Construction has begun on the UTA Airport TRAX Line. This six-mile project has been separated into seven construction “reaches,” or segments, for management and planning purposes. The map below shows each construction reach in a different color, starting with Reach 1 in dark red by the airport and ending with Reach 7 in light green on the east end of the project.
A description of what is happening in each area is listed below. If you need further construction information, please call our toll-free 24-hour hotline at (800) 888-8854.
Reach 1
Reach Description: Reach 1 is the area that extends from Terminal One at the Salt Lake City International Airport to the surplus canal bridge just north of the Wingpointe Golf Course.
Upcoming Construction: Heavier construction is anticipated during Summer 2009.
Traffic Impacts: Currently there are no traffic impacts. Access will be maintained throughout the construction project.
Reach 2
Reach Description: Reach 2 extends from the surplus canal bridge just north of the Wingpointe Golf Course along the fence line on North Temple Drive to 2400 West.
Upcoming Construction: Heavier construction is anticipated Fall 2009.
Traffic Impacts: Currently there are no traffic impacts. Access will be maintained throughout the construction project.
Reach 3
Reach Description: Reach 3 extends from 2400 West along North Temple Drive to I-215. This is the reach where TRAX will move from the side of the road to the center of North Temple.
Current Construction: Currently utility work is taking place in the center of North Temple on either side of the I-215 overpass. Crews are relocating a utility line so it will not run underneath the TRAX guideway. To accommodate utility work on North Temple, west bound traffic near I-215 has been diverted to old North Temple down to 2200 West for the next few weeks. Access to all businesses will be maintained and flaggers will be on site to direct traffic.
Upcoming Construction: Heavy construction will begin during Spring 2009.
Traffic Impacts: There are lane restrictions near the I-215 overpass on North Temple, but access is being maintained.
Reach 4
Reach Description: Reach 4 extends from I-215 to just past Redwood Road on North Temple. TRAX will be center running and will include a station located at approximately 1950 West North Temple. Access to the many businesses and governmental organizations will be maintained.
Current Construction: Utility work extends just east of the I-215 overpass on North Temple. Heavier construction is not anticipated until later this fall.
Upcoming Construction:
Preliminary utility work is scheduled for the Redwood Road and North Temple intersection at the beginning of May. There will be lane restrictions, but traffic will be maintained at all times. Heavier construction is anticipated beginning Fall 2009.
Traffic Impacts: Currently there are no traffic impacts.
Reach 5
Reach Description: Reach 5 extends from just east of Redwood Road on North Temple to the Jordan River. TRAX will be center running and includes a station at 1500 West North Temple. Access to the many businesses and office complexes will be maintained.
Current Construction: Currently construction is not taking place.
Upcoming Construction: Construction is anticipated to begin during Autumn 2009.
Traffic Impacts: Currently there are not traffic impacts.
Reach 6
Reach Description: Reach 6 extends from the Jordan River to I-15 along North Temple. TRAX will be center running and will include two stations located at approximately 1500 West and 1100 West North Temple. Access to the many businesses and the State Fairpark will be maintained.
Current Construction: Crews should finish the preliminary portion of utility work at the 800 West intersection by next week.
Upcoming Construction: Heavy construction is anticipated during Spring 2010.
Traffic Impacts: There are lane restrictions on North Temple that extend from 800 West to just east of 600 West. Access is being maintained. We appreciate the businesses and public’s patience.
Reach 7
Reach Description: Reach 7 is the area where the Airport Line will connect with the current North/South TRAX Line at the Arena Station.
This reach extends from I-15 to 400 West along North Temple and turns south on 400 West proceeding to South Temple. Access to offices and the Gateway will be maintained throughout the construction project.
Current Construction: Preliminary utility work is currently taking place at approximately 641 West North Temple. This work is scheduled for approximately two weeks.
Upcoming Construction: After the utility work is completed at 641 West, preliminary work is expected to begin for approximately three weeks at the 900 West and North Temple intersection.
Traffic Impacts: There are currently no traffic impacts.
General Information
Access during Construction
UTA is committed to maintaining 24-hour access to all of the businesses and residences along the construction corridor. We will coordinate with businesses in cases where access may be temporarily limited.
Construction Hours
Construction is permitted to take place between 7 a.m. to 7 p.m. Monday through Saturday. Additionally, specific activities may require different working hours depending upon the conditions and will be coordinated with city officials.
Construction Tours
If you are interested in learning more about the construction project, please call our toll-free 24-hour hotline at (888) 800-8854.
For More Information
Timely and helpful information is available to assist business and residential communities as well as commuters and stakeholders.
If you have questions or comments regarding the project, please contact our toll-free 24-hour hotline at (888) 800-8854 or e-mail thope@rideuta.com. You can also visit UTA’s Web site at www.rideuta.com
Please note that construction information provided is subject to change.