Mid-Jordan Light Rail TRAX Construction Update: July 23, 2009*Please forward this information on to others that would be interested.
*This schedule is subject to change due to weather, materials issues, or unanticipated utility conflicts.
Bangerter Bridge
UPDATED Activity: Crews will be performing work on the Bangerter Highway overpass at approximately 8700 South. Traffic Impacts: Two right southbound lanes of Bangerter Highway will be closed 8/1 (Saturday) and two left northbound lanes will be closed on 8/2 (Sunday) to accommodate handrail installation. The median will remain closed through mid-August.
Sugar Factory Area
Activity: Please be aware that flagging operations will be taking place intermittently through July at 2700 West near the tracks to accommodate construction vehicles; please follow flagger’s instructions.
Activity: Please be aware that flagging operations will be taking place intermittently through July at 3200 West near the tracks to accommodate construction vehicles; please follow flagger’s instructions.
Old Bingham Area
Activity: Work will be taking place on 4000 West at the trackway located near Old Bingham Highway. Traffic Impacts: 4000 West will be closed at the trackway from 7/27 (Monday) to 8/16 (Sunday). Old Bingham Highway will also be closed at 4000 West during these dates. Please use 4800 West or Bangerter Highway as alternate routes.
Activity: Utility work. Traffic Impacts: On Old Bingham Highway just west of the Bangerter Highway overpass, traffic will be restricted to one lane with flagging operations during working hours (7 am to 5 pm) and lane shifts during non-working hours through 7/26 (Sunday).
Activity: Eastbound shoulder closure on Old Bingham Highway west of Bangerter Highway through July.
Activity: Please be aware that flagging operations will be taking place intermittently through 2009 at 4800 West near Old Bingham Highway to accommodate construction vehicles. Please note that left turns are allowed from the through lane; please follow flagger’s instructions.
Activity: Please be aware that flagging operations will be taking place intermittently through 2009 at Wasatch Meadows Drive near Old Bingham Highway to accommodate construction vehicles. Please note that left turns are allowed from the through lane; please follow flagger’s instructions.
Activity: Please be aware that flagging operations will be taking place intermittently through 2009 at 5200 West and the railway to accommodate construction vehicles.
Activity: Utility work is currently ongoing. Traffic Impacts: Shoulder work with possible lane restrictions.
Gardner Village Area
NEW Activity: Bridge work at 7200 South and approximately 600 West. Traffic Impacts: The leftmost lane of 7200 South in each direction will be closed 8/1 (Saturday) and 8/2 (Sunday) to accommodate pile driving work.
UPDATED Activity: Utility and bridge work. Crews will be working at 700 West near approximately 7400 South. Traffic Impacts: The northbound right lane of 700 West will be closed from 8/6 (Thursday) through 8/14 (Friday) to accommodate drainage work. The southbound shoulder of 700 West will be closed in this immediate area through mid-August.
UPDATED Activity: Construction on the Jordan River TRAX bridge. Traffic Impacts: The Jordan River Parkway Trail near approximately 7500 South will be intermittently detoured through August 2009. Please be aware that the detour does cross a live railway track, and as such, the detour will be closed daily from 7:00 p.m. to 7:00 a.m. when freight is actively running on the track. Please plan accordingly. UPDATE (7/23/09): The trail will be detoured from 7/31 (Friday) through 8/7 (Friday) to accommodate bridge work.
Activity: Access to Gardner Village from the Jordan River Parkway Trail is closed until August 2009.
Cottonwood Area
NEW Activity: Bridge work at 7200 South and approximately 600 West. Traffic Impacts: South sidewalk will be closed in the immediate area through 8/3.
UPDATED Activity: Bridge work on Winchester Street and approximately 400 West. Traffic Impacts: Traffic is also subject to intermittent flagging operations through 7/31 to accommodate construction vehicles. Please plan accordingly and use detour routes as posted.
If you have any construction-related questions or concerns, please call the construction hotline at (888) 550-2211.
If you have any questions or concerns regarding the project, please let me know.
Sarah Loughlin
Community Involvement Specialist
Utah Transit Authority
801-236-4783
sloughlin@rideuta.com