Construction is progressing on UTA’s FrontRunner South Provo to Salt Lake Commuter Rail line.
Below is the FrontRunner South construction update for September 25 – October 1. Please note that construction information is subject to change.
FrontRunner South construction began in 2008 and is more than 50 percent complete. The FrontRunner South line will be complete and operational by 2015. Please visit UTA’s FrontRunner South Webpage to learn more about the project. To view more FrontRunner South construction photos, please visit www.flickr.com/rideuta.
UTA would like to remind Utah County express bus riders that service from the 2100 N. Lehi park and ride lot has been discontinued. Express bus service is now available from the Lehi FrontRunner park and ride lot at 2821 W. Executive Parkway, as well as the American Fork FrontRunner park and ride lot at 782 W. 200 S. Because the Lehi park and ride lot will be opened in phases, more stalls are currently available at the American Fork park and ride lot. Street parking is available near the Lehi park and ride lot.
Area 16 — Downtown Salt Lake City to 4500 South (Murray)
Construction Activity:
Crews will relocate power poles at 1300 South and clear and grub the corridor and continue waterline work between 1700 South and Mill Creek. North of 3900 South crews will be excavating for a retaining wall and south of 3900 South crews will be constructing a wall. At the Central Avenue bridge, crews will pour concrete for the bridge’s back and wing walls and finish shear keys. They will also install signal power service in the area. Between Central Avenue and 4500 South crews will continue track way embankment and at the 4500 South bridge crews will continue retaining wall construction for the bridge’s south abutment and clean up and grade the slopes at the bridge.
Traffic Impacts:
There will be truck traffic on Central Avenue Monday through Friday.
The eastbound right lane will be closed on 4500 South Monday through Friday.
Salt Lake Central Station:
Station complete.
Area 15 — 4500 South (Murray) to Wasatch Street/8000 South (Midvale)
Construction Activity:
Between 4500 South and 4800 South crews will restore street light power and install signal power service. At the 5300 South bridge crews will install deck plates and at Vine Street crews will excavate for a crash wall. Between 5300 South and 5900 South, crews will embank the track way and install storm drain, and between 5900 South and I-215, crews will continue waterline work and also clear and grub the corridor. At the 7200 South bridge, crews will place surcharge.
Traffic Impacts:
The 4500 South Frontage Road is currently closed at the tracks for bridge work through September.
There will be the following impacts on 5300 South this week:
· Westbound left lane closure, Monday
· Eastbound right lane closure, Tuesday through Thursday
There will be truck traffic at 5900 South all week.
Murray Station:
There are no construction activities to report.
Area 14 — Wasatch Street/8000 South (Midvale) to 14600 South (Bluffdale)
General Information:
Considerable progress has been made on the flyover structure west of Salt Lake Community College’s Miller Campus at 9800 South. The 642-foot flyover bridge features a 40-foot-high bridge deck that will allow FrontRunner to travel from the east to the west side of Union Pacific Railroad’s track way. The flyover structure’s approaches consist of keystone block MSE walls filled entirely with lightweight fill to minimize settlement.
Construction Activity:
Crews continue wall excavation north of 9000 South and soil nail installation south of 9000 South. Crews will be installing fencing on top of the retaining wall between 9120 South and 9400 South and at the 9120 South bridge crews will build forms and pour concrete for the south abutment. At the 10600 South bridge crews will install shoring at the south abutment and continue work on the north abutment walls. Crews will continue mass excavation between South Jordan Gateway and 11400 South and sheet pile shoring installation south of 11400 South. At the Bangerter Highway bridge, crews will continue work on the shear keys.
Traffic Impacts:
The eastbound right lane will be closed on 9120 South Monday through Thursday.
There will be a northbound lane closure on South Jordan Gateway at approximately 10300 South for truck traffic.
There will be a full closure of all eastbound lanes on 10600 South between Saturday, October 2 at 10:00 p.m. and Monday, October 4 at 5:00 a.m.
There will be the following impacts on Bangerter Highway this week:
· Westbound right lane closure, Tuesday
· Westbound left lane closure, Wednesday
There will be truck traffic with flaggers on 14600 South Monday through Friday.
South Jordan Station:
Lightweight fill for the job is being stored at the station site. There are no construction activities to report.
Draper Future Station:
There are no construction activities to report.
Area 13 — 14600 South (Bluffdale) to Thanksgiving Point (Lehi)
Construction Activity:
Crews will be repairing a wall near 14600 South and continuing canal realignment work south of 14600 South. Now that Union Pacific traffic has been shifted onto the new bridge constructed at the Jordan River, crews are retrofitting the old UP bridge for UTA’s use. This week, crews will place girders and build deck forms. Crews will be installing permanent fencing north of Thanksgiving Point and along the Golf Course.
Traffic Impacts:
There are currently no impacts to motorists in this area.
Area 12 — Thanksgiving Point (Lehi) to Main Street (American Fork)
General Information:
Crews are currently constructing two major bridges in Lehi at 2300 West and 2100 North. The 2300 West bridge will allow FrontRunner to travel over Lehi City’s future 2300 West road project and the 2100 North bridge will span UDOT’s future Mountain View Corridor, 2100 North roadway. The 2100 North bridge will feature abutments on each end of the bridge and five center piers.
Construction Activity:
In the Cranberry Farms area, crews will be working on a retaining wall at approximately 2400 North, staging ties and distributing rail and installing duct for fiber at the 2300 West and 2100 North bridges. Crews will also install deck plates at the 2300 West bridge and grout and patch and install bolsters at the 2100 North bridge. Between 2100 North and 1500 North crews will stage ties and distribute rail, and between 1220 North and 900 North crews will clear and grub the corridor, build slopes and ditches, prepare the sub grade and install signal power.
Crews will construct crossing upgrades this week at the Main Street crossing in downtown Lehi. This work will include signal and track work, the installation of concrete medians and signs, road striping, and asphalt replacement. Crews will be working 24 hours a day at this crossing in order to reopen it as soon as possible to the travelling public.
On Center Street, crews will be installing concrete medians near the crossing, and southeast of 300 East in Lehi, crews will finish prepping the sub grade prep and place sub ballast.
Traffic Impacts:
There will be truck traffic on 500 West in Lehi near the tracks all week.
The Main Street crossing in Lehi will be closed for crossing upgrade work Monday, September 27 through Sunday, October 3. Traffic will be detoured on 300 West, 500 North and 500 West.
There will be lane restrictions on Center Street in Lehi on Monday.
Lehi Station:
A portion of the Lehi Station Park and Ride Lot is now open for public use.
At the pedestrian tunnel, crews will continue work on the tunnel floor and will also trench for a drain connection. At the Park and Ride Lot, crews continue preparing a new section of the parking lot for paving.
Area 11 — Main Street (American Fork) to University Parkway (Orem)
Construction Activity:
Crews will be installing fiber between 7350 West in American Fork and University Parkway in Orem. In American Fork, crews will continue work to relocate a power pole and phone pedestal at 1500 South. Between 400 North in Vineyard and Geneva Road in Orem, crews will install permanent fencing.
Traffic Impacts:
There will be lane restrictions on 1500 South in American Fork Monday through Wednesday.
American Fork Station:
A portion of the American Fork Station Park and Ride Lot is now open for public use.
There are no construction activities to report.
Vineyard Future Station:
There are no construction activities to report.
Orem Station:
There are no construction activities to report.
Area 10 — University Parkway (Orem) to Center Street (Provo)
General Information:
Significant progress has been made in Area 10 along the Union Pacific Railroad corridor between University Parkway in Orem and Freedom Boulevard in Provo. Crews have prepared a path for FrontRunner by grading and clearing the right-of-way and relocating water lines. Drainage and irrigation installations are generally complete in this area, and main line earthwork has been finalized from University Parkway to 2000 South in Orem and from the Provo River bridge to 500 West in Provo. At-grade crossing improvements have also been completed in Provo at 2000 North, 2800 West, 1680 North, 820 North, Draper Lane, 900 West, 700 West, 500 West and Freedom Boulevard.
Construction Activity:
Crews will surface, line and dress the track between University Parkway in Orem and 2000 North in Provo and install fiber between University Parkway and 1680 North. North of 820 North in Provo, crews will be re-grading ditches, and between 700 West and 900 South crews will de-stress track and remove poles.
Traffic Impacts:
There are currently no impacts to motorists in this area.
Provo Station:
Crews will install vapor barrier and tie rebar for the low deck at the Provo Station.
Thanks again for your interest in the FrontRunner South project. If you have construction-related questions,
please call our 24-hour construction hotline at 1-888-800-8854.