Foundations for the overhead wiring system are scheduled to be installed along Decker Lake Drive in approximately three weeks.



Traffic Impacts: There are lane restrictions on Decker Lake Drive; however, access is being maintained.



Reach 4



Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 S. and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties.



Current Construction: Significant work has been accomplished in the Chesterfield area. Crews are currently preparing the trackway and have placed ties and rail in various areas throughout the reach. Rail has been installed at the Lester Street crossing between Claybourne Avenue and Southgate Avenue.



Upcoming Construction: Paving is scheduled to take place today on Lester Street and the Crosstowne Trail. The trail will not re-open until construction is complete. We appreciate your patience as we work in this area.



Traffic Impacts:

· The Crosstowne Trail along 2770 S. just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will open again.





Reach 5



Reach Description: Reach 5 includes construction along 1070 W. in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 W.



Current Construction: Crews are scheduled to continue installing retaining walls on the east side of 1070 W. until the first week of July. Storm drain work is also scheduled to continue until the first week of July. Work is being completed on the Jordan River TRAX bridge. Access is being maintained and we appreciate the businesses’ patience.



Upcoming Construction: After utility work is complete, crews will begin working on the roadway on the west side of 1070 W. which should last until the end of the summer. Crews will then begin work on the east side of the roadway.



Traffic Impacts: As construction proceeds, there will be lane restrictions, although access will be maintained.





Reach 6



Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction: Significant progress continues on the TRAX bridge structures over the Roper Yard area near 2200 S. and 600 W. Crews are also excavating the TRAX guideway just south of SR 201 between the Jordan River and 900 W. Construction is also proceeding just east of 900 W. along the south side of SR 201.



Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.



Traffic Impacts: Not applicable.



Reach 7



Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction: Storm drain installation along Andy Avenue has been completed. Crews continue roadway construction at Andy Avenue and 400 W. This work is anticipated to be completed on July 18th. We thank businesses for their support during this phase of construction.



Upcoming Construction: Roadway work will continue on Andy Avenue for the next two weeks. Crews will then move to work on the waterway and slope protection under I-215.



Traffic Impacts: Bearcat at Andy Avenue is now permanently closed. Flaggers are on sight to direct traffic and access will be maintained during construction.


Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.



If you have further questions not answered by this report or any comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.

Reblog this post [with Zemanta]

Monday, June 29, 2009

West Valley TRAX Update

UTA TRAX Sandy train at the Gallivan Plaza sto...Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.




A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.





Reach 1



Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.



Current Construction:

· Progress continues on the station platform between West Valley City Hall and the Public Safety Building. Embedded track is scheduled to be installed beginning the first week of July.

· Third party utility work continues along both sides of Constitution Boulevard, and curb and gutter work is taking place in front of Valley Fair Mall.

· Crews continue to do roadwork on Constitution Boulevard between 3100 South and 3500 South and have completed the 16” waterline work.



Upcoming Construction:

· Traffic is scheduled to switch to the east side of Constitution Boulevard on July 12th.

· Crews will begin replacing current fencing along the west side of Constitution Boulevard with temporary fencing on July 13th. We will meet with each resident bordering the west side of Constitution Boulevard early next week to talk about this process.



Traffic Impacts: Traffic on 2700 West between 3100 South and 3500 South is operational on the west side of the road. There are also lane restrictions south of 3500 South; however, access is maintained. Please be mindful of construction crews and obey posted speed limits.



Reach 2



Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained throughout construction and we will work with the E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.



Current Construction: Crews continue to build the TRAX bridge approach between Maple Way and I-215. Work also continues on the actual bridge crossing I-215 south of 3100 South. And utility work also continues at the E Center.



Upcoming Construction:

· Nighttime construction is scheduled to take place on the TRAX bridge over I-215 on the south side of 3100 South from June 29th until July 31st. Work will begin at 7 p.m and last until 5 a.m. Noise impacts are anticipated to be minimal during nighttime work activities. Residents are encouraged to call the 24-hour hotline number at (888) 800-8854 if there are questions or concerns.



Traffic Impacts: Currently, there are lanes restrictions on 3100 South; however, access is being maintained.



Reach 3



Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. It includes many commercial office buildings with thousands of employees who access this area on a daily basis.



Current Construction: The west side of Decker Lake Drive is open and access is being maintained. Crews have started work on the storm drain on the east side of the road. Preliminary utility work has also begun on Research Way near Redwood Road.



Upcoming Construction: Utility work is scheduled to begin along Decker Lake Drive toward the end of June. Foundations for the overhead wiring system are also scheduled to be installed during the first week of July.



Traffic Impacts: There are lane restrictions on Decker Lake Drive; however, access is being maintained.



Reach 4



Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties throughout construction.



Current Construction: Significant work has been accomplished in the Chesterfield area. Crews are currently preparing the trackway and have placed ties and rail in various areas throughout the reach.



Upcoming Construction: Lester Street between Claybourne Avenue and Southgate Avenue is closed until July 2nd so rail can be installed. We appreciate the residents’ patience during this construction phase.



Traffic Impacts:

· The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will open again.





Reach 5



Reach Description: Reach 5 includes construction along 1070 West in the Chesterfield industrial area. This reach includes one bridge structure over the Jordan River and another over 900 West.



Current Construction: Crews are scheduled to continue installing retaining walls on the east side of 1070 West until the first week of July. Storm drain work is scheduled to continue until the first week of July. Work is also being completed on the Jordan River TRAX bridge. Access is being maintained and we appreciate the businesses’ patience.



Upcoming Construction: After utility work is complete in this reach, crews will begin working on the roadway on the west side of 1070 West, which should last until the end of the summer season. Once the west side of the roadway is completed, crews will then begin work on the east side of the roadway. Construction is anticipated to take place for the next several months.



Traffic Impacts: As construction proceeds, there will be lane restrictions, although access will be maintained.



Reach 6



Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction: Significant progress continues on the TRAX bridge structures over the Roper Yard area near 2200 South and 600 West. Crews are also excavating the TRAX guideway just south of SR 201 between the Jordan River and 900 West. Construction is also proceeding just east of 900 West along the south side of SR 201.



Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.



Traffic Impacts: Not applicable.



Reach 7



Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake and crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction: Storm drain installation along Andy Avenue has been completed. We thank businesses for their support.



Upcoming Construction: On Monday, June 29th, night construction will take place at the Andy Avenue and 400 West intersection. Work will begin at 7 p.m. and last until 9 a.m. A flagger will be used to move local traffic through the construction area. At this time, Bearcat Drive at Andy Avenue will close permanently and Andy Avenue will be reconstructed to accommodate work on the West Valley Line.



Traffic Impacts: Access will be maintained during construction.


General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.



If you have questions or any comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.




Reblog this post [with Zemanta]

Saturday, June 20, 2009

West Valley TRAX Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.


Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.

Current Construction:

· Crews continue to weld rail near the station platform in between West Valley City Hall and the Public Safety Building. Embedded track is scheduled to be installed beginning the first week of July.

· Market Street is scheduled to be restriped for traffic early next week.

· Third party utility work continues along both sides of Constitution Boulevard and curb and gutter work is taking place in front of Valley Fair Mall.

Upcoming Construction:

· Crews continue to pour curb and gutter on Constitution Boulevard between 3100 South and 3500 South. Traffic will be switched to the east side of Constitution Boulevard during the second week of July.

· The entrance to Constitution Boulevard at 3360 South is scheduled to open on June 22nd. We thank the residents for their patience during construction.

· Crews will begin replacing current fencing along the west side of Constitution Boulevard with temporary fencing the first week of July. We will meet with each resident bordering the west side of Constitution Boulevard early next week to talk about this process.

Traffic Impacts: Traffic on 2700 West between 3100 South and 3500 South is operational on the west side of the road. There are also lane restrictions south of 3500 South; however, access is being maintained. Please be mindful of construction crews and obey posted speed limits.

Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained and we will work with the E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.

Current Construction: Crews continue to build the TRAX bridge approach between Maple Way and I-215. Work also continues on the actual bridge crossing I-215 south of 3100 South. Utility work also continues at the E Center.

Upcoming Construction:

· Night work is scheduled to take place on the TRAX bridge over I-215 at various times throughout the next few weeks. Noise impacts are anticipated to be minimal during nighttime work activities. Residents are encouraged to call the 24-hour hotline number at (888) 800-8854 if there are questions or concerns.

Traffic Impacts: Currently there are lane restrictions on 3100 South; however, access is being maintained.

Reach 3

Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis. We will continually work with businesses to ensure access is maintained.

Current Construction: The west side of Decker Lake Drive is open and access is being maintained. Crews have started work on the storm drain on the east side of the road. Preliminary utility work has also begun on Research Way near Redwood Road.

Upcoming Construction: Utility work is scheduled to begin along Decker Lake Drive toward the end of June, along with installation of the foundations for the overhead wiring system.

Traffic Impacts: There are minor lane restrictions; however, access is being maintained.

Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties throughout construction.

Current Construction: Significant work has been accomplished in the Chesterfield area. Crews have installed a permanent wall along both sides of the Crosstowne Trail and are currently preparing the trackway and working on the traction power substation.

Upcoming Construction: Lester Street between Claybourne Avenue and Southgate Avenue is scheduled to temporarily close from June 23rd to July 2nd so rail can be installed in the roadway.

Traffic Impacts:

· The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will open again.


Reach 5

Reach Description: Reach 5 will include construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.

Current Construction: Crews are scheduled to continue installing retaining walls on the east side of 1070 West until the first week of July. Work is also being completed on the Jordan River TRAX bridge. Access is being maintained and we appreciate the businesses’ patience.

Upcoming Construction: Water line installation is scheduled to take place along 1070 West from June 25th through July 9th. After utility work is complete, crews will begin working on the roadway on the west side of 1070 West which should last until the end of the summer season. Once the west side of the roadway is completed, crews will then begin work on the east side of the roadway. Construction is anticipated to take place for the next several months.

Traffic Impacts: As construction proceeds, there will be lane restrictions, although access will be maintained.

Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.

Current Construction: Significant progress continues on the TRAX bridge structure over the Roper Yard area near 2200 South and 600 West. Construction is also proceeding just east of 900 West along the south side of SR 201.

Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.

Traffic Impacts: Not applicable.

Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.

Current Construction: Storm drain installation along Andy Avenue has been completed. We thank businesses for their support.

Upcoming Construction: Nighttime construction will begin at Andy Avenue and 400 West on June 29th. Crews will begin roadway excavation at this time. We will work with businesses in this area to maintain access and mitigate any issues that may arise.

Traffic Impacts: Access will be maintained during construction.

General Information

Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.

Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.

Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.

For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.

If you have further questions not answered by this report or any comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.

Please note that construction information provided is subject to change.

Reblog this post [with Zemanta]

Sunday, June 14, 2009

West Valley TRAX Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia

Construction progress continues on the West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in dark green on the north end.


A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.





Reach 1



Reach Description: Reach 1 is the area along Constitution Boulevard (2700 South) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained.



Current Construction:

· Crews continue work on the station platform in between West Valley City Hall and the Public Safety Building and are welding the rail.

· Roadway work continues on Market and Lehman Streets.

· Third party utility work continues along both sides of Constitution Boulevard, and curb and gutter work is taking place in front of Valley Fair Mall.

· Construction on the West Valley Library parking lot continues and is scheduled to be completed on Wednesday, June 17th.



Upcoming Construction:

Crews continue to pour curb and gutter on Constitution Boulevard between 3100 South and 3500 South. Traffic will be switched to the east side of Constitution Boulevard during the first week of July.
· The entrance to Constitution Boulevard at 3360 South will close for one week beginning June 15th. During this temporary closure, residents in the neighborhood east of Constitution Boulevard will be required to use Maple Way at 3100 South.

· Crews will begin replacing current fencing along the west side of Constitution Boulevard with temporary fencing the first week of July. We will meet with each resident with backyards bordering the west side of Constitution Boulevard early next week to talk about this process.



Traffic Impacts: Traffic on 2700 West between 3100 South and 3500 South is operational on the west side of the road. There are also lane restrictions south of 3500 South; however, access is maintained at all times. Please be mindful of construction crews and obey posted speed limits.



Reach 2



Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained and we will work with the E Center to coordinate our efforts so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.



Current Construction: Crews continue to build the TRAX bridge approach between Maple Way and I-215. Work also continues on the actual bridge crossing I-215 south of 3100 South, along with utility work at the E Center.



Upcoming Construction:

· Night work is currently taking place on the TRAX bridge over I-215. Noise impacts are anticipated to be minimal during this section of work and crews prepare to pour the concrete deck on the TRAX bridge.



Traffic Impacts: Currently there are lane restrictions on 3100 South; however, access is being maintained.



Reach 3



Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees who access this area on a daily basis. We will continually work with businesses to ensure access is maintained.



Current Construction: The west side of Decker Lake Drive is open. Crews have started work on the storm drain on the east side of the road. Preliminary utility work has also begun on Research Way near Redwood Road.



Upcoming Construction: Foundation work for the overhead wiring system is scheduled to begin along Decker Lake Drive for mid-June.



Traffic Impacts: There are minor lane restrictions; however, access is being maintained.



Reach 4



Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and proceeds along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties.



Current Construction: Significant work has been accomplished in the Chesterfield area. Crews have installed a permanent wall along both sides of the Crosstowne Trail, are preparing the trackway and working on the traction power substation.



Upcoming Construction: Rail installation and track construction is scheduled for mid-June.



Traffic Impacts:

· The Crosstowne Trail along 2770 South just east of Redwood Road to the Brighton Canal is currently closed. Once TRAX construction is completed, the trail will open again.





Reach 5



Reach Description: Reach 5 includes construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.



Current Construction: Crews are currently installing a storm drain and retaining walls on the east side of 1070 West. Work is also being completed on the Jordan River TRAX bridge. Access is being maintained and we appreciate the businesses’ patience.



Upcoming Construction: After utility work is complete, crews will begin working on the roadway on the west side of 1070 West, which should last until the end of the summer. Once the west side of the roadway is complete, crews will then begin work on the east side of the roadway.



Traffic Impacts: As construction proceeds, there will be lane restrictions, although access will be maintained.







Reach 6



Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place with the Union Pacific Railroad to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction: Significant progress continues on the TRAX bridge structure over the Roper Yard area near 2200 South and 600 West. Construction is also proceeding just east of 900 West along the south side of SR 201.



Upcoming Construction: Coordination will continue with the Union Pacific Railroad to install utilities and bridge structures.



Traffic Impacts: Not applicable.





Reach 7



Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction: Storm drain installation along Andy Avenue has been completed. We thank businesses for their support.



Upcoming Construction: Construction will begin at Andy Avenue and 400 West on June 27th. Crews will begin roadway excavation at this time. We will work with businesses to maintain access and mitigate any issues that may arise.



Traffic Impacts: Access will be maintained during construction.

General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities, as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.



Please note that construction information provided is subject to change.