Saturday, May 22, 2010

West Valley TRAX Construction Update

UTA TRAX and FrontRunner at Night 1Image via Wikipedia



Welcome!



Construction progress continues on the UTA West Valley TRAX Line. To keep business and traffic impacts to a minimum, this five-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in light green on the south end of the project and ending with Reach 7 in light green on the east end of the project.

A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (888) 800-8854.





Reach 1

Reach Description: Reach 1 is the area along Constitution Boulevard (2700 West) from West Valley City Hall at 3600 South extending north to 3100 South. This area includes both large and small businesses, as well as many residents. Access to all businesses and residences will be maintained throughout construction.



Current Construction:

· Crews continue concrete work on ramps, steps and sidewalks near West Valley City Hall.

· Overhead wire work continues near West Valley City Hall.

· Crews are forming and pouring the platform at West Valley City Hall.

· Crews are constructing the driveway entrance to businesses just north of 3500 South on Constitution Boulevard. Access will be maintained as this driveway is constructed half at a time and is scheduled to be completed in approximately one week.



Upcoming Construction:

· Crews will begin forming and pouring the station platform near West Valley City Hall the third week of May.



Traffic Impacts: There are minor lane restrictions along Constitution Boulevard; however, access is being maintained.



Reach 2

Reach Description: Reach 2 is the area along 3100 South from Constitution Boulevard to Decker Lake Drive. The E Center and a few other businesses are located in this reach, as well as residents on either side of 3100 South. Access will be maintained throughout construction and we will coordinate with the E Center so you can continue to visit the great events they have to offer. When TRAX is completed along 3100 South, it will operate on the south side of the roadway.



Current Construction:

· Work continues on the TRAX bridge approaches over I-215 on the south side of 3100 South.

· Work on the overhead electric system is taking place near Decker Lake Drive and 3100 South.

· Crews are working on curbs and sidewalks near 3100 South and Decker Lake Drive.



Traffic Impacts:

· Traffic control is in place along 3100 South; however, access is being maintained.



Reach 3

Reach Description: Reach 3 is the area along Decker Lake Drive from 3100 South to Research Way (2770 South) and running east to Redwood Road. This area includes many commercial office buildings with thousands of employees. We will work with businesses to ensure access is maintained.



Current Construction:

· Progress continues the northern portion of Decker Lake Drive just south of Research Way. This temporary closure is anticipated to last until the first part of June. Access will be maintained to all businesses. We thank businesses for their support and patience during construction. Please see the map for detour information.


Track and station work continues in the center of Decker Lake Drive.

· Ballast, curb and gutter work continues along the east side of Decker Lake Drive.

· Underground utility work continues along Research Way.

· We encourage motorists to obey the posted speed limits.

· Decker Lake Drive is expected to be reopened to north/south traffic the first week of June.



Traffic Impacts: Currently, there are lane restrictions along Decker Lake Drive and Research Way, but access is being maintained.

Reach 4

Reach Description: Reach 4 runs through the Chesterfield residential area along 2770 South and along the Decker Lake Canal and the Crosstowne Trail. We will work with residents to ensure a safe working environment that provides access to their properties throughout construction.



Current Construction:

· Significant work has been accomplished in the Chesterfield area. Crews continue to work on the rail and other items in this area.





Reach 5

Reach Description: Reach 5 will include construction along 1070 West in the Chesterfield industrial area. This reach will include one bridge structure over the Jordan River and another over 900 West.



Current Construction:

· Work continues on the west side of 1070 West. Crews will form and pour curb, gutter, sidewalk and driveways. It is anticipated that the west side of 1070 West will be completed in the upcoming week.

· Crews are currently excavating the east side of 1070 West. This work will include new curb, gutter, sidewalk, and driveways. Access to all businesses will be maintained. We thank the businesses for their patience during construction.

· Work also continues on the Jordan River Bridge and tunnel.



Traffic Impacts: There are various lane restrictions on 1070 West; however, access to businesses is being maintained.



Reach 6

Reach Description: Reach 6 runs through the Union Pacific Railroad’s Roper Yard area. Although there are no businesses and residents, extensive coordination will take place to ensure that freight deliveries and other train travel is maintained. Reach 6 includes plans for an extensive bridging system that will enable TRAX to operate over other train traffic.



Current Construction:

· Progress continues on the TRAX bridge structures over 900 West at approximately 2200 South and also at the Union Pacific Railroad Roper Yard area.

· Work is also taking place on the overhead electric system.



Reach 7

Reach Description: Reach 7 is the area where the West Valley Line will connect with the current north/south TRAX Line. Construction will take place along Andy Avenue in South Salt Lake. Crews will closely coordinate activities with businesses to ensure access is maintained.



Current Construction:

· Drainage and track work continues between 300 West and 600 West.

· Crews are also preparing to tie in to the current north/south TRAX Line. This work is scheduled to be completed during the Memorial Day weekend to avoid disruption to riders.



Traffic Impacts: Currently there are no traffic impacts on Andy Avenue.




General Information



Access during Construction

UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.



Construction Hours

Construction on the project is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.



Construction Tours

If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.



For More Information

Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.



If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail tcamp@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com.